Just Because You Record a Mechanic’s Lien Doesn’t Mean You Get Notice of Foreclosure
September 15, 2016 —
Christopher G. Hill – Construction Law MusingsAs longtime (or new readers for that matter) know, mechanic’s liens are near and dear to my heart here at Construction Law Musings. These powerful tools to collect for your hard work on a construction project are great when prepared and recorded in the very specific fashion required by the Virginia legislature and courts. In most situations, if done properly, a mechanic’s lien gives you some security and priority for your construction claim that you would not have with a simple judgment lien.
Despite the power of a properly perfected and enforced mechanic’s lien (and the fact that the end result of a full mechanic’s lien suit that remains unsettled is in fact a foreclosure), a recent case in the Eastern District of Virginia, Weinberg v. J.P. Morgan Chase, et. al., (thanks for the head’s up on this case to the folks at the Construction Payment Blog) held that under Virginia statute mechanic’s lien holders are not entitled to notice of foreclosure. In the Weinberg case, the plaintiff, a pro se lien claimant that recorded two different liens, one pre-foreclosure and one post-foreclosure, and who had not received notice of the intervening foreclosure, argued, among other things, that he should have been given notice of the foreclosure on the deed of trust on the property by J. P. Morgan Chase.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Before Collapse, Communications Failed to Save Bridge Project
December 30, 2019 —
Scott Judy - Engineering News-RecordThe National Transportation Safety Board’s Oct. 8 release of documents related to its FIU bridge collapse investigation raises questions but provides no definitive conclusions about why the partially built structure suddenly crashed to the ground on March 15, 2018, killing six. The last official word on the cause of the fatal collapse will have to await the agency’s final report, scheduled to be released on Oct. 22.
Scott Judy, Engineering News-Record
Mr. Judy may be contacted at judys@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Vallagio v. Metropolitan Homes: Colorado Supreme Court Upholds Declarant Consent Provision to Amend Arbitration Out of Declarations
June 15, 2017 —
Jean Meyer - Colorado Construction LitigationOn June 5, 2017, the Colorado Supreme Court announced the Vallagio at Inverness Residential Con. Ass’n v. Metro. Homes, Inc., No. 15SC508, 2017 CO 69 (Colo. June 5, 2017) decision. In short, the Colorado Supreme Court upheld the validity of declarant “consent-to-amend” provisions and expressly held that claims under the Colorado Consumer Protection Act are arbitrable.
By way of background, the Vallagio at Inverness Residential Condominiums were developed by Metro Inverness, LLC, (“Declarant”) which also served as the declarant for its homeowners association. Metropolitan Homes was Metro Inverness’ manager and the general contractor on the project. Greg Krause and Peter Kudla served as declarant-appointed members of the Association’s board during the period of declarant control.
When it set up the Association, the Declarant included within the Association’s declaration a mandatory arbitration provision specifically for construction defect claims. This provision stated that it “shall not ever be amended without the written consent of Declarant and without regard to whether Declarant owns any portion of the Real Estate at the time of the amendment.”
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
“Time Is Money!” In Construction and This Is Why There Is a Liquidated Damages Provision
February 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn construction, the adage “Time is Money!” rings true for all parties involved on a project. This includes an owner of a project that wants a project completed on time, i.e., by a substantial completion date. While substantial completion is often defined as when an owner can use a project for its intended purpose, this intended purpose typically equates to beneficial occupancy (in new construction) and other factors as identified in the contract.
The best mechanism for an owner to reinforce time and the substantial completion date is through a liquidated damages provision (also known as an LD provision) that includes a daily monetary rate for each day of delay to the substantial completion date.
A liquidated damages provision is not designed, and should NEVER be designed, to serve as a penalty because then it would be unenforceable. Instead, it should be designed to reasonably compensate an owner for delay to the substantial completion date that cannot be ascertained with any reasonable degree of certainty at the time the contract is being negotiated and executed. (Liquidated damages are MUCH easier to prove than actual damages an owner may incur down the road.) As an owner, you don’t really want to assess liquidated damages because that means the project is not substantially completed on time. And, in reality, a timely completed and performing project should always be better and more profitable than a late and underperforming project. However, without the liquidated damages provision, there isn’t a great way to hold a contractor’s feet to the fire with respect to the substantial completion date.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ensuring Arbitration in Construction Defect Claims
February 04, 2013 —
CDJ STAFFJared E. Berg and John W. Mill of Sherman & Howard note that developers and general contractors would prefer that construction defect claims against them go to arbitration, instead of ending up in front of a jury. They say “there is a way to do this.” For the developer and general contractor, arbitration is “typically less costly and time consuming than litigation.”
On the other side, home owner associations “tend to prefer litigation because the up-front costs of arbitration are greater and they would rather have their cases tried to a jury than a panel of arbitrators in the belief juries offer greater potential for high damage awards. In order to avoid arbitration, “HOAs have taken advantage of their statutory rights to amend declarations by instructing their members to approve amendments removing arbitration clauses.
However, in a recent Colorado case, the developer had taken a precaution of including in the arbitration clauses that “they could not be removed from the declarations by amendment with the developer’s and general contractor’s consent.” The homeowners association had voted to remove these clauses, but the judge found that they could not do so.
Berg and Mill give the advice to “include in the declaration’s arbitration clause a provision making your consent required to amend or nullify the arbitration provision,” adding that “courts will enforce this kind of consent provision.”
Read the court decisionRead the full story...Reprinted courtesy of
Texas Supreme Court Cements Exception to “Eight-Corners” Rule Through Two Recent Rulings
March 06, 2022 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogThe Texas “eight corners” rule precludes insurers from disclaiming a defense obligation based on facts not alleged in the underlying pleadings. Texas federal and appellate courts have been issuing rulings addressing exceptions to the eight corners rule and recently sought guidance from the Texas Supreme Court on whether Texas law recognizes such exceptions to the “eight corners” rule. The Texas Supreme Court has now spoken on the issue.
Monroe Guar. Ins. Co. v. BITCO Gen. Ins. Corp., 65 Tex. Sup. Ct. J. 440 (2022).
In Monroe, David Jones contracted with 5D Drilling & Pump Services in the summer of 2014 to drill a 3,600-foot commercial irrigation well on his farmland. In 2016, Jones sued 5D for breach of contract and negligence relating to 5D’s drilling operations on Jones’s property. Jones’s pleading was silent as to when the damage flowing from 5D’s alleged acts of misconduct occurred. BITCO and Monroe stipulated that 5D’s drill struck a bore hole during 5D’s drilling operations in or around November 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Steel Makeover Under Way for Brooklyn's Squibb Footbridge
January 13, 2020 —
Tom Stabile - Engineering News-RecordBrooklyn Bridge Park’s Squibb Bridge has 127 fewer years of existence than the borough’s iconic East River span, but the pedestrian crossing got lots of New York City attention since it was first opened in 2013 after being shut down twice—once for excessive “bounciness” and again due to rotting wood. Now its reconstruction, hopefully for good, is anything but a straightforward operation.
Tom Stabile, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of