Failure to Comply with Contract Leaves No Additional Insured Coverage
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIndemnity obligations and additional insured coverage were at issue in Strauss Painting, Inc. v. Mt. Hawley Ins. Co., 2014 N.Y. LEXIS 3347 (N.Y. Nov. 24, 2014).
Strauss Painting, Inc. (Strauss) contracted with the Metropolitan Opera Association, Inc. (the Met) to strip and repaint the rooftop steel carriage track for the opera house's automated window-washing equipment. The contract provided that Strauss would indemnify and hold the Met harmless. Exhibit D to the contract set forth three types of insurance that Strauss was to procure: (1) workers' compensation; (2) owners and contractors protective liability (OCP); and (3) comprehensive general liability. The OCP policy was to add the Met as an additional insured. Strauss failed to obtain the OCP policy.
At the time it contracted with the Met, Strauss had a CGL policy issued by Mt. Hawley. The policy's additional insured endorsement (ICO form CG 20 33 07 04) stated that "an insured" included "any organization for whom Strauss is performing operations when Strauss and such organization have agreed in writing that such organization be added as an additional insured."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Three Construction Workers Injured at Former GM Plant
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Linden, New Jersey, three construction workers were injured “when they were apparently struck by steel girders while working at the former General Motors site” police told NJ.com.
Mayor Richard Gerbounka stated that the “[s]ix struts that would support the deck or ceiling of a warehouse collapsed.” He also mentioned that the city “has been trying to redevelop the former General Motors site for years, but has run into several obstacles, including lawsuits from nearby businesses opposed to retail construction.”
Several construction vehicles were “nearly buried under” debris and “[a]t least one I-beam girder and several decking struts—all metal—remain across several heavy construction vehicles,” NJ.com reported. The owner of the vehicles stated “he was told that workers were standing around the vehicles preparing to start their day when high winds knocked down at least one I-beam and several metal decking struts.”
In another article published late afternoon on March 26th, NJ.com reported that “high winds” were the cause of the accident. “The federal Occupational Safety and Health Administration is investigating the accident and all work at the site has been suspended pending the investigation,” according to the article. “Officials said OSHA inspectors had been at the scene once before, but declined to give details because of a continuing investigation.”
Read the full story, NJ.com AM...
Read the full story, NJ.com PM... Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Protects California Policyholders for Intentional Acts of Employees
July 02, 2018 —
William S. Bennett – Saxe Doernberger & Vita P.C.Recently, the California Supreme Court ruled that liability insurers are obligated to cover negligent supervision, hiring, and retention claims against employers resulting from the intentional acts of their employees.
The case, Liberty Surplus Insurance v. Ledesma & Meyer Construction, case no. S236765 (2018), involved an insurance coverage dispute between a construction company, Ledesma & Meyer Construction (“L&M”), and its insurers, Liberty Insurance Underwriters, Inc. (“Liberty”) and Liberty Surplus Insurance Corp (“Liberty Surplus”). Liberty was L&M’s primary insurer, while Liberty Surplus had the excess policy. L&M had contracted with the San Bernardino Unified School District to renovate a school building while the school was still in session. In a separate action, another court found that an L&M employee sexually assaulted a 13-year-old student while working at the project.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Flawed Welding Faulted in Mexico City Subway Collapse
October 04, 2021 —
Jim Parsons - Engineering News-RecordFaulty structural welds have been blamed for the deadly May 3 collapse of an elevated section of Mexico City’s Line 12 subway, according to a report issued Sept. 7 by Norwegian risk management firm DNV.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Do We Really Want Courts Deciding if Our Construction Contracts are Fair?
March 19, 2015 —
Christopher G. Hill – Construction Law MusingsAs I posted recently, the Virginia General Assembly has passed, and I can see no reason why the governor won’t sign, a bill that would
essentially invalidate preemptive contractual waivers of lien rights as they relate to subcontractors and material suppliers. It does not apply to General Contractors, but it is a step in what many (including those attorneys that represent subcontractors and suppliers) believe is the right direction.
