Is it the Dawning of the Age of Strict Products Liability for Contractors in California?
March 30, 2016 —
Garret Murai – California Construction Law BlogIt was the Age of Aquarius.
And everything was changing. Politically, socially . . . and legally.
Through the 19th Century the doctrine of caveat emptor, literally “let the buyer beware,” was the rule of law. Under the doctrine a buyer was expected to protect him or herself against both obvious and hidden defects in a product.
It wasn’t until the late 1800s that U.S. courts began to impose implied warranties – for merchantability and fitness for a particular purpose – to protect consumers. But implied warranties were premised on their being a contract between the manufacturer and the user of a defective product, and by the mid 20th Century it was increasingly uncommon for consumers to purchase products directly from a manufacturer.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Contractor Owed a Defense
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Appellate Court reversed the lower court and found that the insured contractor was entitled to a defense for alleged construction defects. Acuity v. M/I Homes of Chicago, LLC, 2022 Ill. App. LEXIS 393 (Ill. Ct. App. Sept. 9, 2022).
The owners association (AOAO) sued M/I Homes for breach of contract and the implied warranty of habitability due to alleged defects. The AOAO alleged that the defects caused physical injury to the townhomes. There was resulting property damage such as damage to other building materials, windows and patio doors, and water damage to the interior of units. M/I Homes requested a defense from Acuity, but the request was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Construction Practice Team Obtains Summary Judgment and Dismissal of Labor Law Claims
October 01, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (August 23, 2024) – In Trujillo-Cruz v. City of New York, et al., New York Partner Inderjit Dhami, a member of New York Partner Meghan A. Cavalieri’s Construction Practice Team, recently obtained summary judgment and dismissal of the plaintiff's Labor Law §240(1), §241(6) and §200 claims dismissing the entire case against national developer and construction company clients.
The plaintiff alleged to have sustained injuries as the result of a construction site accident occurring on July 11, 2018, while in the scope of his employment as a laborer in connection with the construction/renovation of a residential apartment building in Brooklyn, New York. Specifically, the plaintiff alleged that he was injured when he was coming down from a ladder and fell on a 2”x 4”, causing him disabling injuries. The plaintiffs’ counsel articulated a $3 million settlement demand.
Labor Law §240(1) imposes absolute liability on a defendant where an injured worker engaged in the performance of covered construction work establishes that a safety device proved inadequate to shield him from elevation-related harm, and that the defendant’s failure to provide an adequate safety device proximately caused the injuries alleged. The plaintiff first testified that he stepped on the 2” x 4” after he came down off of the ladder, but his counsel then prompted him to recalibrate his testimony by asking whether the accident arose when he was coming down the ladder or after he had come down off of the ladder. The plaintiff changed his testimony, alleging that the accident arose as he was coming down the ladder and that he remained partially on the ladder when he stepped on the piece of formwork and fell. Inderjit argued that the plaintiff’s reframing of his deposition testimony was immaterial for purposes of the Labor Law § 240 (1) analysis. Irrespective of whether the plaintiff was on solid ground or had one foot on the ladder at the time of the occurrence, his Labor Law § 240 (1) claim was unavailing in that the accident did not arise as a result of the type of extraordinary elevation-related peril protected by Labor Law § 240 (1). Justice Maslow agreed and dismissed the plaintiff’s Labor Law § 240 (1) claims.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
No Damages for Delay May Not Be Enforceable in Virginia
January 08, 2024 —
Christopher G. Hill - Construction Law MusingsAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia. Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work. However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment. This left open the question as to which types of “diminishment” would be barred by the statute.
The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Public Contract Code 9204 – A New Mandatory Claims Process for Contractors and Subcontractors – and a Possible Trap for the Unwary
March 22, 2017 —
Alex R. Baghdassarian & Joseph S. Sestay – Peckar & Abramson, P.C.New California legislation affecting public works contractors was adopted pursuant to Assembly Bill 626, sponsored by the Union Trade Contractors Association of California and endorsed by various trade and contractor associations including the AGC. AB 626, which was intended to assist contractors in presenting claims against public agencies, affords new opportunities, and some potential pitfalls, to contractors and subcontractors submitting claims to public owners.
