'Taylor Swift Is an Economic Phenomenon': CE's Q1 2024 Economic Update and Forecast
April 29, 2024 —
Grace Calengor - Construction ExecutiveOn March 27, Construction Executive presented its "2024 Q1 Economic Update and Forecast," hosted by ABC Chief Economist Anirban Basu. If you've attended previous versions of this webinar, you're familiar with Basu’s pragmatic approach to the economics of the construction industry and his penchant for predicting recession. But this quarter, he opted for an almost-optimistic approach and hinted at walking back his thoughts on recession. Read the most quotable moments, new poll results and top takeaways from the presentation below.
POLL RESULTS: Q1 2024 vs. Q4 2023 Poll 1: Which of these is the leading challenge for your company today?
Supply chain and/or materials issues
Skills/worker shortage
Insufficient demand for construction services
Availability of financing for projects/project work
None of the above
December 2023 | March 2024 |
10% |
7% |
57% |
60% |
11% |
11% |
19% |
17% |
3% |
6% |
Reprinted courtesy of Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Court Adopts Continuous Trigger for Construction Defect Claims
November 15, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe New Jersey Superior Court, Appellate Division, adopted the continuous trigger for establishing which insurers were on the risk for construction defect claims. Air Master & Cooling, Inc. v. Selective Ins. Co. of Am., 2017 N.J. Super. LEXIS 144 (N.J. Super. Ct., App. Div. Oct. 10, 2017).
The insured, Air Master, worked as a subcontractor on the construction of a condominium building. Air Master performed HVAC work in the building between November 2005 and April 2008. Air Master's work consisted of installing condenser units on rails on the building's roof, and also HVAC devices within each individual unit.
Starting in early 2008, some of the unit owners began to notice water infiltration and damage in their windows, ceilings, and other portions of their units. On April 29, 2010, an expert consultant, Jersey Infrared Consultants, performed a moisture survey of the roof for water damage. A report identified 111 spots on the roof damaged by moisture from water infiltration. The report noted it was impossible to determine when moisture infiltration occurred. The expert recommended that these damaged areas of the roof be removed and replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Scope of Alaska’s Dump Lien Statute Substantially Reduced For Natural Gas Contractors
March 16, 2020 —
Trevor Lane - Ahlers Cressman & Sleight PLLCIn All American Oilfield, LLC v. Cook Inlet Energy, LLC,[1] the Supreme Court of Alaska clarified and substantially reduced a natural gas contractor’s ability to secure a preferred lien for its contribution to a natural gas well.
Alaska’s dump lien statute (AS § 34.35.140) authorizes a laborer to claim a lien for the amount owed for their labor in the production of a “dump or mass” of “extracted, hoisted and raised” matter from a mine. While Alaska’s dump lien statute is one of three Alaskan statutes allowing laborers to attach liens to mines, mining equipment or minerals,[2] the dump lien statute is unique because it is prior and preferred over other liens, increasing the laborer’s chance of being paid in a bankruptcy proceeding.
Attaching a lien to a “dump or mass” of hard-rock minerals piled outside a mine or oil stored in a tank is relatively straightforward. However, natural gas is typically left in its natural reservoir until removed by a pipeline that carries the gas to a location far from the mine. Natural gas is not extracted and stored in a “dump or mass” like other minerals, and until August 2019, controversy existed over how—or if—the dump lien statute could be used by natural gas contractors.
Read the court decisionRead the full story...Reprinted courtesy of
Trevor Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
trevor.lane@acslawyers.com
Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Creative Avenue for Judgment Creditor to Collect a Judgment
October 27, 2016 —
David Adelstein – Florida Construction Legal UpdatesI have a judgment against another entity. Now what? I want to briefly talk about this “now what?” in the context of the recent decision in MYD Marine Distributor, Inc. v. International Paint, Ltd., 41 Fla. L. Weekly D2364a (Fla. 4th DCA 2016). Although this case is not a construction case, it poses an interesting issue for any entity that has a judgment entered against it (known as the judgment debtor) while it is contemporaneously the plaintiff and pursuing monetary damages in an unrelated case or cases. This case also presents an avenue for any judgment creditor to pursue in the event other post-judgment collection efforts are unsuccessful.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Construction Litigation Roundup: “Sudden Death”
October 17, 2023 —
Daniel Lund III - LexologyIt’s not football, though. Rather, just when you thought it was safe in Louisiana to wait to file a garden-variety construction contract payment claim, an appellate court slams the door on it – applying a statute of “repose” to your claim.
“Personal actions” – such as an action on contract – are generally subject in Louisiana to a 10-year “liberative prescription,” the applicable statute of limitations pursuant to Louisiana Civil Code article 3499.
Like some other states, Louisiana has a statute of “repose” – imposing “peremption” rather than prescription for claims having to do with construction projects – limiting those claims (generally speaking) to five years post-completion. Like other statutes of “repose,” Louisiana Revised Statute 9:2772 provides that claims on construction projects may not be filed after five years, a duration which is not subject to interruption or extension.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Toronto Skyscraper With $1.2 Billion of Debt Has Been Put in Receivership
November 16, 2023 —
Ari Altstedter - BloombergA landmark condominium project in one of Toronto’s ritziest neighborhoods has been put into receivership after construction delays and cost overruns.
Construction of the 85-story tower will be taken over by a court-appointed receiver after its owners, developer Sam Mizrahi and investor Jenny Coco, defaulted on part of the project’s nearly C$1.7 billion in debt ($1.2 billion), according to a Wednesday order from the Ontario Superior Court of Justice.
Two funds run by South Korea-based IGIS Asset Management Co. applied for the receivership. Another IGIS fund will extend at least another C$315 million to continue work on the project, court documents said.
Read the court decisionRead the full story...Reprinted courtesy of
Ari Altstedter, Bloomberg