Condos Down in Denver Due to Construction Defect Litigation
November 06, 2013 —
CDJ STAFFA new report suggests that fears of construction defect litigation may be the cause of the slump in condo building in the Denver area. The Denver Business Journal reports that the Denver Regional Council of Governments commissioned the study by Economic & Planning Systems. The conclusion of the report was that the only type of condominium likely to be built is high-cost units with high profit margins. This is not good news for the DRCOG, which is seeking to create more affordable housing.
The report found that builders assess the likeliness of being sued “is nearly 100 percent,” that costs of addressing construction defects are 12% higher than at apartment complexes, and that preparing for litigation adds about $15,000 to the cost of a condo unit.
One possible remedy is to reform Colorado’s construction defect laws. Bob Muphy, the mayor of Lakewook and an advocate of construction defect litigation reform, said that he sees “this as a verification of what I’ve been talking about.”
Read the court decisionRead the full story...Reprinted courtesy of
There Was No Housing Bubble in 2008 and There Isn’t One Now
January 17, 2022 —
Ramesh Ponnuru - BloombergHousing markets are red hot, with prices up more than 18% from November 2020 to November 2021. That’s an acceleration over the previous two years, which saw increases of 4% and 8% each. It’s also a faster rate than the U.S. experienced during the housing boom of the 2000s that preceded the Great Recession.
That comparison is causing some heartburn. “Are we in another housing bubble?” asked Mark Zandi, chief economist at Moody’s. The consensus, shared by Zandi, is that the answer is no — or, at least, that today’s bubble is different and less dangerous than the last one. Lending standards are more strict than they were 15 years ago, for example, which ought to mean that fewer homeowners are at risk of defaulting if prices fall.
Read the court decisionRead the full story...Reprinted courtesy of
Ramesh Ponnuru, Bloomberg
A License to Sue: Appellate Court Upholds Condition of Statute that a Contracting Party Must Hold a Valid Contractor’s License to Pursue Action for Recovery of Payment for Contracting Services
June 21, 2017 —
Omar Parra & Jesse M. Sullivan - Haight Brown & Bonesteel LLPCalifornia Business & Professions Code section 7031(a) requires a party to have contractor’s license in order to maintain an action for compensation for services performed for which a contractor’s license is needed. In Phoenix Mechanical Pipeline, Inc. v. Space Exploration Technologies Corp., No. B269186 (2017 WL 2544856) (Cal. Ct. App. June 13, 2017), the Court of Appeal for the Second Appellate District considered the scope of this statute in denying, in part, Phoenix Mechanical Pipeline, Inc.’s (“Phoenix Pipeline”) appeal of a trial court ruling granting Space Exploration Technologies Corporation’s (“SpaceX”) demurrer to Phoenix Pipeline’s second amended complaint, without leave to amend.
Phoenix Pipeline filed the underlying lawsuit for, among other claims, breach of contract and breach of the duty of good faith and fair dealing arising from an agreement with SpaceX for Phoenix Pipeline to perform various plumbing, concrete removal and electrical services. Phoenix Pipeline alleged SpaceX paid for such services from 2010 to October 2013, but failed to pay Phoenix for services performed from October 2013 to August 2014, totaling just over $1,000,000. According to Phoenix Pipeline, this work was performed pursuant to a series of invoices, which constituted individual agreements between SpaceX and Phoenix Pipeline.
Reprinted courtesy of
Omar Parra, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Parra may be contacted at oparra@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Faulty Workmanship Based Upon Exclusion for Contractual Assumption of Liability
August 06, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Supreme Court for West Virginia determined the policy's contractual assumption exclusion barred coverage for the general contractor based upon claims of faulty workmanship. J.A. St & Assocs. v. Bitco Gen. Ins. Corp., 2019 W. Va. LEXIS 205 (May 1, 2019).
J.A. Street & Associates, Inc. entered a contract with the developer, Thundering Herd Development, L.L.C., to build a commercial shopping center on seventy-eight acres of land. Street agreed to oversee the site preparation for the development and the construction of many of the buildings. Thundering Herd retained an engineering firm, S&ME, Inc. to do geotechnical exploration and to provide advice regarding land preparation for the shopping center. Thundering Heard also entered an agreement with the Target Corporation to construct a store on a pad to be prepared at the shopping center.
Street hired subcontractors to prepare the site by grading the land and installing fill material. A slope was constructed at the rear of the proposed Target site, but it failed, causing a landslide, damage to the pad, and damage to adjacent property owned by a third party. Thundering Heard incurred $721,875 in additional costs to repair this slope, reconstruct the Target site, and compensate the neighbor for the damage to the adjacent property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Claim Preclusion: The Doctrine Everyone Thinks They Know But No One Really Knows What it Means in Practice
April 25, 2023 —
Garret Murai - California Construction Law BlogGenerally, I think restraint in litigation is a good thing. Don’t go crazy on your claims, don’t go nut-so in your discovery, and don’t present your case at trial in a way that causes the judge and/or jury to raise their eyebrows or shake their heads in disbelief. But, as with nearly everything, there’s always an exception. One of which is: don’t hold back on a claim because you “think” you might be able to bring it later, because you might not be able to as the next case, 5th and LA v. Western Waterproofing Company, Inc., 87 Cal.App.5th 781 (2023), demonstrates.
The 5th and LA Case
At the outset, let me first say how much I enjoyed reading this case based on the writing alone. The case, as the 2nd District Court of Appeals states, involves “a second lawsuit about an increasingly leaky roof.”
In 2012, property owner 5th and LA hired roofing contractor Western Waterproofing Company, Inc. to remove and recoat a parking lot that served also served as the roof over retail and office space below. Western completed its work in July 2012 and almost immediately 5th and LA noticed water that the coating was failing causing water leaks to the interior of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Preliminary Notice Is More Important Than Ever During COVID-19
June 01, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Construction Law Musings, we welcome Justin Gitelman. Justin is the Content Coordinator at Levelset, where over 500,000 contractors and suppliers connect on a cloud-based platform to make payment processes stress-free. Levelset helps contractors and suppliers get payment under control, and sees a world where no one loses a night’s sleep over payment.
As the construction industry continues to adjust to the coronavirus and an uncertain future, contractors are struggling to get paid. During the COVID-19 pandemic, construction businesses across Virginia need to do everything they can to protect their payments, and get paid faster. One simple action that can help fight payment delays: sending preliminary notice on every job.
Subcontractors and suppliers should send preliminary notices out to the GC, project owner, and/or lender at the start of every single project. These tools allow contractors to make themselves visible on crowded job sites, helping contractors get paid more quickly, and, in some cases, securing their right to file a mechanics lien or bond claim.
Preliminary Notices in Construction
The purpose of a preliminary notice is to allow each member of a construction project to know who you are and what work you’ll be performing. With coronavirus in mind, contractors can use preliminary notices to remind the hiring party of their payment expectations. When you submit a preliminary notice on every project, you’ll have legal protection in your corner while also giving yourself a greater opportunity to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrissghill@constructionlawva.com
North Carolina Learns More Lessons From Latest Storm
October 16, 2018 —
Pam Radtke Russell - Engineering News-RecordThere’s no big wall planned to protect North Carolina’s coast from storm surge. There’s no massive tunnel system proposed to keep floodwaters away from populated areas. There are no grant-funded resilience competitions to help the state plan to manage water more effectively.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com