English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Multisensory Marvel: Exploring the Innovative MSG Sphere
August 14, 2023 —
Aarni Heiskanen - AEC BusinessThe U.S. entertainment industry keeps amazing me. The first Disneyland opened in 1955, and ever since the industry has created experiences that amazingly combine architecture and technology.
The latest example is the
MSG Sphere which will open its doors in Las Vegas, Nevada, on September 29, 2023. It is a large-scale immersive entertainment space hosting various events, concerts, competitions, and residencies from the world’s biggest artists.
The world’s largest spherical structure
The MSG Sphere was initially a partnership between the Madison Square Garden Company (MSG) and Las Vegas Sands Corporation, which Apollo Global Management later replaced. The project’s final construction costs were $2.3 billion.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
The Top 10 Changes to the AIA A201: What You Need to Know
May 24, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Melissa Dewey Brumback. Melissa is a construction law attorney with Ragsdale Liggett in Raleigh, North Carolina. Aside from the fact that she is a UNC grad and fan, she’s okay!
In 2017, as it does every ten years, the American Institute of Architects (AIA) updated most of its standard form contract documents, including the A201 General Conditions. This cycle, the contract changes are evolutionary in nature, not revolutionary. Even so, it is crucial to know the changes to avoid making a fatal mistake that could cost you money on a construction project. In reverse order, the top 10 changes you need to know include:
# 10: Differing Site Conditions
Prior editions of the A201 provided that upon encountering differing site conditions, the Contractor was to promptly provide notice to the Owner and Architect, before the conditions are disturbed, and in no event later than 21 days after the conditions were first observed. A201–2017 shortens the time for notice from 21 to 14 days.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
COVID-19 Pandemic Preference Amendments to Bankruptcy Code Benefiting Vendors, Customers, Commercial Landlords and Tenants
May 03, 2021 —
Andrew Arthur & Steven Ostrow - White and Williams LLPOver the last three months, Congress has passed major pieces of legislation primarily in response to the COVID-19 pandemic, including the Consolidated Appropriations Act of 2021 (CAA), which was signed into law on December 27, 2020. In addition to funding the federal government and a second round of pandemic relief, the CAA contains several amendments to the Bankruptcy Code. One of the amendments provides preference protection to commercial landlords and suppliers who receive overdue payments from their tenants or customers under agreements made on or after March 13, 2020 to postpone the payment of rent or supplier charges.
The preference amendments encourage these creditors to afford their customers and tenants payment deferment arrangements without the risk that the companies will clawback the payments as preferences if they later file for bankruptcy protection. The amendments should facilitate workouts of distribution and leasing agreements to help distressed businesses recover and repay arrearages as COVID-19 related governmental restrictions are lifted this year.
Reprinted courtesy of
Andrew Arthur, White and Williams LLP and
Steven Ostrow, White and Williams LLP
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Arthur may be contacted at arthura@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
How Long does a Florida Condo Association Have to File a Construction Defect Claim?
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a post on Orlando Sentinel’s HOA & Condo Blog, sponsored by the firm Becker & Poliakoff, generally a Condominium Association has “4 years from turnover of control of the Condominium Association from the developer” to file a lawsuit for construction defects. However, the association may have additional time to file.
If defects from the original construction were discovered after the 4 years have lapsed, “[a] condominium association may still pursue a claim for latent defects,” which is one that “is hidden, and not discovered despite the exercise of due diligence, for the period of 4 years from turnover.” The Statute of Repose in Florida is “10 years from the date the building received its original Certificate of Occupancy.”
Read the court decisionRead the full story...Reprinted courtesy of
Saving Manhattan: Agencies, Consultants, Contractors Join Fight to Keep New York City Above Water
November 27, 2023 —
Pam McFarland & Corinne Grinapol - Engineering News-RecordIn densely populated cities surrounded on all sides by water—the borough of Manhattan in New York City as a prime example—the risks from sea level rise and climate change are not just hypotheticals; they are existential threats.
Reprinted courtesy of
Pam McFarland, Engineering News-Record and
Corinne Grinapol, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
BP Is Not an Additional Insured Under Transocean's Policy
April 01, 2015 —
Tred R. Eyerly – Insurance Law HawaiiResponding to a certified question from the Fifth Circuit, the Texas Supreme Court determined that BP was not an additional insured under Transocean's liability policy and had no coverage under the policy for the deaths caused by the explosion of the Deepwater Horizon. In re Horizon, 2015 Tex. LEXIS 141 (Tex. Feb. 13, 2015). We have previously posted on this case in the federal courts here and here.
Transocean owned the Deepwater Horizon, a mobile offshore drilling unit operating in the Gulf of Mexico pursuant to a contract with BP. After an explosion in April 2010, the rig caught fire, killing eleven crew members. Both Transocean and BP sought coverage under Transocean's primary and excess policies. Although they did not dispute that BP was an additional insured, Transocean and its insurers argued that BP was not entitled to coverage for pollution-related liabilities arising from subsurface oil releases in connection with the Deepwater Horizon accident.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Lenders and Post-Foreclosure Purchasers Have Standing to Make Construction Defect Claims for After-Discovered Conditions
August 12, 2013 —
W. Berkeley Mann, Jr. - Higgins, Hopkins, McLain & Roswelll, LLCThe Colorado Court of Appeals has decided a case which answers a question long in need of an answer: do banks/lenders have standing to assert construction defect claims when they receive title to a newly-constructed home following a foreclosure sale or deed-in-lieu of foreclosure? The decision was released on August 1, 2013, in the case of Mid Valley Real Estate Solutions V, LLC v. Hepworth-Pawlack Geotechnical, Inc., Steve Pawlak, Daniel Hadin, and S K Peightal Engineers, Ltd. (Colorado Court of Appeals No. 13CA0519).
The background facts of the case are typical of a Colorado residential construction defect case generally. A developer contracted for an analytical soil engineering report from a geotechnical engineering firm (H-P) which made a foundation recommendation. The developer’s general contractor then retained an engineering firm (SPKE) to provide engineering services, including a foundation design. The general contractor built the foundation in accordance with the H-P and SPKE criteria and plans.
The house was not sold by the developer and went into default on the construction loan. These events resulted in a deed-in-lieu of foreclosure to a bank-controlled entity which purchased the house for re-sale. Shortly after receiving the developer’s deed, the bank-related entity discovered defects in the foundation that resulted in a construction defect suit against the two design firms and related individuals.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.W. Berkeley Mann, Jr. can be contacted at