National Infrastructure Leaders Visit Dallas' Able Pump Station to Tout Benefits of Water Infrastructure Investment
September 25, 2023 —
American Society of Civil EngineersDALLAS, TX. — An award-winning pump station in south downtown Dallas that protects residents from the Trinity River today was showcased by the
national Engineering and Public Works Roadshow as an example of how infrastructure investment can improve the resilience of a community, protect residents, and encourage economic growth.
The Able Pump Station in downtown Dallas, Texas won awards from both the American Council of Engineering Companies and the American Society of Civil Engineers since its completion in 2019 and has been credited with providing 100-year flood protection to approximately three square miles of high-profile land that was historically vulnerable to severe flooding events from the Trinity River.
The Engineering and Public Works Roadshow is a joint project of the
American Council of Engineering Companies (ACEC), the
American Public Works Association (APWA), and the
American Society of Civil Engineers (ASCE).
The properties adjacent to the previous Able sump complex had experienced frequent flooding. The sump complex included nine separate and interconnected ponds that store stormwater, as well as two existing pump stations, constructed in the 1930s and 1950s, with a combined capacity of 220,000 gallons per minute. To help prevent the loss of life as a result of flooding, the City of Dallas hired HDR to design the new Able Pump Station, which increases the pumping capacity nearly fourfold, to 875,000 gallons per minute. It also lowers the 100-year flood elevation from 399.0 to a design elevation of 392.5 feet.
As the federal government continues to implement this monumental legislation, the second year of the Bipartisan Infrastructure Law will not be fully realized without an expanded and robust workforce. It is imperative that students nationwide are educated on the rewarding careers of civil engineering and public works so that these professions have the necessary staffing to complete transformative projects.
Read the court decisionRead the full story...Reprinted courtesy of
Defend Trade Secret Act of 2016–-Federalizing Trade Secret Law
October 07, 2016 —
Erin M. Stines and Reed Cahill - Ahlers & Cressman PLLCThe Defend Trade Secret Act of 2016 (DTSA) was signed into law on May 11, 2016, and became effective immediately. The DTSA allows an owner of a trade secret to sue in federal court for trade secret misappropriation. Previously, only state law governed civil misappropriation of trade secrets. While the DTSA largely mirrors the current state of the law under the Uniform Trade Secrets Act (UTSA), adopted by 48 states, including Washington,[1] there are some additions found in the new law.
The DTSA imposes the same three-year statute of limitations and authorizes remedies similar to those provided under the UTSA. The DTSA also offers new forms of relief, including a provision permitting ex parte seizure orders (that is, without a hearing or response from the opposing party) to prevent further misappropriation of the trade secret. The DTSA further provides for a new definition of trade secret. The UTSA's definition of a trade secret is a “formula, pattern, compilation, program, device, method, technique, or process.” Under the DTSA, the definition of a “trade secret” is broadened to include “all forms and types of financial, business, scientific, technical, economic, or engineering information...whether tangible or intangible...” [2]
Read the court decisionRead the full story...Reprinted courtesy of
Erin M. Stines & Reed Cahill, Ahlers & Cressman PLLCMs. Stines may be contacted at
erin.stines@ac-lawyers.com
Incorrect Information Provided on Insurance Application Defeats Claim for Coverage
July 31, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit affirmed the district court's finding of no duty to defend or indemnify because of an answer on the insured's application for insurance. Snell v. United Specialty Ins. Co., 2024 U.S. App. 12733 (11th Cir. May 28, 2024).
Snell was hired by a family, the Westons, to turn an above ground trampoline into a ground level trampoline. This involved various tasks like tree pruning and removal, installation of shrubs, trees, and sod, and setting up a sprinkler irrigation system. The trampoline aspect of the project involved site work to make a place for the trampoline and assembly and installation of the trampoline. The site work included excavation of a pit, installation of a drain and drainage sand, excavation of a trench to install a drainage pipe, installation of the drainage pipe and of a drain pump, construction of concrete block retainer walls and installation of a wood cap on the retainer walls. Then, Snell unboxed the trampoline, assembled it, and lowered it into the pit.
A few years later, a visitor to the Weston home sued the Westons for injuries to his daughter suffered on the trampoline. The complaint alleged the daughter was injured when she "fell off of the trampoline and struck her face on the wooden board" surrounding the tramline. The complaint was later amended to add Snell as a defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Maryland Finally set to Diagnose an Allocation Method for Progressive Injuries
February 18, 2020 —
William S. Bennett - Saxe Doernberger & Vita, P.C.Maryland’s highest court recently heard arguments regarding the proper method of allocation of the covered damages from a slowly progressing asbestos injury amongst insurance policies in place over a period of years. Rossello v. Zurich American Insurance Company, Case No. 2436 (Md. 2019). The court may also be forced to determine what the proper trigger of coverage is for latent bodily injury claims, although the plaintiff has not framed the issue in that manner.
