Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence
May 10, 2012 —
CDJ STAFFCoverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).
Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.
Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.
The insurer filed for declaratory relief in federal district court.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Georgia House Bill Addresses Construction Statute of Repose
May 04, 2020 —
Jason Gropper - Autry, Hall & Cook, LLPOn March 2, 2020, by a unanimous vote, the House passed HB 968. This Bill seeks to clarify which civil actions are subject to Code Section 9-3-51, which is the eight-year statute of repose for deficiencies in connection with improvements to realty. If passed by the General Assembly, it would explicitly state that the statute of repose will not apply to breach of express warranties. If the Bill is passed, O.C.G.A § 9-3-51 would include a subsection that provides: “This Code section shall not apply to actions for breach of contract, including, but not limited to actions for breach of express contractual warranties.”
Jason Gropper, Autry, Hall & Cook, LLP
Mr. Gropper may be contacted at Gropper@ahclaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Terms Matter. Be Careful When You Draft Them.
February 01, 2022 —
Christopher G. Hill - Construction Law MusingsIn a prior post, I discussed the case of Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys in the context of the interplay between fraud, contract, and statutes of limitation. Some cases just keep on giving. This time the case illustrates the need for careful drafting of those
pesky, and highly important, clauses in your construction documents.
In the
current iteration of this ongoing saga, the Court considered the contractual aspects of the matter. As a reminder, the facts are as follows: In May 2011, the United States Army (“Army) awarded BAE Systems Ordnance Systems, Inc. (“BAE”) a contract to design and construct a natural gas-fired combined heating and power plant for the Radford Army Ammunition Plant (“RAAP”). On October 7, 2015, BAE issued a request for a proposal from Fluor Federal Solutions, LLC (“Fluor”) to design and build a temporary boiler facility at a specific location on the RAAP property. On October 13, 2015, the Army modified the prime contract to change the location of the boiler facility. On December 10, 2015, the Army modified the prime contract to require BAE to design and construct a permanent boiler facility. On December 30, 2015, Fluor and BAE executed a fixed-price subcontract for Fluor to design and construct the temporary boiler. Throughout 2016, BAE issued several modifications to Fluor’s subcontract to reflect the modifications BAE received from the Army on the prime contract. On March 23, 2016, BAE directed Fluor to build a permanent – rather than temporary – boiler facility. On March 28, 2016, Fluor began construction of the permanent facility and began negotiations with BAE about the cost of the permanent facility. On September 1, 2016, the parties reached an agreement on the cost for the design of the permanent facility, but not on the cost to construct the permanent facility. On November 29, 2016, the parties executed a modification to the subcontract, officially replacing the requirement to construct a temporary facility with a requirement to construct a permanent facility and agreeing to “negotiate and definitize the price to construct by December 15, 2016.” The parties were unable to reach an agreement on the construction price.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Governor Signs AB5 Into Law — Reshaping California's Independent Contractor Classification Landscape
December 02, 2019 —
Eric C. Sohlgren & Matthew C. Lewis - Payne & Fears Legal AlertToday, Governor Gavin Newsom signed California Assembly Bill 5 (“AB5”), controversial legislation which will have a substantial impact on California employers when it goes into effect on January 1, 2020.
AB5 enacts into a statute last year’s California Supreme Court decision in Dynamex Operations West, Inc. v. Superior Court, 4 Cal. 5th 903 (2018), and the Court’s three-part standard (the “ABC test”) for determining whether a worker may be classified as an employee or an independent contractor.
Under the ABC test established in Dynamex and now under AB5, a worker may be properly considered an independent contractor only if the hiring entity establishes all three of the following: (A) that the worker is free from the control and direction of the hirer in connection with the performance of the work, both under the contract for the performance of such work and in fact; (B) that the worker performs work that is outside the usual course of the hiring entity’s business; and (C) that the worker is customarily engaged in an independently established trade, occupation, or business of the same nature as the work performed for the hiring entity.
