Trade Contract Revisions to Address COVID-19
August 23, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPMany trade contracts contain a clause that may protect trade contractors from catastrophic events like pandemics. These clauses are known as force-majeure clauses (covering acts of God). They basically say if these unavoidable events happen, the contractor is relieved of its obligations to the extent of the impact.
However, many common industry forms have not been updated to specifically address COVID-19. (They may be waiting to see how the courts treat their existing language first.) So to ensure impacts from COVID-19 are covered, a trade contractor should consider expressly adding it to the force-majeure clause. See the example below.
Notably, typical force-majeure clauses do not say the trade contractor gets more money. So an escalation clause could be added to the force-majeure clause.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Construction Upturn in Silicon Valley
August 17, 2011 —
CDJ STAFFWork resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.
A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
CA Supreme Court Expands Scope of Lawyers’ Statute of Limitations to Non-Legal Malpractice Claims – Confusion Predicted for Law and Motion Judges
August 26, 2015 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Lee v. Hanley (S220775 – Filed 8/20/2015), the California Supreme Court clarified the meaning of Code of Civil Procedure section 340.6 by holding that its limitations period applies to claims against attorneys “whose merits necessarily depend on proof that an attorney violated a professional obligation in the course of providing professional services.” Although it resolved a district split by finding that the statute governs for non-legal malpractice claims against attorneys including those of non-clients, by having the statute’s applicability “turn on the conduct alleged and ultimately proven, not on the way the complaint was styled,” this 5-2 decision also increased the specter of creative pleading and lengthy litigation.
In Lee, the client had advanced $120,000 to cover attorney’s fees, costs and expert witness fees for the underlying litigation. After the case settled, the attorney advised the client that she had a credit balance of approximately $46,000. In response to her demand for a refund, the attorney then advised the client that she did not have a credit balance. More than one year later, the client filed suit to recover the $46,000, plus interest. The trial court sustained the attorney’s demurrer based on the one-year statute of limitations in section 340.6. The appellate court, however, reversed, reasoning that the client’s claim could be construed as one for conversion, in which case section 340.6 would not apply.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Lawsuit Gives Teeth to Massachusetts Pay Law
September 16, 2024 —
Joseph Barra - Robinson+Cole“The Massachusetts Legislature passed the state’s Prompt Pay Act 14 years ago to improve the downstream flow of money on most large-scale private construction projects. While the act established detailed protocols for administering applications for payment and other important construction phase processes, several questions about its interpretation and impact remained unanswered.
Over the years, I watched as a significant portion of the Massachusetts design and construction community either ignored the law’s exacting requirements or were unaware of their applicability. The first indication of how the act would be interpreted came in 2022, when the state appeals court decided Tocci Building Corp. v. IRIV Partners LLC. In that case, the court strictly construed the act. It held that an owner (and its agent) who failed to promptly advise the project’s general contractor of specific factual and legal reasons why it was withholding payment, coupled with a failure to certify that funds were being withheld in good faith, violated the law—making the contractor liable for the unpaid funds.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph Barra, Robinson+ColeMr. Barra may be contacted at
jbarra@rc.com
Keeping Detailed Records: The Best Defense to Constructive Eviction
October 24, 2023 —
Ben T. Welch & Ken Brown - Snell & WilmerInevitably, commercial property owners and managers will be faced with a claim by a tenant of constructive eviction. This article is intended to describe what constructive eviction is and to suggest what owners and managers can do to prepare for, and ward off, such claims.
Constructive eviction occurs where a tenant’s “right of possession and enjoyment” of the leasehold is disrupted by the landlord in a manner that renders the premises “unsuitable for the purposes intended.”i Put another way, it is interference that is so “substantial nature and so injurious as to deprive the tenant of the beneficial enjoyment of a part or the whole of the demised premises.”ii Although easy to describe in theory, constructive eviction can be devilishly difficult to determine in the real world. In litigation, determining when interference crosses over the line to constructive eviction is intensely fact-sensitive and resists sweeping generalizations.iii
For instance, Utah courts have held that tenants have been constructively evicted when they have been subjected to continual harassment or insults by the landlord or the landlord’s agent,iv prevented or impaired in their access to the leased premises during operating hours,v or when a landlord fails to provide an operable elevator (or other essential commercial amenities) necessary for a tenant’s business operations.vi By contrast, claims of “discomfort” or “inconvenience” have been rejected as a basis for constructive eviction.vii The same goes for claims that a landlord wrongfully served a three-day notice to pay or quit.viii
Generally, constructive eviction is an affirmative defense made in response to a landlord’s lawsuit for nonpayment of rent.ix It is not, as is commonly supposed, a basis for a tenant’s premature abandonment of the premises. In other words, the defense is raised after the tenant has vacated as a result of being effectively “evicted.”x Further, the defense requires the tenant to actually abandon the premises and do so within a “reasonable time” after the alleged interference.xi A tenant cannot stay in possession and simply refuse to pay rent on the basis of constructive eviction.xii
The key consideration in preparing for, and responding to, a claim of constructive eviction is keeping good records. A tenant claiming constructive evicting likely must prove that the issue was raised in a timely manner and, despite multiple entreaties, was never resolved.xiii As such, it is critical that landlords acknowledge tenant complaints as well as document in writing their efforts to ameliorate those complaints. While a landlord does not carry the burden of proof for constructive eviction, detailed documentation can thwart a tenant’s claim that a landlord has been inattentive or unwilling to address the tenant’s concerns.
