Does Stricter Decertification Mean More “Leedigation?”
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsRecently, my friend and fellow construction attorney/consultant, Chris Cheatham (@chrischeatham) posted the news that USGBC will be more stringent on the de-certification front. This statement relates to the continued energy performance of LEED certified buildings and increases the likelihood that energy performance (as opposed to mere reporting) could lead to de-certification.
I have discussed on several occasions the potential legal risks relating to green building. One of the big potential sources for such litigation (or “leedigation” as coined by Mr. Cheatham) is the possible de-certification of a previously certified building. With this latest statement by USGBC the specter of such de-certification seems even stronger.
Couple this potential with the fact that anyone can challenge the certification of a building at any time and contractors, subcontractors and other construction professionals face potential liability for the performance of a building in ways well beyond their control.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Colorado Supreme Court holds that loans made to a construction company are not subject to the Mechanic’s Lien Trust Fund Statute
February 21, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCIn a prior blog post, we summarized the Court of Appeals decision in the case of AC Excavating, Inc. v. Yale, ___ P. 3d. ___, 2010 WL 3432219 (Colo. App. Sept. 2, 2010) which provided an interpretation of the Colorado Mechanic’s Lien Trust Fund Statute, C.R.S. § 38-22-127 (hereafter “the Trust Fund Statute”). A divided Court of Appeals reversed the trial court, and held that capital loans infused into a limited liability company which performed construction could be subject to the provisions of the Trust Fund Statute.
The Court of Appeals reasoned that this determination was necessary because the statute was considered applicable to “all funds disbursed on a construction project.” Additionally, the Court of Appeals held that the intent of the provider of funds was not relevant, and that the statute applied “irrespective of the [originator of the funds]’s intended use of the funds.”
This decision was reviewed by the Colorado Supreme Court in an opinion released on February 4, 2013, and it reversed the Court of Appeals’ decision. See, Yale v. AC Excavating, Inc., ___ P. 3d. ___, 2013 WL 441895 (Colo. Feb. 4, 2013). The Supreme Court strongly disagreed that loaned or infused capital funds which were obtained by the general contractor entity were “funds disbursed on a construction project,” simply because some of the infused monies were used for operational purposes to pay down specific project obligations.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.mann@hlmrlaw.com
Montana Supreme Court: Insurer Not Bound by Insured's Settlement
December 02, 2019 —
K. Alexandra Byrd - Saxe Doernberger & Vita, P.C.In Draggin’ Y Cattle Co., Inc. v. Junkermier, et al.1 the Montana Supreme Court held that where an insurer defends its insured and the insured subsequently settles the claims without an insurer’s participation, a court may approve the settlement as between the underlying plaintiff and underlying defendant, but the settlement will not be presumed reasonable as to the insurer. Therefore, an insurer who defends its insured cannot be bound by a stipulated settlement that the insurer did not expressly consent to.
The case involved Draggin’ Y Cattle Company (the “Cattle Company”), a ranching and cattle business that utilized the services of an accounting firm, Junkermier, Clark, Campanella, Stevens, P.C. (“Junkermier”), to structure the sale of real property to take advantage of favorable tax treatment. It was discovered that Junkermier’s employee misinformed the Cattle Company’s owners of the tax consequences of the sale. The Cattle Company’s owners subsequently filed suit against Junkermier and its employee and alleged nearly $12,000,000 in damages due to the error. Junkermier’s insurer, New York Marine, provided a defense for Junkermier and its employee.
The Cattle Company’s owners offered to settle the claims against Junkermier and its employee for $2,000,000, the policy limit of the New York Marine policy. New York Marine refused to give its consent or tender the policy’s limit. Subsequently, Junkermier, its employee, and the Cattle Company entered into their own settlement agreement for $10,000,000. The settlement was contingent upon a reasonableness hearing to approve the stipulated agreement.
Read the court decisionRead the full story...Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C.Ms. Byrd may be contacted by
kab@sdvlaw.com
Candis Jones Named to Atlanta Magazine’s 2022 “Atlanta 500” List
February 14, 2022 —
Candis Jones - Lewis Brisbois NewsroomAtlanta, Ga. (February 11, 2022) - Atlanta Partner Candis R. Jones has been named to Atlanta Magazine’s 2022 “Atlanta 500” list of the most powerful business leaders in Atlanta. This is the second year in a row she has received this recognition.
To compile this list, the publication reviewed nominations from the public and consulted experts across various sectors. The magazine’s editors and writers considered not only the status of the nominees within their respective organizations, but also whether the nominees were visionary by, for example, leading programs for their communities or creating opportunities for employees.
Read the court decisionRead the full story...Reprinted courtesy of
Candis Jones, Lewis BrisboisMs. Jones may be contacted at
Candis.Jones@lewisbrisbois.com
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at
gazzolaj@pepperlaw.com
Treasure Island Sues Beach Trail Designer over Concrete Defects
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFThe city of Treasure Island, Florida “has filed a lawsuit against Graham Landscape Design of St. Petersburg and Coastal Technology Corp. of Vero Beach for failing to properly design the 1-mile trail along the city's beachfront, which has hundreds of cracks in its concrete surface,” reported the Tampa Bay Times.
"The city has been unable to resolve the construction defects of the Central Beach Trail outside of the litigation process," City Attorney Maura Kiefer said to the Tampa Bay Times.
Cracks allegedly began appearing on the $1.2 million dollar trail soon after the project was concluded (March 2013). Treasure Island “submitted a performance bond claim and notified insurance companies representing Graham Landscape of the problem.”