Of course, as soon as I posted last week, my friend and colleague
Scott Wolfe (@scottwolfejr) commented on that post and then
gave his two cents worth at his Zlien blog. The gist of the comments here at Musings and the post over at his blog was essentially that these contractual provisions were inherently unfair and therefore should be abolished because of both a relative disparity in leverage between the Owner or GC and the Subcontractor when it comes to negotiations and the fact that subcontractors often don’t read their contracts or
discuss them with a construction attorney prior to signing them. I hear this first of his arguments often when I am reviewing a contract after the fact and a client or potential client acts surprised that a provision will be enforced and the courts of the Commonwealth of Virginia will actually enforce them. As to Scott’s second reason, I have always warned here at Musings that
you should read your contracts carefully because they will be the law of your business relationship in the future.
The first of his two points is more interesting and in some ways more easily supported. However, where we are speaking of contracts between businesses where both sides are bound by the terms of the contract, it begs the question of whether in seeking to make contracts more “fair” we could add a layer of uncertainty that could cause more problems than it solves. Do we really want courts stepping in after the fact to renegotiate the terms of a deal that was struck months or possibly years before because one judge believes that the deal was too one sided? Do we really need such “Monday morning quarterbacking?” Is one person’s idea of “fair” better than another’s when both parties to the contract had the full ability to read, negotiate and possibly reject the deal long ago? Personally, I think that the answer to these questions is, in all but the most egregious cases or where the legislatures have stepped in adding certainty (whether to the good or bad), “No.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Notice of Claim Sufficient to Invoke Coverage
August 06, 2014 —
Tred R. Eyerly – Insurance Law HawaiiIndirect notice to the insurer was sufficient to trigger coverage for the additional insured under a liability policy. Spoleta Constr., LLC v. Aspen Ins. UK Ltd., 2014 N.Y. App. Div. LEXIS 5174 (N.Y. App. Div. July 11, 2014).
An employee of the subcontractor was injured at the construction project on October 20, 2008. The general contractor was named as an additional insured on the subcontractor's CGL policy with Aspen. Under the subcontract, the subcontractor also agreed to defend and indemnify the general contractor for all claims arising out of the subcontractor's work.
The general contractor did not receive notice of the accident until late December 2009 in a letter from the injured employee's attorney. On January 27, 2010, the general contractor's liability carrier sent a letter to the subcontractor giving notice of the employee's claim and requesting that the subcontractor put its carrier on notice. On February 9, 2010, the subcontractor sent to Aspen a claim form with the January 2010 letter attached.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractors Liable For Their Subcontractor’s Failure To Pay Its Employees’ Wages And Benefits
November 01, 2022 —
Edward O. Pacer & David J. Scriven-Young - ConsensusDocsRecently, Illinois Governor J.B. Pritzker signed two House Bills that amend the Illinois Wage Payment & Collections Act, 820 ILCS 115 et. seq. (“Wage Act”), to provide greater protection for individuals working in the construction trades against wage theft in a defined class of projects. Pursuant to this new law, every general contractor, construction manager, or “primary contractor,” working on the projects included in the Bill’s purview will be liable for wages that have not been paid by a subcontractor or lower-tier subcontractor on any contract entered into after July 1, 2022, together with unpaid fringe benefits plus attorneys’ fees and costs that are incurred by the employee in bringing an action under the Wage Act. This new wage theft law follows several other states that have considered and passed similar legislation.
These amendments to the Wage Act apply to a primary contractor engaged in “erection, construction, alteration, or repair of a building structure, or other private work.” However, there are important limitations to the amendment’s applicability. The amendment does not apply to projects under contract with state or local government, or to general contractors that are parties to a collective bargaining agreement on a project where the work is being performed. Additionally, the amendment does not apply to primary contractors who are doing work with a value of less than $20,000, or work that involves only the altering or repairing of an existing single-family dwelling or single residential unit in a multi-unit building.
Reprinted courtesy of
Edward O. Pacer, Peckar & Abramson, P.C. (ConsensusDocs) and
David J. Scriven-Young, Peckar & Abramson, P.C. (ConsensusDocs)
Mr. Pacer may be contacted at epacer@pecklaw.com
Mr. Scriven-Young may be contacted at dscriven-young@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of