Difficult Task for Court to Analyze Delay and Disorder on Construction Project
August 23, 2021 —
David Adelstein - Florida Construction Legal UpdatesOne of my favorites quotes from a case, and I am sure others in the construction industry feel the same way or can relate, is from the District of Columbia Court of Appeals in Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569, 575 (D.C. 1981):
We note parenthetically and at the outset that, except in the middle of a battlefield, nowhere must men coordinate the movement of other men and all materials in the midst of such chaos and with such limited certainty of present facts and future occurrences as in a huge construction project such as the building of this 100 million dollar hospital. Even the most painstaking planning frequently turns out to be mere conjecture and accommodation to changes must necessarily be of the rough, quick and ad hoc sort, analogous to ever-changing commands on the battlefield. Further, it is a difficult task for a court to be able to examine testimony and evidence in the quiet of a courtroom several years later concerning such confusion and then extract from them a determination of precisely when the disorder and constant readjustment, which is to be expected by any subcontractor on a job site, become so extreme, so debilitating and so unreasonable as to constitute a breach of contract between a contractor and a subcontractor.
Do you agree with this sentiment? The reality is that retrospectively analyzing delay on a complicated construction project with numerous moving parts on a day-by-day, hour-by-hour, basis is no easy feat. It is not easy for the parties and certainly not easy for courts to unravel. With every party claiming delay based on a retrospective analysis there will be another party with either a different delay analysis or providing credible cross examination as to flaws with the delay analysis. The same bodes true with loss of productivity / inefficiency claims and the particular case-specific facts are important, preferably with evidence such as photos, videos, notifications, daily reports, manpower reports, etc., supporting the facts. But the facts are complicated, and the delay analysis is complicated, and it is a difficult task for a trier of fact to unravel these facts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
#12 CDJ Topic: Am. Home Assur. Co. v. SMG Stone Co., 2015 U.S. Dist. LEXIS 75910 (N. D. Cal. June 11, 2015)
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFIn his article, “Remediation Work Caused by Installation of Defective Tiles Not Covered,” attorney
Tred R. Eyerly analyzed the Am. Home Assur. Co. case that involved a dispute between a developer and a subcontractor over fractured tiles: “On cross-motions for summary judgment, the court first found that the fracturing of the stone floor tiles caused by the subcontractor's defective installation was the result of an 'occurrence.' There was no evidence that the subcontractor knew that its tile installation work was defective before the tiles fractured. Instead, the fracturing was an unexpected consequence of the defective installation.”
Everly continues, “But there was no ‘property damage.’ For the subcontractor to prevail, the defective installation work had to be considered separate and distinct from the physical manifestation of the defective work. Under California law, coverage resulted from construction defects that involved physical injuries to other parts of the construction project.” Everly concludes, “Because there was no genuine issues of material fact as to the potential for coverage, there was no duty to defend.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (8/21/24) – REITs Show Their Strength, Energy Prices Increase Construction Costs and CRE Struggles to Keep Pace
October 01, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, UBS to liquidate $2 billion real estate fund, hotel workers in San Francisco vote to strike, housing market to change after blockbuster settlement, and more!
- When it comes to buying and selling homes, new rules are about to be put in play, five months after the National Association of Realtors agreed to a settlement over how its 1.5 million agents across the U.S. are paid commissions. (Kate Gibson, CBS)
- Project abandonments tumbled in July in one of the largest monthly declines ever due to the anticipated interest rate cut. (Sebastian Obando, Construction Dive)
- Increases in energy prices drove most of the total rise in construction input costs over the past month. (Sebastian Obando, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Cherokee Nation Wins Summary Judgment in COVID-19 Business Interruption Claim
February 01, 2021 —
Sergio F. Oehninger, Geoffrey B. Fehling & Matt Revis - Hunton Insurance Recovery BlogIn a resounding victory for policyholders, an Oklahoma state court granted partial summary judgment for the Cherokee Nation in its COVID-19 business interruption claim. The Cherokee Nation is seeking coverage for losses caused by the pandemic—specifically, the inability to use numerous tribal businesses and services for their intended purpose.
