Attorney’s Fees Entitlement And Application Under Subcontract Default Provision
May 06, 2019 —
David Adelstein - Florida Construction Legal UpdatesMany subcontracts contain a provision in the default section that reads something to the effect:
“Upon any default, Subcontractor shall pay to Contractor its attorney’s fees and court costs incurred in enforcing this Subcontract or seeking any remedies hereunder.”
Oftentimes, a party may wonder as to the enforceability of the provision and how it is applied in the context of a dispute between a contractor and its subcontractor where both parties have asserted claims against the other.
In an opinion out of the Middle District of Georgia, U.S. f/u/b/o Cleveland Construction, Inc. v. Stellar Group, Inc., 2019 WL 338887 (M.D.Ga. 2019), a subcontractor and prime contractor on a federal construction project each asserted claims against the other in the approximate amount of $4 Million, meaning there was a potential $8 Million swing in the dispute.
The subcontract contained a provision entitling the contractor to recover attorney’s fees incurred in enforcing the subcontract or seeking remedies under the subcontract upon any default, identical to the provision above.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Arkansas Federal Court Fans the Product Liability Flames Utilizing the Malfunction Theory
September 14, 2020 —
Michael J. Ciamaichelo - The Subrogation StrategistTo establish a product liability claim in Arkansas, the plaintiff must prove that the product was supplied in a defective condition, which rendered it unreasonably dangerous and that the defective condition was the proximate cause of the claimed damage or injury. Ordinarily, a plaintiff relies upon direct evidence of a product defect to establish its product liability claim. However, in some cases, the product sustains so much damage that it is impossible for a plaintiff to obtain direct evidence of a defect.
The malfunction theory allows a plaintiff in a product liability action to establish a defect through circumstantial evidence, when direct evidence of a defect no longer exists. In order to utilize the malfunction theory, a plaintiff must present evidence that an unspecified product defect was the most likely cause of the damage/accident and rule out all other possible causes of the damage/accident. In Am. Nat’l Prop. & Cas. Co. v. Broan-Nutone, No. 5:18-CV-5250, 2020 U.S. Dist. LEXIS 117116, the United States District Court for the Western District of Arkansas ruled that the plaintiff offered sufficient evidence under “the malfunction theory” to defeat a summary judgment motion in a product liability action involving a bathroom fan that was destroyed in a fire.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
BWB&O ranks as a 2025 Best Law Firm by Best Lawyers®
December 10, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to announce the firm has been recognized for its fifth consecutive year in the 2025 edition of Best Law Firms® and is ranked by Best Lawyers® regionally in three practice areas. To read the publication, please click here.
Metropolitan Tier 1
Las Vegas: Litigation – Construction
Orange County: Litigation – Construction
Metropolitan Tier 2
Orange County: Family Law
San Diego: Litigation – Real Estate
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
St. Mary & St. John Coptic Orthodox Church v. SBS Insurance Services, Inc.
January 18, 2021 —
Michael Velladao - Lewis BrisboisIn St. Mary & St. John Coptic Orthodox Church v. SBS Insurance Services, Inc., ----Cal.App.5th--- (November 23, 2020), the California First District Court of Appeal reversed the trial court's entry of judgment in favor of SBC Insurance Services ("SBC") regarding a claim for water damage sustained by a residence owned by St. Mary & John Coptic Church ("St. Mary") under property coverage afforded by a policy issued by Philadelphia Indemnity Insurance Company ("Philadelphia"). The policy was procured by SBC on behalf of St. Mary. Philadelphia denied coverage of the claim based on the vacancy exclusion in its policy, but entered into a settlement and loan receipt agreement, whereby St. Mary gave Philadelphia the right to control litigation in St. Mary’s name against SBC or third parties who might be liable for the loss in exchange for a loan of money to repair and remediate the damage sustained by the residence. The loan was to be repaid out of any recovery made against SBC or third parties. After a bench trial, the trial court found in favor of SBC and held that the vacancy exclusion was ambiguous. Essentially, the exclusion did not apply to the time period prior to the time St. Mary purchased the residence, such that the 60-day vacancy requirement could not be satisfied. The trial court reasoned that since St. Mary did not have an insurable interest in the property before it purchased the property, the 60-day requirement did not include the period before such residence was purchased and St. Mary held an insurable interest.