Reprinted courtesy of
Eric C. Sohlgren, Payne & Fears and
Matthew C. Lewis, Payne & Fears
Mr. Sohlgren may be contacted at ecs@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Resulting Loss Provision Does Not Salvage Coverage
April 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court confirmed that there was no coverage for damage to the policyholder's building caused by a large volume of water. Praetorian Ins. Co. v. Arabia Shrine Ctr. Houston, 2016 U.S. Dist. LEXIS 20186 (S.D. Texas Feb. 19, 2016).
The damage occurred when water began seeping through the baseboards of the Shrine. Employees saw a large amount of water entering the building. Eventually, the city shut off a water main valve. It was later determined that an 8 inch diameter fire suppression metal pipe failed at the elbow, causing over one million gallons of water to be released into the building. Damages were estimated at nearly $1.7 million. Clean up and repair costs amounted to $237,156.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Revised Cause Identified for London's Wobbling Millennium Bridge After Two Decades
December 20, 2021 —
Peter Reina - Engineering News-RecordU.S. and British researchers claim to have found a better explanation for the wobble of London's River Thames Millennium pedestrian suspension bridge than the one prevailing for over 20 years. Alarming swaying of the bridge was caused not by synchronization of walkers' footsteps, as previously believed, but the negative damping effect of their efforts not to fall over.
Reprinted courtesy of
Peter Reina, Engineering News-Record
Mr. Reina may be contacted at reina@btinternet.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Court Weighs In On Insurance Coverage For COVID-19 Business Interruption Losses
October 11, 2021 —
Rondi J. Walsh - Newmeyer DillionOn October 1, 2021, the Ninth Circuit Court of Appeals ruled on a trio of cases involving COVID-19 business interruption losses, in a series of written opinions with results favoring the insurers. Despite the slate of wins for insurers in this round of cases, these rulings are limited to cases where policyholders either did not allege the presence of COVID-19 on their premises causing “physical alteration” of the property itself, or had a virus exclusion in their policy, or both. This leaves room for future cases potentially ruling in favor of coverage where the insureds allege the presence of coronavirus on the premises, and that there was a detrimental physical alteration of the property as a result. To date, the Ninth Circuit has not ruled on such a situation.
RULING 1: Mudpie v. Travelers Casualty Insurance Co. of America
The Ninth Circuit first considered a proposed class action brought by a children’s store operator, Mudpie. Mudpie sought business income and extra expense coverage from Travelers after California and local authorities issued shutdown orders impacting Mudpie’s operations due to COVID-19. (Mudpie, Inc. v. Travelers Casualty Insurance Company of America, Case No. 20-16858, --- F.4th --- (9th Cir. Oct. 1, 2021).) Travelers denied coverage, asserting that the claim did not involve “direct physical loss of or damage to” property “caused by or resulting from a covered Cause of Loss.” Travelers also denied coverage under language excluding “loss or damage caused by or resulting from any virus…that induces…physical distress, illness or disease.” Applying California law, the trial court agreed with Travelers on both accounts.
Read the court decisionRead the full story...Reprinted courtesy of
Rondi J. Walsh, Newmeyer DillionMs. Walsh may be contacted at
rondi.walsh@ndlf.com
Duty to Defend Negligent Misrepresentation Claim
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Kansas Court of Appeals determined that the insurer must defend claims of negligent misrepresentation against its insured. Central Power Sys. & Servs. v. Universal Underwriters Ins. Co., 2014 Kan. App. LEXIS 9 (Kan. Ct. App. Feb. 21, 2014).
Central Power contracted to furnish Eagle Well with 10 oil-rig engines and 10 oil-rig transmissions. Eagle Well alleged that Central Power informed them that the engines and transmissions would be operational without any additional components. As is turned out, the engines could not operate without a wiring harness. Eagle Well had to hire a third party to make wiring harnesses that would meet their needs and to install the wiring harnesses.
Eagle Wells sued Central Power, alleging damages in the form of lost profits for the time it took to make the engines independently operational. Further, damages were incurred due to money needed for the costs of purchasing the wiring harnesses from the third party and attaching the harnesses to the engines. Claims asserted against Central Power included breach of contract, negligence and negligent misrepresentation.
Read the court decisionRead the full story...Reprinted courtesy of