Spotting Problem Projects
October 26, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPPerhaps more than any other specialty contractor, electrical contractors bear the brunt of the “problem project.” Long after most other trades have completed their work and scattered in the wind, electrical contractors remain on site until the owner’s last inspection. And when the project is a “problem project,” the owner or prime contractor tend to liberally share their losses and liquidated damages among those specialty contractors remaining on site at the end. So what is an electrical contractor to do when the project starts coming off the rails?
What is a Problem Project?
First, it helps to identify the attributes of a problem project. While there are many negative qualities of a bad job, a problem project is one that busts budgets – whether labor, material, or time. Most commonly, the problem project will significantly exceed the labor budget. Because an electrical contractor’s most important (and understandably expensive) resource is its people, the labor budget is critical to the success of a job. When a project suffers delays or is ineptly managed, the labor costs soar, turning a potentially profitable job into a disaster.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Insurers Refuse Indemnification of Subcontractors in Construction Defect Suit
November 13, 2013 —
CDJ STAFFSMG Stone Co. Inc. and J. Colavin & Son Inc. were hired by Webcor Construction LP to install stone floor tiles at the Ritz-Carlton residences at the L.A. Live complex in Los Angeles. But the tiles began to crack even before installation was finished. The building management had all the tiles ripped out and replaced, although only 10% of the tiles were defective. The building management then claimed Webcor owed them $40 million, but settled for $8 million.
$7 million of that claim was paid by Steadfast Insurance Co., with the remaining $1 million paid by Webcor. The two other insurers involved, American Home and The Insurance Company of the State of Pennsylvania, are attempting to deflect Webcor or Steadfast from making claims against them.
Both insurers claim no obligation to indemnify the contractor or subcontractors as the claims do not involved “property damage,” as defined in the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Alert: AAA Construction Industry Rules Update
August 26, 2015 —
Christopher G. Hill – Construction Law MusingsThe American Arbitration Association has made some needed updates to their Construction Industry Arbitration and Mediation Rules, effective July 1, 2015. Among the changes listed at their website are:
- A mediation step for all cases with claims of $100,000 or more (subject to the ability of any party to opt out).
- Consolidation and joinder time frames and filing requirements to streamline these increasingly involved issues in construction arbitrations.
- New preliminary hearing rules to provide more structure and organization to get the arbitration process on the right track from the beginning.
- Information exchange measures to give arbitrators a greater degree of control to limit the exchange of information, including electronic documents.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Requesting an Allocation Between Covered and Non-Covered Damages? [Do] Think Twice, It’s [Not Always] All Right.
October 12, 2020 —
Todd Likman - Colorado Construction LitigationAs is often the case in construction defect and other insurance defense litigation, a plaintiff’s claims for relief typically encompass both covered and uncovered damages. Obviously, it is in the insured’s best interests to have as many damages covered by insurance as possible. From the insurer’s perspective and against the backdrop of owing duty of good faith and fair dealing to its insureds, however, it is generally better to have an allocation of covered vs. non-covered damages. This places the insurer, insured, and insurance retained defense counsel in a difficult position.
A recent opinion from U.S. District Court for the District of Colorado, Rockhill Ins. Co. v. CFI-Global Fisheries Mgmt, Civil Action No. 1:16-CV-02760-RM-MJW, 2020 U.S. Dist. LEXIS 35209 (D. Colo. Mar. 2, 2020), sheds light on the issue, even though some may feel it only further muddies already murky waters.
Rockhill involved review of an arbitration proceeding that property-owner, Heirloom I, LLC (“Heirloom”) filed against CFI-Global Fisheries Management (“CFI”). Rockhill Insurance Company (“Rockhill Insurance”) was asked to defend the arbitration as CFI’s professional and general liability insurer. At issue in the arbitration was Heirloom’s claim that CFI defectively designed and constructed a fisheries enhancement that was destroyed by natural processes four times in three years.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Likman, Higgins, Hopkins, McLain & RoswellMr. Likman may be contacted at
likman@hhmrlaw.com
Court Sharpens The “Sword” And Strengthens The “Shield” Of Contractors’ License Law
July 24, 2023 —
Kyle S. Case - ConsensusDocsPerforming construction work without the necessary license can have significant repercussions on a contractor’s business. California in particular has become known for its imposition of “strict and harsh” penalties for a contractor’s failure to maintain proper licensure. In the realm of public works projects, any contract with an unlicensed contractor is deemed void. See Business & Professions Code Section 7028.15(e). On private projects, California’s Contractors’ License Law prohibits contractors from maintaining any action to recover payment for their work, and more severe, may require a contractor to disgorge all funds paid to it for performing unlicensed work. See Business & Professions Code Section 7031). These methods of deterrence are referred to as the “shield” and “sword” of the Contractors’ State License Law. Loranger v. Jones, 184 Cal. App. 4th 847, 854 (2010).
