Show Me the Money: The Good Faith Dispute Exception to Prompt Payment Penalties
March 13, 2023 —
Garret Murai - California Construction Law BlogCalifornia has a number of
prompt payment penalty statutes on the books. Among them is Civil Code section 8800 which requires project owners on private works projects to pay progress payments to direct contractors within 30 days after demand for payment pursuant to contract or be subject to prompt payment penalties of two percent (2%) per month on the amount wrongfully withheld. Like California’s other prompt payment penalty statutes, however, there is an important carve out: If there is a good faith dispute between the project owner and the direct contractor the project owner may withhold up to 150% of the dispute amount and not be subject to prompt payment penalties. And that, my friends, is a higher-tiered party’s “get out of jail free” card.
In a case of first impression, the 1st District Court of Appeals, in
Vought Construction Inc. v. Stock (2022) 84 Cal.App.5th 622, examined whether a project owner’s claim for liquidated damages constitutes a good faith dispute under Civil Code section 8800.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Miller Wagers Gundlach’s Bearish Housing Position Loses
May 19, 2014 —
Alexis Leondis – BloombergBill Miller said investor Jeffrey Gundlach and real estate billionaire Sam Zell are wrong about housing.
Gundlach, the chief executive officer of DoubleLine Capital LP, and Zell, chairman of landlord Equity Residential, predict fewer young people will buy homes, further driving down the U.S. ownership rate. Miller, the stock picker who beat the Standard & Poor’s 500 Index for a record 15 years, said he’s so confident lending and housing will rebound that he’s betting on mortgage insurers, homebuilders and subprime servicers.
“Anytime there’s a cataclysm, people always say it’s never going to come back,” said Miller, 64, sitting outdoors at a table overlooking Baltimore’s harbor. “I don’t believe there’s been a secular change in demand for housing. People may just rent longer than they otherwise would have before eventually buying.”
Read the court decisionRead the full story...Reprinted courtesy of
Alexis Leondis, BloombergMs. Leondis may be contacted at
aleondis@bloomberg.net
Alexis Crump Receives 2020 Lawyer Monthly Women in Law Award
August 31, 2020 —
Alexis Crump - Lewis BrisboisLos Angeles Partner Alexis G. Crump has been recognized with a 2020 Lawyer Monthly "Women in Law Award." In receiving this honor, Ms. Crump joins an elite group of women from around the world who have influenced the legal profession with their experience and expertise.
Lawyer Monthly’s "Women in Law Awards" emerged as one of the first industry awards to celebrate the achievements and contributions made by women working globally in the legal sector and in business. Recognizing women at all levels of seniority, the publication seeks to acknowledge the challenges that female legal professionals regularly overcome to serve their clients and perform at their best.
“It is an honor to be recognized alongside so many outstanding and accomplished women. I look forward to continuing to support my colleagues in their work and participating in the global network of female attorneys,” Ms. Crump said.
Read the court decisionRead the full story...Reprinted courtesy of
Alexis Crump, Lewis BrisboisMs. Crump may be contacted at
Alexis.Crump@lewisbrisbois.com
Court Denies Insurers' Motions for Summary Judgment Under All Risk Policies
June 05, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that the insurers could not escape coverage by summary judgment under their all risk policies. Eagle Harbour Condo Assoc'n v. Allstate Ins. Co., 2017 U.S. Dist. LEXIS 54761 (W.D. Wash. April 10, 2017).
Eagle Harbour Condominium Association sued several of its insurers who denied coverage for hidden water damage. Various insurers provided coverage from 1988 to 2015.
The Association asserted that wind-driven rain and inadequate construction allowed water to penetrate the buildings' sheathing and framing, causing decades of deterioration and decay, until the damage was exposed to view in August 2014. The insurers claimed that the loss resulted from poor decisions in constructing and inadequately maintaining a stucco building in the wet and windy Pacific Northwest. The Association argued that the policies did not explicitly exclude damage caused by wind-driven rain, so there was coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pentagon Has Big Budget for Construction in Colorado
January 17, 2013 —
CDJ STAFFThe Pentagon is an important source of construction contracts, and one place where they’re acutely aware of this in Colorado Springs, Colorado. Luckily for the town’s economy, the military awarded $400 million in construction contracts to Colorado, many of them in the town of Colorado Springs.
Projects in Colorado Springs include facilities for a helicopter unit at Fort Carson and renovations at the Air Force Academy. The new operation center for defense intelligence at Buckley Air Force Base will be built in nearby Aurora. The price tag on the operations center is $117 million. Meanwhile, the military has thousands of both civilian and military employees who will be using these facilities.
Read the court decisionRead the full story...Reprinted courtesy of
SNC-Lavalin’s Former Head of Construction Pleads Guilty to Bribery, Money Laundering
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFRiadh Ben Aissa, a former SNC-Lavalin executive, “pleaded guilty to charges including bribery and money laundering in Switzerland, according to a court filing released on Wednesday,” reported the Wall Street Journal.
SNC-Lavalin “issued a separate statement acknowledging the court's acceptance of Mr. Ben Aissa's guilty pleas, adding it was recognized as ‘an injured party’ in the case and would recover an unspecified amount of money from him.”
Chief Executive Robert Card stated, “SNC-Lavalin's goal is nothing less than to set a new standard for clean business in the engineering and construction industry,” as quoted by the Wall Street Journal. “We've adopted a zero-tolerance policy for ethics violations of any kind. We have the right people in place and systems and procedures which are designed to protect the company and its stakeholders from future fraudulent actions."
Read the court decisionRead the full story...Reprinted courtesy of
Repair of Fractured Girders Complete at Shuttered Salesforce Transit Center
July 22, 2019 —
Nadine M. Post - Engineering News-RecordThe repair of two fractured girders spanning Fremont Street and the reinforcement of twin girders spanning First Street are complete at the beleaguered Salesforce Transit Center in San Francisco.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
New Mandatory Bond Notice Forms in Florida
December 16, 2019 —
Brian A. Wolf & Miles D. Jolley - Smith CurrieSubcontractors and suppliers must now use new, statutory notice of nonpayment forms to preserve payment bond claims, and sign each notice of nonpayment under oath.
The State of Florida instituted changes to the statutes governing public-project payment bonds (section 255.05, Florida Statutes) and private-project payment bonds (section 713.23, Florida Statutes). The changes went into effect on October 1, 2019. Previously, notices of nonpayment were not required to be signed under oath. Now, the law requires the use of specific statutory notice forms that claimants must sign under oath. Previously, there were no statutory penalties for claimants who exaggerated the amount claimed against a payment bond. Now there are specific statutory penalties against a claimant who willfully or negligently signs a notice of nonpayment that includes a claim for work not performed or materials not furnished, or who is guilty of signing a notice prepared with willful or gross negligence.
Public construction payment bonds are governed by section 255.05, Florida Statues, also known as Florida’s Little Miller Act. This statute requires all payment bond claimants who don’t have a direct contract with the general contractor to serve both the bonding company and the general contractor with a notice of nonpayment no later than 90 days after their last date of work or last delivery of materials. The amended statute now requires that the claimant use the statutory notice form and sign the form under oath. If the claimant includes exaggerated claims, or intentionally makes a claim for work or materials not provided, or otherwise prepares a notice with gross negligence, then the bonding company and the general contractor will be able to use such as a complete defense to an otherwise valid bond claim.
Reprinted courtesy of
Brian A. Wolf, Smith Currie and
Miles D. Jolley, Smith Currie
Mr. Wolf may be contacted at bawolf@smithcurrie.com
Mr. Jolley may be contacted at mdjolley@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of