A Quick Checklist for Subcontractors
January 26, 2017 —
Christopher G. Hill – Construction Law MusingsAfter the last two weeks’ analyses of a couple of big construction decisions that came out recently, I thought I’d keep this week’s post practical and short for those that are not construction lawyers. So without further ado, here is a short checklist of the top things (aside from calling their local experienced construction attorney) a construction subcontractor should do or look for when reviewing a construction contract from a general contractor (and for a couple of these that a general contractor can look for in its prime contract).
- ALWAYS get a copy of the Prime Contract between the Owner and the General Contractor. This contract will contain terms that will “flow down” to you through the incorporation clause that almost every subcontract contains. You can’t do much to change these terms, but you will need to know them as the job progresses.
- READ every provision of the subcontract. I know this sounds simple, but not all subcontracts hide the red flags in the same places. Remember the details of a subcontract can sink you later if you aren’t prepared.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Visual Construction Diaries – Interview with Jeff Sassinsky of Fovea Aero
November 30, 2017 —
Aarni Heiskanen - AEC BusinessJeff Sassinsky, President of Fovea Aero, gave me a live demonstration on Fovea Aero Vision – an app that allows you to a get a fully immersive visual construction diary of your project.
The idea for the development of Fovea Aero Vision came from discussions with general contractors, owners, and other construction industry professionals. They were talking about the use of smartphones, particularly phone cameras, in construction. The photos, for example, of a fitting that does not look right end up in a folder on a server or goes back and forth in email messages. “The lack of any structure behind both the collection and the storage and sharing of the photos is hampering their usage,” Jeff said. “We wanted to solve the problem by creating a full record of everything that takes place on a construction site, on a regular basis, sharing it among the stakeholders, and making it super easy to use.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
The Peak of Hurricane Season Is Here: How to Manage Risks Before They Manage You
September 21, 2020 —
Vincent E. Morgan - Construction ExecutiveThe Atlantic hurricane season runs from June 1 to Nov. 30, but it peaks sharply during August, September and October. The latest forecasts predict this will be one of the most active seasons in history, in terms of frequency and severity, though it is always important to remember that even a single hurricane or tropical storm making landfall can still be a devastating event.
Hurricanes pose unique risks to the construction industry ranging from project and labor force disruptions to concerns about the availability and price of construction materials. This is even more true this year, which requires merging hurricane preparedness and response plans with the realities of COVID-19. Because hurricanes cannot be avoided, preparing for them is the only way to manage these risks. Ensuring the personal safety and wellbeing of affected individuals is the first priority. After that, here are some key issues, and suggestions for handling them, that may help guide construction companies through the storm.
SITE PROTECTION
Construction contracts often place responsibility for site protection on contractors. Where those duties exist, failing to properly carry them out can lead to enormous losses that then turn into liability claims. This could be anything from removing materials that can become projectiles, covering exposed ventilation shafts, and sealing electrical conduits to ensuring that key equipment such as generators and pumps can remain functional in a storm. One way to approach it is to imagine sustained 100-mph winds and relentless water, and then make sure preparedness efforts are likely to survive that kind of test. This is not the time for guessing. It is far better to go through a rigorous analytical process now than in a courtroom years later.
Reprinted courtesy of
Vincent E. Morgan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Building a Strong ESG Program Can Fuel Growth and Reduce Company Risk
June 19, 2023 —
The Hartford Staff - The Hartford InsightsCompanies are addressing today’s evolving ESG (Environmental, Social and Governance) issues like they never have before. From climate change to diversity, equity and inclusion, these topics are at the forefront of discussion for businesses, with many seeking to understand stakeholder concerns and implement strategies to improve their ESG efforts.
Stakeholders – consumers, investors and employees alike – have recently become more vocal and united in their demand for sustainable corporate behavior. In fact, 83% of consumers think companies should be actively working on Environmental, Social and Governance (ESG) program best practices and 86% of employees prefer to support or work for companies that care about the same issues they do.1 In turn, companies are addressing these issues like they never have before, in recognition of their importance as indicators of long-term value.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New Insurance Case: Owners' Insurance Barred in Reimbursement Action against Tenant
April 17, 2019 —
Jason Adams - Gibbs GidenThe Western Heritage Ins. Co. v. Frances Todd, Inc. (2019 Cal.App. LEXIS 299 / 2019 WL 1450731) case has potential implications for insurance carriers, policyholders, condominium associations, unit owners, landlords and tenants.
The case involves a fire at a commercial condominium complex (the “Association”). The Association’s CC&Rs required the Association to purchase a master fire insurance policy for the benefit of the Association and owners, with a waiver of subrogation endorsement that stated the insurance company could not seek reimbursement from the Association, its officers, owners or occupants of the units in the event of a covered fire. The CC&Rs also prohibited individual owners from obtaining their own fire insurance. The Association purchased the required fire insurance policy from Western Heritage Insurance Company (“Western Heritage”).
One of the owner’s tenants, Frances Todd, Inc. (“Frances Todd”), allegedly caused a fire that damaged several units. Although the unit owner was covered as an additional named insured under the Western Heritage fire policy, the tenant, Frances Todd, was not. Western Heritage paid for the common area fire damage caused by Francis Todd, and then sued Frances Todd in a subrogation action to recover the amounts paid.
Read the court decisionRead the full story...Reprinted courtesy of
Jason M. Adams, Gibbs GidenMr. Adams may be contacted at
jadams@gibbsgiden.com
Yes, Virginia, Contract Terms Do Matter: Financing Term Offers Owner an Escape Hatch
November 25, 2024 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, Musings welcomes Timothy R. Hughes, Esq., LEED AP. Tim (@vaconstruction on Twitter) is Of Counsel to the Arlington, Virginia firm of Bean, Kinney & Korman, P.C. In his practice as a business, corporate, and construction law attorney, Tim served as the previous Chair of the Construction Law and Public Contracts Section of the Virginia State Bar. He has served in numerous volunteer, board and leadership roles with such organizations as the Arlington Chamber of Commerce, the Northern Virginia Building Industry Association, Vanguard Services Unlimited, Leadership Arlington, Associated Builders & Contractors (Metro DC and Virginia), and numerous other volunteer and construction trade association activities. A regular speaker and writer, Tim is the lead editor of his firm blog, Virginia Real Estate, Land Use and Construction Law.
A recent Virginia case once again demonstrates that contract terms matter. An unusual financing term allowed the owner of a project a complete escape from any liability on a project despite significant work being performed. The opinion from the Circuit Court of Norfolk involved five separate cases consolidated together, four claims by subcontractors and one by the general contractor Turner. All five cases hinged on an unusual financing clause in Turner’s contract with the other. That provision stated:
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Haight Proudly Supports JDC's 11th Annual Bike-A-Thon Benefitting Pro Bono Legal Services
July 21, 2018 —
Stephen M. Tye - Haight Brown & Bonesteel LLPHaight proudly donates to the Justice & Diversity Center of the Bar Association of San Francisco’s 11th Annual “Ride for Justice” in support of San Francisco attorney Stephen M. Tye. This is Mr. Tye’s second year participating in the JDC’s Bike-A-Thon, which raises funds to provide pro bono legal services programs that provide access to justice for thousands of San Franciscans every year.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen M. Tye, Haight Brown & Bonesteel LLPMr. Tye may be contacted at