Consultants hired by Phil Graham IV, the owner of the design company, determined that the cracking was caused by “a combination of problems in the design, construction and composition of materials.”
Read the court decisionRead the full story...Reprinted courtesy of
Revisiting the CMO; Are We Overusing the Mediation Privilege?
November 19, 2021 —
Michael T. Kennedy Jr. - BERDING|WEILOne of the most common features in construction defect cases is the Case Management Order (“CMO”) or Pre-Trial Order (“PTO”) to govern pre-trial and mediation procedures. CMOs and PTOs arose in the days when the HOA would sue the developer, the developer would cross-complaint against the subcontractors, and each defendant and cross-defendant might have 2 or 3 insurance carriers defending, each of whom may retain their own panel counsel. In a large case there may have been 20 parties and 30 defense attorneys. In order to avoid the cost and chaos of all of those parties propounding their own discovery, and in order to prepare these cases for mediation well before trial and the associated costs, it became standard practice in California to include provisions in the CMO to stay all discovery until just before trial.
Plaintiff would provide a Defect List or Statement of Claims and the parties experts would meet and exchange information as part of the mediation process. All of the information exchanged would be subject to mediation privileges and inadmissible at trial. The benefit of this practice was that the parties (and carriers) would avoid the cost of formal discovery and allow the experts to discuss compromised scopes of repair to help settle the case while being able to take a more aggressive position at trial. The disadvantages are that each party uses its privileged initial expert reports to stake out negotiating positions more extreme than what they would put on at trial, with each side losing credibility with the other in assessing the value of the case, and for those cases that did not settle, the parties would be faced with having to do all of the depositions and discovery in the last 60 days, or delaying trial, or both.
Over the last 10 or 15 years with the advent of wrap-up insurance policies, these cases now usually involve 2 sides instead of 20; only the HOA and the developer remain in the case. However, old habits die hard, and the standard CMO/PTO hasn’t evolved with other aspects of these cases. The practice of staying all discovery and exchanging information only under mediation privileges remains, and as a result insurance carriers don’t receive the admissible evidence that they need to determine coverage and evaluate the real settlement value of the case until just before trial. On the plaintiff’s side, if most of the experts’ work is done under the guise of mediation privilege, those costs may not be recoverable. Outside the context of mediation, costs incurred in investigation of the defects and preparation of a scope and cost of repair are recoverable.
This reflexive claim of mediation privilege over all information exchanged during the case has outlived its usefulness. The CMO can and should remain to regulate formal discovery and to help the parties prepare for mediation, but regulated discovery should be opened early in the case. In California, the SB800 process already provides for the exchange of admissible information during the prelitigation right to repair process. Continuing that exchange during the early litigation allows the parties to continue to prepare for mediation, but waiving privileges had advantages for both sides.
A senior claims manager once commented that Plaintiff’s mediation-protected Statement of Claims “might as well be a stack of blank paper” for all of its usefulness to the carrier in assessing the value of the case. If the Plaintiff and it expects are free to inflate their claims early in the case without having to worry about every supporting those claims in front of a jury, they have little or no credibility. And if those claims are inflated or not “real,” not only can the carrier not properly assess the verdict range and settlement value of the case, but it may also be hampered in making a coverage determination. Simply put, if the exchange of real information through formal discovery is put off until just before trial, the defense cannot be ready to settle until then. Worse, the cost of defense goes through the roof in the last 60 days before trial as the lawyers’ scramble to take all of the depositions and to all of the other work that had been stayed for the previous year or two.
The Plaintiff is faced with the same question of credibility of defense experts where they are free to take a “low ball” negotiating position without having to support that position through cross-examination in front of the jury. Just as the carrier behind the defense attorney needs the Plaintiff’s “real” evidence to assess the claim, so does the HIOA Board of Directors behind the Plaintiff’s counsel. Additionally, in California as in most states, the cost of experts’ preparation for mediation may not be recoverable as costs or damages, but investigation of the defects and preparation of the scope and cost of repair is recoverable.
The biggest challenge is resolving construction defect claims for both sides is how to resolve these cases quickly while keeping costs under control. Practices that worked 20 years ago are no longer applicable with changes in insurance, and in light of some of the bad habits that arise when all of the information exchanged was confidential.
The CMO/PTO process can still be useful to regulate the discovery and mediation schedule given the volume of documents and other information to be exchanged but exchanging “real” information in a form that may come into evidence at trial should foster earlier resolution, resulting in cost savings for the parties. The CMO can provide for the parties to respond to controlled discovery, and the exchange of expert reports and potentially depositions can and should be done earlier in the case, well before the eve of trial. The parties can then assess the true value of each case and prepare for more substantive mediation without waiting until they are on the figurative courthouse steps.
Construction defect cases have a pattern, and it is tempting for busy lawyers to just put each case through the same algorithms that they have used for years. However, these cases have evolved and those of us handling these cases need to reevaluate our approach to these cases. Taking aggressive negotiating positions that no longer have any credibility with the other side has become counterproductive, and the exchange of real evidence earlier in the case would better serve our clients and carriers.
BERDING|WEIL is the largest and most experienced construction defect and common interest development law firm in California. For more information, please visit https://www.berding-weil.com
Read the court decisionRead the full story...Reprinted courtesy of
Michael T. Kennedy Jr., BERDING|WEILMr. Kennedy may be contacted at