Risk Protection: Force Majeure Agreements Take on Renewed Relevance
November 30, 2020 —
Michael E. Carson - Construction ExecutiveForce majeure clauses have been standard in contracts dating back hundreds of years in the United States—and even longer in Europe. “Force majeure,” which is French for “greater force,” removes liability for unforeseen events that prevent parties from fulfilling contractual obligations.
In a year defined by the COVID-19 pandemic, these clauses have gone from boilerplate basics to something worthy of further examination and attention in order to minimize risk for all parties involved in a construction project. Prior to COVID-19, drafters might have considered a localized or regional event that would lead to invoking a force majeure clause. It is doubtful, however, that anybody envisioned the impact on such a world-wide scale.
UNDERSTANDING THE AGREEMENTS
Force majeure clauses cover unforeseen events, a broad term that encompasses both acts of God and human-caused incidents. These range from natural disasters like earthquakes and hurricanes to acts of terrorism, strikes, political strife, government actions, war and other difficult- or impossible-to-predict disruptions. When such an event occurs, the force majeure clause attempts to remove, or at least reduce, uncertainty as to the rights and liabilities of the parties to the agreement.
Reprinted courtesy of
Michael E. Carson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Carson may be contacted at
michael.carson@nationwide.com
Carbon Sequestration Can Combat Global Warming, Sometimes in Unexpected Ways
April 02, 2024 —
Michael S. McDonough, Robert A. James & Amanda G. Halter - Gravel2Gavel Construction & Real Estate Law BlogWhether by land, by sea or through human innovation, carbon sequestration is likely coming to (or already happening in) a destination near you. As our planet, overdosed on greenhouse gases, battles climate disasters, a logical solution is to simply stop pumping carbon dioxide into the air. Legislation worldwide is aimed at that target, but reducing output alone may not be enough. There are still billions of tons of extra CO2 already in the atmosphere—this crossroads is where sequestration comes into play.
Carbon sequestration is exactly what it sounds like—the storage of CO2. Once carbon is sucked out of the air, or in some cases pulled directly from industrial smokestacks, sequestration can be undertaken in a lot of different ways. Carbon storage happens naturally, when forests and oceans absorb and convert CO2 into organic matter, but carbon dioxide can also be artificially injected into deep underground rock formations (or wells), or in some cases technological approaches repurpose carbon into a resource like concrete, or as a catalyst in a closed-loop industrial system. However it’s accomplished, the point of sequestration is to stabilize carbon and ensure it doesn’t creep back into our atmosphere. Researchers, like those at the United Nations’ Intergovernmental Panel on Climate Change, now say that CO2 removal is vital to keeping global warming to 1.5 degrees Celsius (past that threshold, climate change could reach catastrophic levels). A 2023 University of Oxford study estimated that, currently, about two billion metric tons of carbon dioxide are being removed each year, primarily through land management (i.e., planting trees), and suggested that we need to double that amount to avoid dangerous global warming levels.
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Robert A. James, Pillsbury and
Amanda G. Halter, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Court of Appeals Upholds Judgment on behalf of Homeowners against Del Webb Communities for Homes Riddled with Construction Defects
February 26, 2015 —
Law Offices of Kasdan Weber Turner LLPARIZONA COURT OF APPEALS UPHOLDS LOWER COURT DECISION APPROVING $13,703,039 JUDGMENT ON BEHALF OF 460 SUN CITY GRAND HOMEOWNERS AGAINST DEL WEBB COMMUNITIES, INC., A SUBSIDIARY OF PULTEGROUP, INC., FOR HOMES RIDDLED WITH CONSTRUCTION DEFECTS
--
In a separate case, an Arizona Superior Court awards $10,619,640 to another 279 Sun City Grand homeowners who sued Del Webb over construction defects, which Del Webb has appealed--
PHOENIX, Arizona – The Arizona Court of Appeals, Division One, [on Tuesday] issued a unanimous ruling upholding a lower court decision awarding $13,703,039 to 460 Sun City Grand homeowners who sued developer Del Webb Communities, Inc., a subsidiary of PulteGroup, Inc., for numerous construction defects that severely damaged the plaintiffs’ homes. Sun City Grand is an age-restricted community located in Surprise.
In a separate case, an Arizona Superior Court awarded $10,619,640 to another group of 279 Sun City Grand homeowners for multiple construction defects in their homes.
Stephen Weber, the managing partner in the Phoenix office of Kasdan Weber Turner LLP, which represents the homeowners, said that the case is based on construction defects that damaged the plaintiffs’ homes and took several years to resolve. The defects include defective windows, poorly installed stucco, expansive soil conditions that resulted in cracking of drywall, and deteriorating concrete foundation systems, among other problems.
“Del Webb placed an arbitration clause in the sales contracts and the homeowners honored it. The binding arbitration that includes the owners of 460 homes in Sun City Grand was completed in late 2011 when the arbitration panel unanimously awarded the homeowners $13,703,039. Del Webb then challenged the award in Superior Court and the Superior Court confirmed the award in full,” Weber explained. “Del Webb did not like the Superior Court ruling either and challenged it in the Court of Appeals. And now three justices of the Arizona Court of Appeals have unanimously affirmed the Superior Court order and the arbitration award stands. Now they will have the funds to repair their homes, restore their value, and live in comfort,” Weber said.
The $13,703,309 award includes amounts for home repairs, attorney fees, expert fees, court costs and pre-judgment interest. An additional $1,401,236 in post-judgment interest also accrued while the case was on appeal. The other construction defect case that awarded $10,619,640 to homeowners was not covered by binding arbitration.
Del Webb has also appealed that case which will now go through the appeals process. That could take two to three years and again the homeowners will have to wait for the final judgment, Weber noted.
Ken Kasdan, senior and managing partner of the Kasdan Weber Turner firm and one of the nation’s leading experts on construction defect litigation, said the defects are egregious. “The multiple defects rob them of pride of ownership,” he said. “A home is something that a homeowner wants to be proud of. Unfortunately, defective workmanship and poor construction have caused damage to the homes. Now these homes can be repaired and the homeowners will no longer have to deal with defective windows and cracked slabs. Developers need to understand that arbitration awards are final and binding,” Kasdan noted.
The Kasdan Weber Turner law firm has offices in Phoenix, Arizona and in Irvine, California and Walnut Creek, California. The firm represents property owners in major construction defect litigation. For more information on the firm, visit www.kasdancdlaw.com. Stephen Weber may be contacted at (602) 224-7800.
Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Eric D. Suben and Associate Laura Puhala Win Summary Judgment in Favor of Insurer, Determining it has No Duty to Defend
September 18, 2023 —
Traub LiebermanIn a declaratory judgment action brought before the United States District Court, Eastern District of New York, Traub Lieberman Partner Eric D. Suben and Associate Laura Puhala won summary judgment in favor of Plaintiff Foremost Signature Insurance Co. (“Foremost”), obtaining a declaration that it has no obligation to defend or indemnify Defendant 170 Little East Neck Road LLC (“Little East”) in an underlying state court personal injury action.
In the underlying action, a self-employed financial advisor leasing a suite for her business on the second floor of the property at 170 Little East Neck Road (the “Property”), sued Little East in New York Supreme Court, Suffolk County, alleging injuries resulting from slipping on ice on a walkway near an exterior door at the Property.
Reprinted courtesy of
Eric D. Suben, Traub Lieberman and
Laura S. Puhala, Traub Lieberman
Mr. Suben may be contacted at esuben@tlsslaw.com
Ms. Puhala may be contacted at lpuhala@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Washington Court Tunnels Deeper Into the Discovery Rule
July 09, 2019 —
Lian Skaf - The Subrogation StrategistOften times, properly analyzing when a statute of limitations begins to run – not just how long it runs – is crucial to timely pleading. In Dep’t of Transp. v. Seattle Tunnel Partners, 2019 Wash.App. LEXIS 281 (Was. Ct. App. Feb. 5, 2019), Division Two of the Court of Appeals of Washington addressed when the discovery rule starts the statute of limitations clock on a negligence cause of action. The court held that the statute of limitations begins to run when the plaintiff knows that the factual elements of the claim against the defendant exist. The clock starts to run even if the plaintiff wants to investigate the possibility of other contributing factors or the defendant identifies opposing viewpoints on the theory of the claim.
In this matter, the Washington State Department of Transportation (WSDOT) contracted with an engineering firm, WSP USA, Inc. (WSP), for an evaluation of the Alaskan Way Viaduct in 2001. As part of this project, WSP retained the services of Shannon and Wilson (S&W), another engineering firm, to conduct geological profile logs, groundwater-pumping tests, and prepare technical memoranda. In 2002, WSP and S&W installed a pumping well with an eight-inch steel casing (TW-2). In 2009, apparently based on the work done by WSP and S&W, WSDOT determined that a bored underground tunnel was the best option for replacing the viaduct.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
McCarthy Workers Test Fall-Protection Harnesses Designed to Better Fit Women
November 09, 2020 —
Corinne Grinapol - Engineering News-RecordAt project sites in Dallas, Houston and Atlanta, 27 McCarthy Building Co. women employees are testing a harness better suited to fit a diversity of body types than the more ubiquitous harnesses generally available at construction sites.
Reprinted courtesy of
Corinne Grinapol, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Holds Insurer Owes Duty to Defend Latent Condition Claim That Caused Fire Damage to Property Years After Construction Work
October 05, 2020 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogMost general liability policies only provide coverage for “property damage” that occurs during the policy period. Thus, when analyzing coverage for a construction defect claim, it is important to ascertain the date on which damage occurred. Of course, the plaintiffs’ bar crafts pleadings to be purposefully vague as to the date (or period) of damage to property. A recent Fifth Circuit decision applying Texas law addresses this coverage issue in the context of allegations of a condition created by an insured during the policy period that caused damage after the policy expired.
In Gonzalez v. Mid-Continent Cas. Co., 969 F.3d 554 (5th Cir. 2020), Gilbert Gonzales (the insured) was a siding contractor. In 2013, the underlying plaintiff hired Gonzales to install new siding on his house. In 2016, the underlying plaintiff’s house was damaged in a fire. The underlying plaintiff sued Gilbert in Texas state court alleging that when Gonzalez installed the siding in 2013, he hammered nails through electrical wiring and created a dangerous condition that caused a fire three years later in 2016.
At the time Gilbert performed construction work, he was insured by Mid-Continent Casualty Company. Mid-Continent disclaimed coverage to Gonzales on the basis that the complaint unequivocally alleged that property was damaged in 2016 and there were no allegations that property damage occurred prior to 2016 or was continuing in nature.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at