Based on the “all risks” nature of the policy and the fortuitous nature of its loss, the Cherokee Nation sought a partial summary judgment ruling that the policies afford business interruption coverage for COVID-19-related losses. The policy provided coverage for “all risk of direct physical loss or damage,” which the Cherokee Nation contended was triggered when the property was “rendered unusable for its intended purpose.” In support of this view, and consistent with established insurance policy interpretation principles, such as providing meaning to every term and reading the policy as a whole, the Cherokee Nation argued that a distinction must exist between “physical loss” and “physical damage.” This distinction demands an interpretation supporting the “intended purpose” reading of the policy language. Thus, the physical presence of COVID-19 depriving the Cherokee Nation of the use of covered property for its intended purpose triggered a covered loss.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Matt Revis, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Another Municipality Takes Action to Address the Lack of Condominiums Being Built in its Jurisdiction
March 12, 2015 —
Heather M. Anderson – Higgins, Hopkins, McLain & Roswell, LLCWhether you are in the market to downsize or are looking to be a first time home buyer, you have likely noticed that your housing options in Colorado have become extremely limited over the course of the last several years. If you are a contractor and have worked on multi-family projects in the recent past, you know why the housing options are limited in the State of Colorado. In the past two years, there have been studies commissioned and articles published in local periodicals investigating the extreme slowdown seen in the construction of owner-occupied multi-family housing, namely condominiums and townhomes. Those of us involved in and with the construction industry are intimately familiar with the lengthy, complicated, and incredibly expensive construction defect litigation that has plagued multi-family construction in the State of Colorado and brought it to a virtual halt.
And now, local municipalities and elected officials are starting to take notice. Most recently, the City of Lone Tree passed Ordinance No. 15-01, to become effective on April 1, 2015. According to the City of Lone Tree, Ordinance No. 15-01 is “aimed at encouraging the development of owner-occupied, multi-family residential projects through the adoption of regulations designed to balance the risk and exposure to builders and developers of such projects, while still protecting homeowners from legitimate construction defect claims.”
Read the court decisionRead the full story...Reprinted courtesy of
Heather M. Anderson, Higgins, Hopkins, McLain & Roswell, LLCMs. Anderson may be contacted at
Anderson@hhmrlaw.com
NEHRP Recommendations Likely To Improve Seismic Design
November 09, 2020 —
Nadine M. Post - Engineering News-RecordCode-based earthquake engineering is on the verge of getting simpler, thanks to the National Earthquake Hazards Reduction Program’s recommendation to replace the traditional seismic hazard maps with an improved seismic hazards database. The recommendation is one of the most significant changes put forth in the 2020 update of the NEHRP seismic design provisions, which are the foundation for the prescriptive seismic design code for buildings and other structures.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fixing the Problem – Not the Blame
November 30, 2016 —
Curtis W. Martin – Peckar & Abramson, P.C. BulletinWho is responsible for defective design under Texas law? The contractor, under Lonergan? The
owner, under Spearin? A recent Fifth Circuit decision suggests that in some cases this might be the
wrong question when design responsibility is disputed. The appellate court recently remanded a
case back to the district court to determine whether the contractor or owner breached an implied
duty to cooperate in discovering defects in design and subsequently pricing the change required
to correct the problem.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C.Mr. Martin may be contacted at
cmartin@pecklaw.com
Flood Sublimits Do Not Apply to Loss Caused by Named Windstorm
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Jersey Superior Court considered whether recovery for storm surge was limited by the policy's sublimit for loss caused by flood. Public Serv. Enter. Group, Inc. v. Ace Am. Ins. Co., 2015 N. J. Super. Unpub. LEXIS 620 (N.J. Super. Ct. Law Div. March 23, 2015).
Storm surge from Superstorm Sandy inundated and damaged Public Service Enterprise Group, Inc.'s (PSEG) property, including eight large generating stations. PSEG had coverage of $1 billion under policies with defendant carriers. There was no sublimit in the policies for "named windstorms," other than named windstorms in Florida. A $250 million sublimit appeared in the policies for losses caused by "flood."
The carriers paid only a portion of PSEG's claim. The total damages exceeded $500 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com