In Rossello, the plaintiff, Patrick Rossello, worked for a period of years for the now-defunct Lloyd E. Mitchell, Inc. (“Mitchell”), a construction company operating until 1976. In 1974 he was exposed to and inhaled asbestos fibers. He was ultimately diagnosed in 2013 with malignant mesothelioma as a result of that exposure. Rossello obtained a judgment for approximately $2,700,000 against Mitchell and secured the right to pursue its insurance. As relevant to this dispute, Mitchell carried liability insurance policies, which provide coverage for asbestos related claims, from 1974 to 1977.
Rossello seeks to hold Zurich, as successor to Maryland Casualty Company, accountable for the full value of his award, based on the 1974 policy. Although this contention actually implicates two separate issues, plaintiff’s counsel passed over the initial trigger of coverage issue and focused instead on the issue of allocation of coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Seattle Condos, Close to Waterfront, Construction Defects Included
February 11, 2013 —
CDJ STAFFThere's a cluster of eight condominium projects in Seattle, some within easy walking distance of each other, that are either in construction defect lawsuits, arbitration, or mediation. Jeff Reynolds, contributing a Seattle PI.com reader blog, notes that as Seattle condo projects have neared the end of the four-year warranty period, condo boards are being targeted by attorneys. Reynolds writes that "once [the attorneys] are hired by the associations, they retain specialists that test for any and all construction defects with the building envelope."
The problem that Reynolds sees is that that "major lending institutions stay away from condos with lawsuits." And so homeowners dealing with construction defects have apartments they can't sell to anyone who might want to use financing. This tightens Seattle's already limited inventory, leading to both frustrated sellers and frustrated buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Suffolk Stands Down After Consecutive Serious Boston Site Injuries
May 23, 2022 —
Scott Van Voorhis - Engineering News-RecordAfter two serious safety incidents in consecutive days, the Boston-area’s largest contractor voluntarily issued a safety stand down on all projects in Boston through May 6.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Randy Maniloff Recognized by U.S. News – Best Lawyers® as a "Lawyer of the Year"
October 14, 2019 —
Randy Maniloff - White and Williams LLPCongratulations to Randy Maniloff, Counsel in the Insurance Coverage and Bad Faith Group, who was named the U.S. News – Best Lawyers® 2020 Insurance Law “Lawyer of the Year” in Philadelphia. Randy was recognized by his peers for his professional abilities in this area. "Lawyer of the Year" recognitions are awarded to individual lawyers with extremely high overall peer-feedback for a specific practice area and geographic location.
Randy concentrates his practice in the representation of insurers in coverage disputes over primary and excess obligations under a host of policies, including general liability and various professional liability policies. He has significant experience in coverage matters involving additional insured and contractual indemnity issues.
His practice also includes an academic side. He is an adjunct professor of Insurance at Temple University Beasley School of Law and the co-author of “General Liability Insurance Coverage – Key Issues in Every State” (4th edition), a nearly 1,000 page reference book that provides 50-state surveys on 20 critical liability coverage issues.
Read the court decisionRead the full story...Reprinted courtesy of
Randy Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
A Landlord’s Guide to California’s New Statewide Rent Control Laws
May 18, 2020 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogApplicability of California’s Rent Control Laws: California Civil Code Sections 1946.2 and 1947.12 took effect on January 1, 2020, and implement statewide rent control in California for most residential properties. The rent control laws, however, do not apply to a rental property that was issued a certificate of occupancy in the last 15 years. (Civ. Code §§ 1947.12(d)(4), 1946.2(e)(7)). The statutes also do not apply to most single-family residences, provided that (a) the owner is not a real estate investment trust, a corporation, or a limited liability company where one of the members is a corporation, and (b) the required statutory language is included in the lease agreement for tenancies commencing or renewing on or after July 1, 2020. (Civ. Code §§ 1947.12(d)(5), 1946.2(e)(8)).
Annual Increases Permitted Under California’s Rent Control Laws: Commencing on January 1, 2020, unless otherwise permitted by California law, a Landlord cannot increase the gross rental rate for a rental unit over a continuous 12-month period more than the change in the regional cost of living index where the property is located plus 5%, and gross rental rate increases are subject to a maximum cap of 10% over a continuous 12-month period regardless of the change in the cost of living index. (Civ. Code § 1947.12(a)(1)). The gross rental rate is determined using the lowest rental amount charged in any month in the immediately preceding 12 months. (Id.) Any incentives, discounts, concessions, or credits are not taken into account. (Id.) Even if a rent increase does not exceed the amount permitted under the statute, a Landlord is prohibited from increasing rent more than twice in any continuous 12-month period. (Civ. Code § 1947.12(a)(2)).
Retroactive Applicability of Restrictions on Rent Increases: Although the statute took effect on January 1, 2020, the statute retroactively applies to all rent increases that occurred on or after March 15, 2019. (Civ. Code § 1947.12(h)(1)). If a landlord increased the rent amount more than the amount permitted under California Civil Code Section 1947.12(a)(1) after March 15, 2019, and prior to January 1, 2020, the rent amount on January 1, 2020, is reduced to the amount of the rent on March 15, 2019, plus the maximum permissible increase under California Civil Code Section 1947.12(a)(1). (Civ. Code § 1947.12(h)(2)). The Landlord does not have to refund the tenant any rent payments that were in excess of the permissible rent increase that the tenant made prior to January 1, 2020. (Id.)
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at
caddy@swlaw.com