Appraisal Panel Can Determine Causation of Loss under Ohio Law
February 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured's motion to compel an appraisal that would include a determination of causation of the loss. Eagle Highland Owners Association v. State Farm Fire and Casualty Co., 2023 U.S. Dist. LEXIS 220937 (S.D. Ohio Dec. 12, 2023).
Plaintiff argued its property suffered wind and hail damage from a storm on June 18, 2021. A claim was submitted to State Farm. State Farm's investigation determined the loss to be $0.00. Plaintiff's investigator determined the loss to be $586,647.08 in repair costs.
State Farm opposed appraisal because, in its view, the damage arose from a loss in 2019, not from the June 18, 2021 storm. Plaintiff submitted a loss claim in 2019 for damage that State Farm alleged was exactly the same as the damage alleged in the loss claim for the June 18, 2021 storm. Therefore, State Farm did not view the matter as a dispute over an amount of loss, but rather over whether a loss even occurred on June 18, 2021.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
White House’s New Draft Guidance Limiting NEPA Review of Greenhouse Gas Impacts Is Not So New or Limiting
September 09, 2019 —
Norman F. Carlin & Eric Moorman - Gravel2Gavel Construction & Real Estate Law BlogOn June 21, 2019, the White House Council on Environmental Quality (CEQ) issued draft guidance clarifying the treatment of greenhouse gas (GHG) emissions in environmental impact reviews of federal projects under the National Environmental Policy Act (NEPA). Those wishing to comment on the draft must submit comments within 30 days after it is published in the Federal Register.
The draft guidance is part of the Trump Administration’s continuing efforts to streamline the permitting and environmental review process for infrastructure and energy projects. It replaces NEPA guidance on climate impacts issued in 2016 by the Obama administration, which was rescinded by President Trump’s Executive Order 13783 early in 2017. Although some initial reports suggest that the new draft guidance significantly pulls back from the Obama administration’s approach, on closer comparison it does not depart that much from the major recommendations of the rescinded guidance.
In general, NEPA requires federal agencies proposing to undertake, approve or fund a major federal action to evaluate its environmental impacts, including both direct and reasonably foreseeable indirect effects; to consider alternatives and mitigation; and to discuss cumulative impacts resulting from the incremental effects of the project when added to those of other past, present, and reasonably foreseeable future projects. The new draft and the rescinded 2016 guidance contain similar recommendations regarding an agency’s obligations to consider indirect and cumulative GHG impacts, as well as on the use of cost-benefit analysis and the contentious Social Cost of Carbon (SCC) metric.
Reprinted courtesy of
Norman F. Carlin, Pillsbury and
Eric Moorman, Pillsbury
Mr. Carlin may be contacted at norman.carlin@pillsburylaw.com
Mr. Moorman may be contacted at eric.moorman@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Upholds Prevailing Wage Statute
August 19, 2024 —
Ahlers Cressman & Sleight PLLCHistorically, the prevailing wage was calculated by averaging the wages within a certain industry and county. However, in 2018 the Washington Legislature amended the statute so that the prevailing wage would be assessed based on the highest wage set by collective bargaining agreements in the county. The amendment (RCW 39.12.015(3)) reads as follows:
(3)(a)…the industrial statistician shall establish the prevailing rate of wage by adopting the hourly wage, usual benefits, and overtime paid for the geographic jurisdiction established in collective bargaining agreements…
(b) For trades and occupations in which there are no collective bargaining agreements in the county, the industrial statistician shall establish the prevailing rate of wage by…conducting wage and hour surveys.
So, for example, if union engineers bargain for a wage, that is the wage all engineers in the county must be paid on public projects. The legislature passed this law for the sake of efficiency because it took significant resources for the Industrial Statistician to compute the prevailing wage for every trade and every county, but the law has significant knock-on effects.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Insurance Law Client Alert: California Appeals Court Refuses to Apply Professional Services Exclusion to Products-Completed Operations Loss
March 19, 2014 —
Valerie A. Moore and Chris Kendrick - Haight Brown & Bonesteel LLPIn North Counties Engineering v. State Farm (No. A133713, filed 3/13/14), State Farm insured an engineering company under CGL insurance that had a professional services exclusion and included products-completed operations (PCO) coverage. The owner of the engineering company, NCE, contracted with a winery to construct a dam and associated works. Also on the project was the owner's son, who had his own construction company, NCD. There were multiple contracts, both oral and written, variously naming one company or the other. The evidence later showed that the father performed hands-on work for the project.
After completion, the winery was sued over sediment and erosion caused by the dam. State Farm denied coverage on the ground that the professional services exclusion applied, as well as a mistaken belief that the policy had no PCO coverage. State Farm then changed its position and agreed to defend, but only going forward. The insured sued State Farm over past defense fees, alleging breach of contract and bad faith. The case went to trial and after testimony detailing State Farm's claim handling, the trial judge granted a nonsuit, finding that the professional services exclusion barred all coverage:
"[I]f you look at the pleadings, the legal pleadings and the contracts, the NCE role is, as the engineering company, the support company, and that company was overseeing the [sic] NCD to make sure that whatever they did was done right.... NCE is the expert on the job, the professional providing professional services, design and construction, and also overseeing the work of NCD, the son’s business, which is doing more of the physical activity.... That takes professional expertise and I think all of what Mr. Akerstrom did was professional.... It was this professional work, and not 'something incidental to their professional involvement' that gave rise to the underlying actions. In this situation, it’s not a malpractice or E and O policy. It’s a business policy, which has good benefits, but is subject to the professional services exclusion."
