Oregon agreement to procure insurance, anti-indemnity statute, and self-insured retention
March 05, 2011 —
CDCoverage.comIn Continental Casualty Ins. Co. v. Zurich American Ins. Co., No. 09-35484 (9th Cir. Oct. 28, 2010), general contractor TCR was sued by an employee of subcontractor Safeway for bodily injuries suffered while working on the project. In the subcontract, Safeway agreed to procure primary insurance providing coverage for TCR for liability arising out of Safeway’s negligence. Safeway’s CGL policy included a self-insured retention that had to be satisfied before the insurer had a duty to defend. TCR filed suit against Safeway alleging that
Read the full story...Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
A Few Green Building Notes
December 02, 2019 —
Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
The first of these is the foreclosure of the Chapel Hill, North Carolina Greenbridge project. This project is well documented at my friend Doug Reiser’s (@douglasreiser) Builders Counsel blog so I won’t further discuss the details here. However, the question that Doug asks is a good one, i. e. were the “green” elements of the project to blame?
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Connecticut Court Clarifies a Limit on Payment Bond Claims for Public Projects
May 15, 2023 —
Bill Wilson - Construction Law ZoneIn All Seasons Landscaping, Inc. v. Travelers Casualty & Surety Co., No. DBD-CV21-6039074-S, 2022 WL 1135703 (Conn. Super. Ct. April 4, 2022) the plaintiff, a subcontractor on a state project, commenced a lawsuit against the surety who issued a payment bond on the project two years after the subcontractor last performed any original contract work on the project. The defendant surety moved to dismiss the action based on the one-year statute of limitation in Connecticut General Statute § 49-42. The plaintiff countered that it complied with that deadline because it also performed warranty inspection work after the contract was completed and within the limitation period in section 49-42. The issue of whether warranty work or minor corrective work can extend the limitations period in section 49-42 had not previously been addressed by a Connecticut court.
Section 49-42(b) governs the limitation period on payment bond claims on public projects. It provides in relevant part that “no … suit may be commenced after the expiration of one year after the last date that materials were supplied or any work was performed by the claimant.” Section 49-42 provides no guidance on what “materials were supplied or any work was performed” by the claimant means, nor is there any direct appellate-level authority in Connecticut on this issue. What is clear under well-established law in Connecticut is that the time limit within which suit on a payment bond must be commenced under Section 49-42 is not only a statute of limitation but a jurisdictional requirement establishing a condition precedent to maintenance of the action and such limit is strictly enforced. If a plaintiff cannot prove its suit was initiated within this time constraint, the matter will be dismissed by the court as untimely.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
New Jersey Construction Worker Sentenced for Home Repair Fraud
October 22, 2013 —
CDJ STAFFMarcin Gradziel, who formerly worked for a construction company in Camden County, New Jersey, has been sentenced to seven years in state prison for insurance fraud. Mr. Gradziel admitted to creating fraudulent property damage claims, which he did for Precision Network Solutions, which did business as Precision Builders.
Mr. Gradziel and others went through neighborhoods telling residents that their roofs or siding were damaged by hail and that they could get their homes repaired at no cost. Mr. Gradziel would then return to create damage before the inspectors arrived. Another employee, Dominik Sadowski, previously plead guilty, as did Precision Builders. The firm paid out $68,720 in restitution and is now out of business.
Read the court decisionRead the full story...Reprinted courtesy of
Washington Court of Appeals Divisions Clash Over Interpretations of the Statute of Repose
August 07, 2023 —
Masaki Yamada & Ryanne Mathisen - Ahlers Cressman & Sleight PLLCThe construction statute of repose under RCW 4.16.310 bars any claims arising from construction, design, or engineering of any improvement upon real property that has not accrued within six years after substantial completion or termination of services, whichever is later, even if the injury has not yet occurred.
On June 20, 2023, Division One of the Washington Court of Appeals (Div. I) published its decision in
Welch v. Air & Liquid Systems severely criticizing and rejecting the statute of repose reasoning contained in
Maxwell v. Atlantic Richfield Co., 15 Wn. App. 2d 569, 476 P.3d 645 (2020), a Division Two (Div. II) opinion.
More than a mere difference of opinion, the courts in Welch and Maxwell reached different results as to whether claims asserted against Brand Insulations, Inc. were barred by the statute of repose despite involving (i) the same procedural posture, both appeals from summary judgment decisions; (ii) the same facility, Atlantic Richfield Corporation’s (ARCO) petroleum refinery at Cherry Point in Ferndale; (iii) the same activity of installation of asbestos laden insulation on pipes; (iv) the same type of injury, mesothelioma; and (v) application of the same test set forth in Condit v. Lewis Refrigeration Co., 101 Wn.2d 106, 676 P.2d 466 (1984).
Reprinted courtesy of
Masaki Yamada, Ahlers Cressman & Sleight PLLC and
Ryanne Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Yamada may be contacted at masaki.yamada@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
BWB&O’s Motion for Summary Judgment is Granted in a Premises Liability Matter
November 05, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Newport Beach Partner Courtney Serrato and Associate Joseph Real on Prevailing on a Motion for Summary Judgment for their Client!
Plaintiff filed a lawsuit alleging negligence and premises liability against BWB&O’s client, a general contractor of a multi-level construction project. Plaintiff was injured after a fall at the construction project and filed suit against BWB&O’s client and another subcontractor.
Plaintiff alleged BWB&O’s client was negligent and was responsible for causing Plaintiff’s fall. BWB&O filed a Motion for Summary Judgment arguing under the Privette Doctrine and its progeny, it neither owed nor breached any duty to Plaintiff and that no exception to the doctrine applied. Under the Privette Doctrine, when a person or entity hires an independent contractor to provide work or services, and one of the contractor’s employees is injured on the job, the hirer is generally not liable to the employee.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
New York vs. Miami: The $50 Million Penthouse Battle From Zaha Hadid
October 28, 2015 —
James Tarmy – BloombergThe Anglo-Iraqi starchitect Zaha Hadid has designed just two residential buildings in the U.S., one in New York (520 West 28th Street in the Chelsea Gallery District next to the High Line) and one in Miami (One Thousand Museum, next to PAMM and overlooking Biscayne Bay). Both have yet to be completed and both, as it happens, have penthouses priced in the region of $50 million.
Two trophy properties by a Pritzker Prize-winning architect and two almost identical price tags? (The Miami penthouse clocks in at a mere $49 million, the New York penthouse an even $50 million.) It’s practically begging for a head-to-head comparison.
Read the court decisionRead the full story...Reprinted courtesy of
James Tarmy, Bloomberg
Insurers Need only Prove that Other Coverage Exists for Construction Defect Claims
August 27, 2013 —
CDJ STAFFWriting on the Sheppard Mullin web site, Scott Hennigh looks at the implications of the 2012 California case Axis Surplus Insurance. A condominium complex was covered by two insurance policies, covering different time periods. During a construction defect claim, one insurer argued that the claim was not covered. The other insurer settled and sued that both needed to contribute to the settlement. The court held that when multiple insurers are in conflict, the burden to prove that coverage does not exist lies solely on the party claiming it.