A Primer on Suspension and Debarment for Federal Construction Projects
August 10, 2020 —
Hal J. Perloff - Construction ExecutiveWe’ve all heard the expression that those who deal with the government must turn square corners. This is because the government has a broad array of tools at its disposal to motivate, coax and cajole contractors and federal grant recipients to play by the rules. Those tools include harsh measures such as criminal prosecution and civil false claims act enforcement on the one hand and poor CPARS ratings on the other. A seemingly less severe administrative option available to the government is suspension and debarment. However, any entity that has been suspended or debarred knows that these measures can prove harsh and disruptive.
While the numbers of suspensions and debarments have declined from the all-time high in 2011, there is still significant activity. In its FY 2018 report, the Interagency Suspension and Debarment Committee reported 2444 referrals, 480 suspensions, 1542 proposed debarments and 1334 debarments. The number of referrals for suspension and debarment in FY 2018 is almost exactly the same as the number of GAO bid protests filed that year.
WHAT IS SUSPENSION AND DEBARMENT?
Suspension and debarment are the government’s tools to avoid entities it views as a high risk for poor performance, fraud, waste and abuse. Suspension and debarment preclude a business entity or individual from contracting with the government or from receiving grants, loans, loan guarantees or other forms of assistance from the government. A suspension is a temporary exclusion when the government determines immediate action is necessary pending the completion of an investigation or legal proceeding. A debarment is an exclusion for a defined, reasonable period of time—often three years.
Reprinted courtesy of
Hal J. Perloff, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Perloff may be contacted at
hal.perloff@huschblackwell.com
Repairs to Hurricane-damaged Sanibel Causeway Completed in 105 Days
February 12, 2024 —
Marigo Farr - Engineering News-RecordPermanent repairs to the roadway portion of the Sanibel Causeway are substantially complete one year and four months after more than 6,000 Sanibel Island residents lost access to the mainland in the wake of Hurricane Ian. The Superior Construction and The De Moya Group joint-venture team, responsible for the work, say that all travel lanes are now permanently open to the island off Florida's southwest coast near Fort Myers.
Reprinted courtesy of
Marigo Farr, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Private Mediations Do Not Toll The Five-Year Prosecution Statute
April 28, 2016 —
Zachary P. Marks – Chapman Glucksman Dean Roeb & Barger In FocusIf you thought private mediation could toll the five-year period for case prosecution – think again. In a recent decision handed down by the Second District Court of Appeal, the court unequivocally held that voluntary, private mediations do not toll the five-year period before dismissal for failure to bring an action to trial.
California Code of Civil Procedure section 583.310 sets forth the applicable rule: “[a]n action shall be brought to trial within five years after the action is commenced against the defendant.” Section 1775.7(b) clarifies this rule, stating that the five-year period can be tolled if it is “submitted to mediation” within the final six months of the five-year period. However, the Code is silent with respect to the effect of tolling on public versus private mediations.
The Court of Appeal addressed this issue in its recent decision entitled Castillo v. DHL Express (USA) (2015) 243 Cal.App.4th 1186. Castillo was an employment class action brought by truck drivers against their employers. Plaintiffs argued that the case was “submitted to mediation” within the meaning of Section 1775.7(b) because the court’s Case Management Order reflected the fact that the parties agreed to pursue mediation. Conversely, defendants argued that the Case Management Statement clearly stated that the parties voluntarily agreed to a private mediation, not a court-ordered mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary P. Marks, Chapman Glucksman Dean Roeb & Barger In FocusMr. Marks may be contacted at
zmarks@cgdrblaw.com
Dot I’s and Cross T’s When It Comes to Construction Licensure Requirements
February 21, 2022 —
David Adelstein - Florida Construction Legal UpdatesIt should serve as no surprise that making sure you are appropriately licensed is important. This includes complying with any state requirement that requires licensure, as well as complying with any local licensure requirement. Not doing so can result in the dispute centered on the lack of licensure, as opposed to leading facts relating to the substance of the dispute. In other words, you are dealing with a technicality that could have harsh implications. This lack of licensure issue recently played out in a dispute with a contractor and subcontractor in ABA Interior, Inc. v. The Owen Corp., 2022 WL 386103 (Fla. 4th DCA 2022), dealing with a local licensure requirement.