Reprinted courtesy of
Valerie A. Moore and
Chris Kendrick of Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nader Eghtesad v. State Farm General Insurance Company
September 28, 2020 —
Michael Velladao - Lewis BrisboisIn Eghtesad v. State Farm Gen. Ins. Co., 51 Cal.App.5th 406 (June 29, 2020), the California Court of Appeal reversed the trial court’s entry of judgment in favor of State Farm General Insurance Company (“State Farm”) based on an order sustaining a demurrer without leave to amend regarding a complaint filed by Nader Eghtesad. Mr. Eghtesad, representing himself, filed a form complaint checking a box for breach of contract. The complaint alleged two paragraphs contending that State Farm had acted in bad faith and concealed benefits due under a policy issued to a former tenant who rented space in a building owned by Eghtesad. Eghtesad was an additional insured under the tenant’s policy. In that regard, the building was damaged during the time that the building was rented and Eghtesad tendered a claim under the State Farm policy contending that he was an additional insured pursuant to the terms of the lease with the tenant. According to Eghtesad, State Farm advised him that he could only make a claim for slander against the former tenant and that coverage was not afforded for his property damage claim.
After Eghtesad filed his form complaint, State Farm demurred to the complaint and argued that it did not state facts supporting a cause of action for breach of contract. Ultimately, the trial court agreed with State Farm and entered an order sustaining the demurrer without leave to amend, such that a judgment was entered in State Farm’s favor. Due to health reasons, Eghtesad was never able to file an opposition to the demurrer, despite two extensions of time provided by the trial court intended to allow Eghtesad time to retain counsel and to recover from injuries sustained as a result of an automobile accident.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Construction Defect Class Action Lawsuit Alleges National Cover-up of Pipe Defects
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFTwo Miami condominium associations have filed suit “concerning defective fire sprinkler systems and a national cover up over a significant life safety issue in multi-unit condominiums in Florida and across the country.”
The attorneys representing the class action lawsuit, Gonzalez, Montoya, Siegfried, Sobel, and Hale, “believe that the problem is nationwide and that monetary damages arising from the claims will exceed $1 billion,” a press release by Colson Hicks Eidson stated. “The 56-count lawsuit filed against a dozen manufacturers, suppliers and distributors seeks compensatory, incidental and consequential damages.”
According to CBS Miami, “The suit claims the companies knowingly used [a] chemical that caused cracks and leaks in pipes that affected the water pressure in sprinkler systems.”
Plaintiff attorneys claim that the cost to repair each building is estimated at between $50 to $100 million each.
Read the full story, Press Release...
Read the full story, CBS Miami... Read the court decisionRead the full story...Reprinted courtesy of
The Biggest Trials Coming to Courts Around the World in 2021
January 04, 2021 —
Anthony Lin - BloombergSeveral former world leaders, a Hong Kong media tycoon, the CEO of Theranos and Jeffrey Epstein’s confidante — all are scheduled to have their day in court next year.
With vaccinations heralding a return to normalcy, the next year should see courtrooms around the world coming back to life. Ghislaine Maxwell, China critic Jimmy Lai and Samsung heir Jay Y. Lee are among those facing high-profile criminal cases in 2021. Some proceedings, including the fraud trial of Theranos founder Elizabeth Holmes, are resuming after being postponed by the pandemic. Another delayed case, UBS’s appeal of its $4.9 billion French government tax penalty, is among the many that will be heard by higher-level and supreme courts.
There are also a number of cases against former world leaders, including France’s Nicolas Sarkozy, Malaysia’s Najib Razak and South Africa’s Jacob Zuma. One of the most tantalizing questions will be whether a certain former U.S. president could find himself facing trial as well.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Lin, Bloomberg
Big Data Meets Big Green: Data Centers and Carbon Removal Compete for Zero-Emission Energy
October 15, 2024 —
Robert A. James, Sidney L. Fowler & Ashleigh Myers - Gravel2Gavel Construction & Real Estate Law BlogArtificial intelligence, data centers, carbon removal and zero-emission power may sound like a winning line (plus the Free Space) on a 2024 Buzzword Bingo card. But the concepts have come into dramatic real-world tension as private and public actors seek to accommodate the digital and environmental imperatives for green energy.
After years of fairly stable demand, punctuated by declines during the pandemic and economic slumps, electricity demand is projected to double by 2050. A principal cause is the rapid expansion in the power needed to energize and cool servers amid explosive growth in the number and size of data centers, crypto miners, and other point sources of computation. Data centers were 3% of U.S. demand and are projected to be up to 9% or more by 2030; AI will drive a 160% surge in data center demand by 2030. A commentator notes, “We haven’t seen [growth like] this in a generation.”
Reprinted courtesy of
Robert A. James, Pillsbury,
Sidney L. Fowler, Pillsbury and
Ashleigh Myers, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Fowler may be contacted at sidney.fowler@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of