Accident/Occurrence Requirement Does not Preclude Coverage for Vicarious Liability or Negligent Supervision
June 06, 2018 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn Liberty Surplus Ins. Corp. v. Ledesma & Meyer Construction Co., Inc. (No. S236765, filed 6/4/18) (L&M), the California Supreme Court ruled that the liability insurance requirement that injury be caused by an “occurrence,” defined as an “accident,” does not preclude coverage of an employer’s independent tort liability for injury deliberately caused by its employee.
In L&M, Liberty insured a construction company that contracted to manage a construction project at a middle school in San Bernardino, California. A 13-year-old student subsequently sued the company in state court, alleging that she had been sexually molested by a company employee, Hecht. Among others, she alleged a cause of action for negligent hiring, retention and supervision of the employee. The construction company tendered to Liberty, which defended the employer under a reservation of rights while seeking declaratory relief in federal court. The district court granted summary judgment for Liberty, ruling that the injury was not caused by an “occurrence.” On appeal, the 9th Circuit Court of Appeals certified the question to the California Supreme Court as a matter of state law.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Global Insurer Agrees to Pay COVID-19 Business Interruption Claims
July 06, 2020 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogAXA, one of the biggest insurance companies in the world, has agreed to pay COVID-related business interruption claims by a group of restaurants in Paris after a court ruled that the restaurants’ revenue losses resulting from COVID-19 and related government orders were covered under AXA’s policies.
AXA initially took the position that its insurance policies did not cover business interruption caused by COVID-19. The restaurant then sued AXA in a French court, seeking coverage for operating losses resulting from a government order issued in March mandating the closure of restaurants and bars in response to the COVID-19 pandemic. The court concluded that the government orders, which prohibited restaurants from receiving the public and offering traditional sit-down dining services, triggered the policy’s coverage for business interruption coverage. The court rejected AXA’s argument that the pandemic was uninsurable, and made clear that if AXA intended to exclude such a risk it should have done so expressly in its policy. The court also rejected AXA’s argument that there must be a prerequisite of an insured event for the application of the “administrative closure” provision, noting that no prerequisite was required by the policy. AXA’s argument that the government orders did not require the restaurant to be closed because the restaurant was authorized to maintain take-away services was also rejected. As a result, the court ruled in favor of the policyholders, holding that the business interruption loss resulting from the government orders qualified for insurance coverage.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Details Matter: The Importance of Strictly Following Public Bid Statutes
September 22, 2016 —
Wally Zimolong – Supplemental ConditionsContractors bidding on public contracts know that failing to strictly following all of the technical aspects contained in the instructions to bidders can mean the difference between a winning and losing bid. In the span of two weeks, I was involved with two cases that underscored the importance of this axiom. Both cases involved New Jersey’s public bid laws. While these cases show the importance of following a specific section of New Jersey’s public bid statute, the take away – that details matter – is universal.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 —
CDJ STAFFThe Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Supreme Court Clarifies Area Variance Standard; Property Owners May Obtain an Area Variance When Special Circumstances Existed at Purchase
October 19, 2017 —
Nick Wood, Adam Lang, Noel Griemsmann, & Brianna Long – Snell & Wilmer Real Estate Litigation BlogIn Pawn 1st v. City of Phoenix, the Arizona Supreme Court rejected a Court of Appeals rule that would have unduly restrained alienation of property in Arizona. The Court of Appeals found that the City of Phoenix Board of Adjustment acted beyond its authority when it granted an area variance to a pawn shop where the special circumstances causing a need for the variance existed before the pawn shop purchased the property. Under Arizona law, boards of adjustment cannot grant an area variance where the special circumstances requiring the variance are self-imposed. The Court of Appeals adopted a rule that knowledge of special circumstances at the time of purchase made the special circumstances self-imposed, foreclosing the purchaser’s ability to obtain a variance. This rule would have severely restricted property purchasers’ ability to obtain area variances in Arizona and by extension likely strained property transactions.
The underlying case involved a pawn shop that was proposed in southeast Phoenix. After the property purchaser obtained approval for a required use permit (for a pawn shop) and a variance (for a 500 foot residential setback) from the City of Phoenix Board of Adjustment, a competing pawn shop filed a special action arguing that the variance was a use variance, not an area variance, beyond the board of adjustment’s authority.
Reprinted courtesy of Snell & Wilmer attorneys
Nick Wood,
Adam Lang,
Noel Griemsmann and
Brianna Long
Mr. Wood may be contacted at nwood@swlaw.com
Mr. Lang may be contacted at alang@swlaw.com
Mr. Noel may be contacted at ngriemsmann@swlaw.com
Ms. Brianna may be contacted at bllong@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois Promotes 35 to Partnership
March 15, 2021 —
Lewis BrisboisLewis Brisbois is proud to announce the promotion of 35 of its associates to partner. With these promotions, Lewis Brisbois’ total partnership comes to 933 across its 53 offices. The diverse class of newly promoted attorneys includes 15 women, which brings the total percentage of female partners at Lewis Brisbois to 33%.
Los Angeles Managing Partner Jana I. Lubert expressed her excitement about the recent promotions, stating, “On behalf of the Management Committee, I congratulate these outstanding attorneys on their achievement. They have demonstrated an exceptional level of dedication to Lewis Brisbois and to our clients, especially during this difficult past year. I am particularly proud of the diversity that exists across this group.”
Similarly, San Bernardino and Chief Diversity Partner Rima M. Badawiya shared her enthusiasm over the diversity of the new partners, explaining, “This group of exceptional attorneys, who have been promoted based upon their extraordinary performance, represents the diversity that exists throughout Lewis Brisbois and our commitment to advancing those who achieve at the highest level.”
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
A DC Office Building Offers a Lesson in Glass and Sculpture
May 08, 2023 —
Kriston Capps - BloombergFrom the outside, the facade of 2050 M Street, an office building in Washington, DC, looks like it’s made with liquid soap. Standing inside and looking out, its structure is almost invisible. The building, which was finished in 2020, boasts an ethereal curtain wall, created from hundreds of fluted planes of glass treated with a special industrial coating. The result is a multifaceted surface that pushes the limits of transparency, enhanced with a silver opal shine.
According to Joshua Ramus, founding principal of the architecture firm REX, the 12-story structure’s design reflects Washington’s building history, while its construction required a rather novel procurement process. The building, he says, is very much a DC story.
Each of its 978 glass panels is concave, shaped using an innovative machine called a bending tempering furnace. Curving glass makes it stronger as a material, and this building’s panes are strong enough to stand up with minimal infrastructure. The building doesn’t employ mullions, window components that hold glass in place. Even a few years ago, achieving such an effect by shaping pieces of glass would have been prohibitively expensive.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg