General Liability Alert: ADA Requirements Pertaining to Wall Space Adjacent to Interior Doors Clarified
February 26, 2015 —
Lawrence S. Zucker II and Kristian B. Moriarty – Haight Brown & Bonesteel LLPIn Kohler v. Bed Bath & Beyond (No. 12-56727, filed February 19, 2015) the United States Court of Appeals for the Ninth Circuit affirmed a grant of summary judgment in favor of a department store related to the necessary moving clearance for an interior restroom door pursuant to the Americans With Disabilities Act ("ADA").
Plaintiff, Chris Kohler, is paraplegic and requires the use of a wheelchair to move in public. On two separate days in May 2011, Kohler used the restroom inside the Bed Bath & Beyond store in Riverside, California. Of relevance to the appeal, Kohler contends there was less than ten inches of strike-side wall space on the pull side of Bed Bath & Beyond’s restroom door which allegedly made it difficult for Mr. Kohler to pull open the restroom door by pushing off the strike-side wall with one hand while pulling the door handle with the other. He also contends there was less than three inches of strike-side wall or floor space on the push side of the door, making it difficult for Kohler to open the door from the push side. The door at issue did not have a latch which would stop the door from freely swinging on a hinge.
Reprinted courtesy of
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Zucker may be contacted at lzucker@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Google, Environmentalists and University Push Methane-Leak Detection
December 21, 2016 —
Mary B. Powers – Engineering News-RecordNational Grid, which serves New York, Massachusetts and Rhode Island, is set to be the second U.S. natural-gas utility to use technology advanced by Google Earth, the Environmental Defense Fund (EDF) and Colorado State University to boost large-scale methane-leak detection. It is launching a $3-billion effort to replace gas pipelines in New York. The technology uses cutting-edge spatial analytics methods and methane sensors, specially fitted to Google Street View cars, to identify leaks and accurately measure the amount of methane escaping.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Storm Debby Is Deadly — Because It’s Slow
September 16, 2024 —
Brian K Sullivan - BloombergTropical Storm Debby has killed at least five people as it churns across the US East, where it’s expected to inflict $1 billion or more in damage and losses.
One reason for the storm’s destructive power: It’s moving very slowly.
Although Debby came ashore with hurricane-strength winds, its rainfall — forecast to exceed two feet in some areas — is even more dangerous.
The St. Marys River in northern Florida rose more than 10 feet in one day, while New York will likely see downpours from Debby later in the week. Homes, businesses and farms may be deluged, putting crops and infrastructure at risk.
Read the court decisionRead the full story...Reprinted courtesy of
Brian K Sullivan, Bloomberg
Traub Lieberman Partner Michael K. Kiernan and Associate Brandon Christian Obtain Dismissal with Prejudice in Favor of Defendant
November 27, 2023 —
Michael K. Kiernan & Brandon Christian - Traub LiebermanIn a 14-count breach of contract action brought in the Fifteenth Judicial Circuit in Palm Beach County, Florida, Partner Michael K. Kiernan and Associate Brandon Christian obtained dismissal with prejudice in favor of Defendant St. Joseph’s Episcopal Church of Boynton Beach, Florida (“Church”).
Plaintiffs, St. Joseph’s Episcopal School (“School”) and its benefactor, William Swaney, filed suit to enforce an alleged 99-year oral lease agreement which Swaney asserted had been made to him by a prior rector of the Church in exchange for his contributions to the School. Plaintiffs also sought emergency injunctive relief to allow the School to continue to operate on Church property. The Church maintained in part that the only lease in effect was a written lease, approved by the Church Vestry and the Diocese of Southeast Florida, and which the Church Vestry unanimously voted not to renew in 2022.
Reprinted courtesy of
Michael K. Kiernan, Traub Lieberman and
Brandon Christian, Traub Lieberman
Mr. Kiernan may be contacted at mkiernan@tlsslaw.com
Mr. Christian may be contacted at bchristian@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Resolve to Say “No” This Year
January 26, 2016 —
Christopher G. Hill – Construction Law MusingsWe hear all of the time how to “get to ‘yes'” and how doing so can lead to more business and of course more business leads to more profits. Purely logical, right? Without construction owners with work for general contractors to perform and general contractors hiring subcontractors to perform that work, construction grinds to a halt and clients and friends of mine in the construction industry don’t make money. For this to happen, “yes” has to happen more often than not. So, why the title of this post?
Chalk it up to spending much if not all of my time as a construction attorney either anticipating or dealing with the Murphy’s Law ruled nature of the construction world or to the “Monday morning quarterback” nature of my profession, but I see numerous instances where not taking the job or signing the bad contract would have led to a better outcome than performing the work. What do I mean by this? I mean that as a construction company (particularly one that is lower down the “payment chain” and therefore less in control of the flow of money), you need to carefully evaluate not only the contract presented, but whether you get a good feeling about the party with whom you are contracting.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
ISO’s Flood Exclusion Amendments and Hurricane Ian Claims
October 03, 2022 —
Randy J. Maniloff - White and Williams LLPI understand that it may seem early to be addressing possible coverage issues, under homeowner’s policies, for the devastation in Florida caused by Hurricane Ian. At the moment, those affected are dealing with a major catastrophe and possibly life-altering situation.
But I’m a realist. While we all have those impacted in our thoughts and prayers, that’s not going to rebuild the state or people’s lives. Money is. And when it comes to the source of money to do so, insurance will be far and away the first and principal place that people turn.
Indeed, even before it started to rain, Florida Governor DeSantis was discussing the availability of insurance for his citizens, as well as plenty of articles written forecasting how significant the insurance impact could be. If Covid-19 taught us anything about the pursuit of insurance, the discussion begins the second the need arises.
When it comes to insurance coverage for hurricanes, the starting place is always the same. Homeowner’s [and commercial property] policies generally cover wind damage and exclude flood damage. For flood coverage, a flood policy is needed, offered by the National Flood Insurance Program or the private market.
Read the court decisionRead the full story...Reprinted courtesy of
Randy J. Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
Insurer in Bad Faith Due to Adjuster's Failure to Keep Abreast of Case Law
June 13, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that the insurer acted in bad faith when the claim was denied based on the adjuster's lack of knowledge of recent case law in Washington. Sec. Nat'l Ins. Co. v. Constr. Assocs. of Spokane, 2022 U.S. Dist. LEXIS 53533 (E.D. Wash. March 24, 2022).
Construction Associates of Spokane was a general contractor hired for a project at the Paulsen Building in Spokane. Construction Association hired a subcontractor, Merit Electric, for whom Mark Wilson worked. Wilson was seriously injured on August 20, 2016. He sued the Construction Associates along with other defendants three years later.
Construction Associates tendered to Merit Electric's broker, Alliant Insurance Services, Inc. Alliant forward the tender to Security National. The tender letter included a certificate of insurance issued by Alliant to Contractor Associates on September 3, 2019 and the subcontract with Merit. The subcontract required Merit to maintain CGL coverage with limits of $1 million. Further, the subcontractor was to issue certificate of insurance to the Contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com