2021 Executive Insights: Leaders in Construction Law
August 16, 2021 —
Donald Berry - Construction ExecutiveGregory Cokinos, President and CEO, Cokinos | Young
First, experience in the construction industry is of primary importance and vital to successfully negotiating construction contracts and handling construction claims and disputes. Even a mildly complex construction dispute is more than most non-construction lawyers can properly handle. Issues concerning scheduling, productivity, change management and risk shifting (among many others) are complex and unique to construction and can be further complicated by the procedural and substantive law that differs from jurisdiction to jurisdiction.
Second, it is essential that your law firm has a culture of representing construction professionals. Understanding construction nomenclature and how construction projects are staffed, organized and documented saves time and money in an already expensive and time-consuming process.
You cannot overstate the advantage of shared resources within an established construction firm when evaluating and handling construction matters. A law firm that dedicates a significant portion of its practice to the construction industry is uniquely positioned to realize this advantage. Finally, as I tell our young lawyers, “success” only comes before “work” in the dictionary. Hard work is the key to successfully negotiating a contract or executing a litigation plan in this complex industry. So, look for a firm that is not afraid of working long days and weekends to achieve success.
Reprinted courtesy of
Donald Berry, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Maryland Contractor Documents its Illegal Deal and Pays $2.15 Million to Settle Fraud Claims
January 07, 2015 —
Craig Martin- Construction Contractor Advisor BlogWhy would a contractor create a contract for illegal work? I really don’t know.
Late last year, the FBI announced that a Maryland contractor, Forrester Construction Company, agreed to pay $2.15 million dollars to resolve a criminal investigation into alleged fraud in connection with the use of disadvantaged business enterprises involving more than $145 million of District of Columbia government contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Don’t Forget to Mediate the Small Stuff
August 02, 2017 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I talked mediation here at Construction Law Musings. Those that read regularly (thanks) have likely missed my musings on the topic. Those who read this construction blog regularly also know that I am both a Virginia Supreme Court certified general district court mediator and a huge advocate of mediation as a method to resolve construction disputes. While many of us think of mediation as a method to resolve the major disputes or litigation that occasionally rear their heads in the course of running a construction law practice or construction business, my experience as both a construction attorney and a mediator has taught me something: mediation works for all sizes of cases.
As an advocate for my construction clients, I know that proper trial preparation requires the same diligence and attention to detail for a smaller case as it does for a larger case. While a smaller case in the Virginia general district court may not have the depositions, written discovery and motions practice that a Virginia circuit court case may have, it still requires witness preparation, document processing and review and many of the other aspects of a larger case. While construction litigation is never a money maker in the best of circumstances, in the smaller cases the attorney fees often total a larger percentage of the total potential recovery. For this reason, the small cases are almost better suited for a quick mediated resolution than the larger ones. The larger cases may cost more to prosecute or defend, but the fees are less likely to eat up such a large percentage of any recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Beyond the Statute: How the Colorado Court Upheld Modified Accrual in Construction Contracts
November 13, 2023 —
Hal Baker - Colorado Construction Litigation BlogIn a case of first impression, the First Division of the Colorado Court of Appeals recently reviewed whether parties may contractually alter the accrual time established by Colorado’s statute of limitations for construction defect actions, C.R.S. § 13-80-104, in South Conejos Sch. Dist. RE-10 v. Wold Architects, Inc., 2023 COA 85 (2023), decided on September 21, 2023. The Court held that sophisticated parties may contractually alter the accrual time standards, enlarging the accrual time as was the issue in this case. Notably, the Court’s decision was made in the context of commercial construction, not residential.
The issue in South Conejos Sch. Dist. RE-10 arose from the construction of a school in Antonito, Colorado. Prior to construction, the South Conejos School District RE-10 (the “School District”) and Wold Architects, Inc. (“Wold”) entered a contract that provided:
Unless a longer period is provided by law, any action against [Wold] brought to recover damages for deficiency in the design, planning, supervision, inspection, construction or observation of construction or for injury to person or property shall be brought within two years after the claim for relief arises and is discovered by [the District]; … “Discovered” as used herein means detection and knowledge by [the District] of the defect in the improvement that ultimately causes the injury, when such defect is of a substantial or significant nature.
Read the court decisionRead the full story...Reprinted courtesy of
Hal Baker, Higgins, Hopkins, McLain & Roswell, LLCMr. Baker may be contacted at
baker@hhmrlaw.com
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Hail Damage Requires Replacement of Even Undamaged Siding
February 05, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute over the property policy's requirement that lost or damaged property be repaired or replaced, the Minnesota Supreme Court held that the policy language called for replacement of undamaged siding panels to obtain a color match. Cedar Bluff Townhome Condominium Ass'n, Inc. v. Am. Family Mut. Ins. Co., 2014 Minn. LEXIS 661 (Minn. Dec. 17, 2014).
During a hail storm, all 20 of Cedar Bluff's buildings sustained some damage. The roofs on all of the buildings needed to be replaced, and at least one siding panel on each building sustained damage. Eleven of the 20 buildings had three or fewer damaged panels. At the time of the hail storm, the siding was approximately 11 years old, and the color of the panels had faded. Replacement panels were available, but not in the same color.
Cedar Bluff submitted a claim under its business owners' policy to American Family. The policy obligated the insurer to pay for "direct physical loss of or damage to Covered Property at the premises . . . caused by or resulting from any Covered Cause of Loss." "Covered Property" was broadly defined in the policy to include buildings at the premises.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
University of California Earthquake Report Provides List of Old Concrete Buildings in LA
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a list provided to the city of Los Angeles by the University of California, there are “about 1,500 old concrete buildings that are potentially at risk of collapse during an earthquake,” the Los Angeles Times reported. The list can help the city identify “concrete buildings most likely to fail in an earthquake.”
The report, however, “does not amount to a list of dangerous buildings,” the university scientists told the Los Angeles Times. It is a list of concrete buildings built before 1980. Some of the “buildings are vulnerable, others are not.”
Concrete buildings pose a potentially dangerous threat, reported the Los Angeles Times: “After the Northridge earthquake caused two concrete buildings to collapse and severely damaged others, structural engineers warned that the collapse of a single concrete building ‘has the potential for more loss of life than any other catastrophe in California’ since the 1906 San Francisco earthquake.”
Eric Garcetti, Los Angeles Mayor, has asked Lucy Jones, a U.S. Geological Survey seismologist, to act as his science advisor on earthquake issues. Garcetti has asked Jones “to come up with recommendations by the end of the year on retrofitting issues, including how to get privately owned concrete buildings retrofitted.”
Read the court decisionRead the full story...Reprinted courtesy of