Detailed records are also useful in disputes where a tenant claims substantial interference. “The whole point of constructive eviction is that the landlord basically drove the tenant out through the landlord’s action or inaction.”xiv As such, a landlord that is unable to document the steps taken in response to complaints will be grossly disadvantaged whereas the tenant, which had control and knowledge of the premises, will have a much easier time describing how the alleged interference deprived them of enjoying the premises.
Even with meticulous records, however, owners and managers may still face claims of construction eviction. In such instances, counsel should be retained to properly advise on compiling, preserving, and employing the evidence necessary to refute the tenant’s claims.
i Gray v. Oxford Worldwide Grp., Inc., 139 P.3d 267, 269 (Utah Ct. App. 2006).
ii Gray, 139 P.3d at 270 (citing Neslen, 254 P.2d at 850) (internal formatting omitted).
iii See Gray, 139 P.3d at 269–70 (citing Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847, 850 (Utah 1953)); Brugger v. Fonoti, 645 P.2d 647, 648 (Utah 1982).
iv See Gray, 139 P.3d at 270–71.
v Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847 (Utah 1953).
vi See Richard Barton Enterprises, Inc. v. Tsern, 928 P.2d 368, 375, 378 (Utah 1996) (citing Union City Union Suit Co. v. Miller, 162 A.D.2d 101, 556 N.Y.S.2d 864 (1990)).
vii See Myrah v. Campbell, 163 P.3d 679, 682–84 (Utah Ct. App. 2007).
viii Barton v. MTB Enterprises, 889 P.2d 476, 477 (Utah Ct. App. 1995); see also Brugger, 645 P.2d at 648 (stating that the tenant’s complaints revolved around standard problems commonly associated with building maintenance and did not rise to the level of substantial interference); viv Reid v. Mutual of Omaha Ins. Co., 776 P.2d 896, 898–900 (Utah 1989) (upholding trial court’s findings of fact concerning insufficiency of disruption so as to justify claim for constructive eviction).
ix See Kenyon v. Regan, 826 P.2d 140, 142 (Utah Ct. App. 1992).
x See Kenyon, 826 P.2d at 142.
xi See Kenyon, 826 P.2d at 142; see also Barton v. MTB Enterprises, Inc., 889 P.2d 476, 477 (Utah Ct. App. 1995); Brugger, 645 P.2d at 648.
xii See Kenyon, 826 P.2d at 142 (citing Fernandez v. Purdue, 518 P.2d 684, 686 (Utah 1974)).
xiii See Brugger, 645 P.2d at 648 (noting that while the tenant had raised legitimate issues concerning state of the premises, the landorld had taken steps to remedy the problems within a reasonable time) (citing 49 Am.Jur.2d, Landlord and Tenant, § 617).
xiv Barton, 889 P.2d at 477.
Reprinted courtesy of
Ben T. Welch, Snell & Wilmer and
Ken Brown, Snell & Wilmer
Mr. Welch may be contacted at bwelch@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Construction Stitch in Time
October 28, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s a cliche for a reason that “A Stitch in Time Saves Nine.” Why? Because it is almost always cheaper and more efficient in the long run to get something right the first time than to fix it later. This old adage is true in life, and particularly true in the world of construction.
Whether it’s measuring twice before making your bid, checking with your subcontractors and suppliers to be sure they haven’t missed anything when giving you a price, or yes (and you knew this was coming), being sure that your contracts are written as they should be and cover the bases. To use another construction related analogy, these types of basic practices create a great foundation for your construction project(s) that will (hopefully) see you through to a successful and profitable construction project.
Aside from the last of my examples, how can adding a knowledgeable construction attorney help with laying this foundation? We construction lawyers spend our days either dealing with problems that have occurred (not ideal), anticipating risks that could occur (better, though can lead to a relatively cynical world view), and advising clients before the fact of the potential risks and how to best avoid them (best). Speaking from experience, I would much rather spend my time keeping my construction clients making money and avoiding the pitfalls of the “Murphy’s Law” governed world of construction than spend time with them in court.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Updates to the CEQA Guidelines Have Been Finalized
February 06, 2019 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThe California Natural Resources Agency (CNRA) recently posted final adopted text for amendments to the CEQA Guidelines. The result of over five years of development efforts by the Governor’s Office of Planning & Research and CNRA, the amendments are the most comprehensive update to the CEQA Guidelines since 1998. In “Natural Resources Agency Finalizes Updates to the CEQA Guidelines,” Pillsbury environmental attorneys Norman F. Carlin, Kevin Ashe and Eric Moorman explore the wide range of issues covered in the amendments, including the new Vehicle-Miles-Traveled (VMT) methodology for analyzing transportation impacts; use of regulatory standards as significance thresholds; environmental baselines; and numerous procedural and technical improvements.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
COVID-19 Likely No Longer Covered Under Force Majeure
February 01, 2023 —
Rachel E. Pelovitz - Construction ExecutiveA recent decision by the U.S. Government Accountability Office (GAO) has shaken up construction contracts. While companies could claim “force majeure” to exempt themselves from contractual obligations during much of the pandemic, this decision challenges ongoing validity of those claims.
The decision was based on the Army Corps of Engineers deeming a bid from Boulder, Colorado–based American Mine Services (AMS) as nonresponsive because it included a COVID-19 force majeure clause. In reviewing the Corps’ decision, GAO—referencing the Federal Acquisition Regulation—found that “epidemics” and “quarantine restrictions” were already included in the contract between the Corps and AMS. Although AMS claimed that “COVID-19 is considered a force majeure event along with any other similar disease, epidemic or pandemic event,” the GAO concluded that this interpretation limited the rights of the government too much.
Reprinted courtesy of
Rachel E. Pelovitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.