In any discussion surrounding licensure, it is important to review the language of the Business and Professions Code (“Bus. & Prof.”). Section 7031(a) states:
Except as provided in subdivision (e), no person engaged in the business or acting in the capacity of a contractor, may bring or maintain any action, or recover in law or equity in any action, in any court of this state for compensation for the performance of any act or contract where a license is required by this chapter without alleging that they were a duly licensed contractor at all times during the performance of that act or contract regardless of the merits of the cause of action brought by the person…
Read the court decisionRead the full story...Reprinted courtesy of
Kyle S. Case, Watt, Tieder, Hoffar & Fitzgerald LLPMr. Case may be contacted at
kcase@watttieder.com
Differing Site Conditions Produce Differing Challenges
February 18, 2019 —
Sarah E. Carson - Smith CurrieThe saying “The best laid plans of mice and men often go awry” can too often apply in the construction industry. A contractor may receive a description of site conditions that is ultimately found flawed or misleading. The costs associated with addressing these surprise conditions often fall on the contractor to pay. The following article details proactive steps to avoid costly obstacles that may cause a project’s success to go awry.
What are Differing Site Conditions?
There are generally two recognized types of differing site conditions. The first, often referred to as a “Type I Changed Condition,” exists when a specification in the conditions indicated in the contract documents varies from what is represented. The second category, generally referred to as a “Type II Changed Condition,” is a variance so unusual in its nature that it materially differs from conditions ordinarily encountered in performing the type of work called for in the geographic area where the project is located.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah E. Carson, Smith CurrieMs. Carson may be contacted at
secarson@smithcurrie.com
You May Be Able to Dodge a Bullet, But Not a Gatling Gun
November 16, 2020 —
Garret Murai - California Construction Law BlogIn the days before cable, and long before Netflix, I watched my fair share of spaghetti westerns on lazy weekend afternoons. Bullets zinging past cowboys, knocking off hats, and ricocheting off rocks. But while you might get lucky and dodge a bullet, not so with a Gatling gun.*
In the next case, C. W. Johnson & Sons, Inc. v. Carpenter, Case No. B300187 (August 7, 2020), a contractor who was unlicensed during a portion of a project dodged a bullet. However, I’m not so sure that he’s going to be able to dodge the hail of bullets that are coming after.
The C. W. Johnson & Sons Case
As cases go, the C. W. Johnson & Sons case is pretty straightforward. In March 2016, Contractor C. W. Johnson & Sons, a family owned flooring company, was contracted to install flooring at Randall Carpenter’s house for a total contract price of $68,343. Work was performed between March and September 2016 including some warranty, repair and corrective work after September 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Certified Question Asks Hawaii Supreme Court to Determine Coverage for Allegations of Greenhouse Gas Emissions
October 09, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court certified questions to the Hawaii Supreme Court regarding coverage for underlying allegations of greenhouse gas emissions. Aloha Petroleum, Ltd. v. Nat'l Union Fire Ins. Co. of Pittsburgh, 2023 U.S. Dist. LEXIS 156211 (D. Haw. Sept. 5, 2023).
Aloha was sued in two lawsuits, one filed by the County of Maui and the second filed by the City and County of Honolulu. The underlying lawsuits alleged that Aloha disregarded known risks of harm to the counties when selling its fuel products that would inevitably combust and produce greenhouse gasses, particularly carbon dioxide, thereby changing the climate and causing harm to the counties.
Aloha tendered the suits to AIG. Coverage was denied based on AIG's determination there was no "occurrence" and the pollution exclusion barred coverage. Aloha sued AIG in federal district court seeking a declaratory judgment on AIG's obligations under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com