The parties’ dispute arose of out of the Pope of the Coptic Church requesting St. Mary to purchase a home to be used as his papal residence in the Western United States. St. Mary also intended to use the home as a residence for visiting bishops. The home was purchased on May 28, 2015. As part of the purchase, SBC placed the home under St. Mary’s commercial policy, rather than purchasing a separate homeowner’s policy for the residence. Subsequently, the home sustained water damage due to a broken pipe. The water damage was discovered on July 24, 2015, 57 days after the inception of the Philadelphia policy and the loss. St. Mary tendered the property loss to Philadelphia, which denied coverage of the claim based on the reasoning that the home had been vacant for 60 consecutive days prior to the loss. Subsequently, St. Mary filed suit against SBC after securing the loan receipt agreement with Philadelphia based on the argument that the vacancy exclusion barred coverage of the claim and SBC breached its duty of care by not securing the proper coverage of the home. The trial court entered judgment in favor of SBC finding that the vacancy exclusion did not apply to bar coverage of the loss, such that SBC did not breach its duty of care owed to St. Mary as its broker.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
A Bill for an Act Concerning Workers’ Compensation – 2014 Edition
January 13, 2014 —
W. Berkeley Mann, Esq. - Higgins, Hopkins, McLain & Roswell, LLCWorkers’ compensation (“WC”) costs are a significant portion of the labor costs experienced by construction companies. These costs have typically risen over time due to the “experience modification factor.” This term means the amortized cost of past claims recovered through future premiums charged by an insurer to an employer. As a company’s claims go up in both number of claims and total expense of claims over time, the experience modifier increases as a multiplier of the base WC premium. As with other general medical costs, the question is not whether the cost of claims with a medical component will go up, but rather the rate at which they will increase from year to year.
It is with these facts of life in mind that it is reported that the Colorado legislature will take up a bill concerning WC benefits in the 2014 session. This bill, if passed, will have the likely effect of dramatically increasing the cost of WC claims to the construction industry - along with all other Colorado employers.
The draft bill has three distinct changes for the current law, each of which serves to change the delicate balance of rights and obligations of employers and employees under existing law.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Esq.W. Berkeley Mann, Esq. can be contacted at
mann@hhmrlaw.com
Court Agrees to Stay Coverage Matter While Underlying State Action is Pending
October 29, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court granted the insured's motion to stay the coverage action while the construction defect case was pending in state court. Auto Owners Ins. Co. v. Essex Homes Southeast, Inc., 2014 U.S. Dist. LEXIS 133120 (D. S.C., Sept. 23, 2014).
The homeowners sued Essex Homes in state court for construction defects in a home built and sold to them by Essex Homes. The suit sought damages for property damage based on negligence, breach of implied warranty, and breach of express warranties arising out of the alleged construction defects. The complaint alleged that a water leak in the house caused water damage and resulted in mold growth that was not discovered for several years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Rules Planned Development of Banning Ranch May Proceed
June 10, 2015 —
Kristian B. Moriarty and Lawrence S. Zucker II – Haight Brown & Bonesteel, LLPIn Banning Ranch Conservancy v. City of Newport Beach (filed 5/20/2015, No. G049691), the California Court of Appeal, Fourth District, held the Environmental Impact Report prepared by the City of Newport Beach for the partial development of Banning Ranch complied with California environmental protection statutes and local ordinances.
Under the California Environmental Quality Act (“CEQA”), a city desiring to approve or carry out a project that may have significant effect on the environment must prepare an environmental impact report (“EIR”) designed to provide the public with detailed information about the effect which a proposed project will have on the environment. The California Coastal Act of 1976 provides for heightened protection of environmentally sensitive habitat areas (“ESHA”) defined as any “area in which plant or animal life or their habitats are either rare or especially valuable because of their special nature or role in an ecosystem and which could be easily disturbed or degraded by human activities and developments.”
In 2006, the City of Newport Beach adopted a General Plan for the physical development of the city. The plan specifically identifies Banning Ranch as having significant value as a wildlife habitat and open space resource for citizens. The general plan includes a primary goal of complete preservation of Banning Ranch as open space. To the extent the primary goal cannot be achieved, the plan identifies a secondary goal allowing limited development of Banning Ranch “to fund preservation of the majority of the property as open space.” The plan also requires the City to coordinate any development with the state and federal agencies.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com; Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Certificates Of Merit For NC Lawsuits Against Engineers And Architects? (Still No)(Law Note)
April 22, 2019 —
Melissa Dewey Brumback - Construction Law in North CarolinaCertificates of Merit are documents intended to show that a true issue exists with a professional’s work, prior to that person being sued. While North Carolina does require that a person suing a medical provider first have the matter reviewed by a professional (and attest to that in the Complaint), there is no requirement for any review prior to a lawsuit against an architect, engineer, or surveyor. Thus, anyone can file a lawsuit against an engineer/architect/surveyor without first having their case eyeballed reviewed by another professional.
Over the years, there have been attempts at adding a Certificate of Merit requirement to design professional lawsuits. See, for example, examples here: from
2005; from
2007; from
2011; and from
2013.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com