In this case, a subcontractor was hired by the general contractor for a commercial project in Palm Beach County. The subcontract contained the standard provision that the subcontractor would comply with all federal, state, and local laws and ordinances.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Appraisal Goes Forward Even Though Insurer Has Yet to Determine Coverage on Additional Claims
December 11, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's order granting the insured's motion to stay litigation and compel an appraisal was affirmed even though the insurer had not determined coverage on the insured's additional claims.Heritage Prop. & Cas. Ins. Co. v. Wellington Place HOA, 2023 Fla. App. LEXIS 6405 (Fla. Ct. App. Sept. 13, 2023).
The insured homeowner's association reported roof damage to its insurer, Heritage, after Hurrican Irma struck. Heritage agreed the damage was covered, but issued no payment because the amount of loss was less than the deductible.
The insured hired its own adjuster. The insured requested an extension of the policy's two year time limit to complete repairs because the claim was still in dispute and the insurer had not yet paid sufficient funds to allow necessary repairs. Heritage sent a revised estimate and asked the insured to send its adjuster's estimate in order to address any disputes. The insured submitted its adjuster's estimate of more than $6 million, including, for the first time, the cost to replace all the windows and sliding glass doors.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insureds Survive Summary Judgment on Coverage for Hurricane Loss
June 19, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the insurer's motion for summary judgment be denied, finding a material issue of fact regard the cause of loss after Hurricanes Laura and Delta. Armstrong v. Amguard Ins Co., 2023 U.S. Dist. LEXIS 76869 (E.D. Texas, April 14, 2023).
The policy excluded damage caused by wear and tear, differential foundation movement, as-built deficiencies, manual damage, and pre-existing conditions. Texas applied the doctrine of concurrence causes, meaning if damages were due to both covered and non-covered causes of loss, the insureds had to segregate the damage caused by covered causes of loss from the damage caused by non-covered causes of loss. Coverage was denied and the insureds filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Second Circuit Certifies Question Impacting "Bellefonte Rule"
December 15, 2016 —
Ellen Burrows – White and Williams LLPCalling into question the continued validity of the so-called “Bellefonte Rule,” on December 8, 2016, the United States Court of Appeals for the Second Circuit certified to the New York Court of Appeals the question whether a facultative reinsurance contract limit is presumptively all-inclusive and “caps” the reinsurer’s total exposure even where the reinsured policy pays defense costs in addition to the limit. Global Reinsurance Corporation v. Century Indemnity Company Docket No. 15-2164-cv (December 8, 2016).[1]
In Bellefonte Reinsurance Company v. Aetna 903 F.2d 910 (2d Cir. 1990), the court ruled that a reinsurer was not liable to pay defense costs above the stated reinsurance contract limit. Although litigants argued that this ruling was dependent on the fact that the reinsured policy limits were defense cost-inclusive, a later panel of the Second Circuit applied the “cap” ruling in Bellefonte to a situation where the reinsured policy limit was not cost-inclusive and where the insurer was obligated to pay defense costs in addition to the policy limit. Unigard Security Insurance Company v. North River Insurance Company 4 F.3d 1049 (2d Cir. 1993).
Read the court decisionRead the full story...Reprinted courtesy of
Ellen Burrows, White and Williams LLPMs. Burrows may be contacted at
burrowse@whiteandwilliams.com
What You Need to Know to Protect the Project Against Defect Claims
October 28, 2024 —
Scott L. Baker - Los Angeles Litigation BlogIf a property owner claims there is a construction defect, that not only brings the project’s integrity into question but also your business’s reputation. So, how can you take steps to prevent these claims from causing such damage?
Here are three things to know before beginning a project to effectively protect it and
manage construction defect claims.
1. Documentation is key
California and Los Angeles County require certain permits and documents in order for a construction project to move forward. Los Angeles County
will also conduct plan checks to ensure everything is up to code. Detailed documentation will be important while making your plans.
However, keeping notes throughout every step of the project will also be essential. Documenting all aspects of the project helps you:
- Stay updated and aware of the project’s progress
- Proactively catch and handle issues that could result in disputes
- Create a record of evidence that can help manage defect claims
Read the court decisionRead the full story...Reprinted courtesy of