The legislation, codified at California Public Contract Code (PCC) section 9204, is effective for public works contracts entered into after January 1, 2017. All public entities (including the CSUS and the UC system), other than certain Departments of the State (CalTrans, High-Speed Rail Authority, Water Resources, Parks and Recreation, Corrections and Rehabilitation, General Services and the Military) are bound by the provisions of PCC Section 9204. PCC 9204 establishes a mandatory pre-litigation process for all claims by contractors on a public works project. It is an attempt to address the reluctance of public owners to promptly and fairly negotiate change orders on projects, putting some teeth to the mandate of existing law under PCC Section 7104, which precludes public owners from shifting to the contractor the risk of addressing differing subsurface and/or concealed hazardous site conditions.
Reprinted courtesy of
Alex R. Baghdassarian, Peckar & Abramson, P.C. and
Joseph S. Sestay, Peckar & Abramson, P.C.
Mr. Baghdassarian may be contacted at abaghdassarian@pecklaw.com
Mr. Sestay may be contacted at jsestay@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
It’s Getting Harder and Harder to be a Concrete Supplier in California
December 04, 2018 —
Garret Murai - California Construction Law BlogIn 2015, the California state legislature passed AB 219, which amended the state’s prevailing wage law to add Labor Code section 1720.9, which requires the payment of prevailing wages to “ready-mixed concrete” drivers on state and local public works projects.
Ready-mixed concrete suppliers filed suit in Allied Concrete and Supply Co. v. Baker (September 20, 2018) U.S. Court of Appeals for the Ninth Circuit, challenging the law on the ground that, because AB 219 singled out ready-mixed concrete drivers but not other drivers of materials on state and local public works projects, the law violated the Equal Protection Clause of the U.S. Constitution.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Court Denies Insurers' Motions for Summary Judgment Under All Risk Policies
June 05, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that the insurers could not escape coverage by summary judgment under their all risk policies. Eagle Harbour Condo Assoc'n v. Allstate Ins. Co., 2017 U.S. Dist. LEXIS 54761 (W.D. Wash. April 10, 2017).
Eagle Harbour Condominium Association sued several of its insurers who denied coverage for hidden water damage. Various insurers provided coverage from 1988 to 2015.
The Association asserted that wind-driven rain and inadequate construction allowed water to penetrate the buildings' sheathing and framing, causing decades of deterioration and decay, until the damage was exposed to view in August 2014. The insurers claimed that the loss resulted from poor decisions in constructing and inadequately maintaining a stucco building in the wet and windy Pacific Northwest. The Association argued that the policies did not explicitly exclude damage caused by wind-driven rain, so there was coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Three Recent Cases Strike Down Liquidated Damages Clauses In Settlement Agreements…A Trend Or An Aberration?
November 01, 2021 —
Adam M. Tuckman - ConsensusDocsBeginning more than one century ago, owners and contractors generally have adopted the convention of including liquidated damages in their contracts to fix potential liability for delay (and other losses) at the inception of the project. The proliferation of liquidated damages clauses in modern contracts can be attributed to economic and legal factors. From the owner’s standpoint, it may be exceedingly difficult to prove the actual cost impact of a delayed completion of the project. A properly calculated liquidated damages rate would save the owner the significant expense of quantifying its delay damages. On the contractor’s side, a reasonable amount of liquidated damages may be preferable to uncapped or unknown liability, allowing the contractor to more accurately price its bid and efficiently allocate risk.
Coinciding with, or perhaps a leading cause of, the industry’s embrace of liquidated damages provisions, was the shift in courts throughout the country from disfavoring such clauses to accepting them (within limits) as an appropriate exercise of contract rights. While some variation exists among the states, courts have generally recognized that liquidated damages clauses are a viable alternative to proof of actual loss so long as (i) actual losses were difficult to quantify, and (ii) the stipulated sum bears a reasonable relationship to the anticipated loss at the time of contracting. See, e.g., Restatement (Second) of Contracts § 356. Conversely, a clause that penalizes the breaching party rather than serving as an estimate of probable loss is likely to be found unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of