Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Governor Murphy Approves Legislation Implementing Public-Private Partnerships in New Jersey
August 28, 2018 —
Steven M. Charney & Charles F. Kenny - Peckar & Abramson, P.C.On Tuesday, August 14, 2018, New Jersey Governor Phil Murphy signed Senate Bill S-865, creating the state’s new Public-Private Partnership (PPP) law, making New Jersey the latest state to embrace this burgeoning delivery system for the construction of public infrastructure projects. The new law goes into effect 180 days from today.
Peckar & Abramson (P&A) has teamed with both The Associated Construction Contractors of New Jersey (ACCNJ) and the Association for the Improvement of American Infrastructure (AIAI) who have been at the forefront in promoting this landmark legislation. P&A anticipates that the new law will create multiple opportunities for much needed public building and infrastructure projects in the state. In our recent Client Alert (June 29, 2018), we highlighted the numerous opportunities that will be available as a result of the PPP legislation, notably for the delivery of projects that may not have otherwise come to fruition.
Reprinted courtesy of
Steven M. Charney, Peckar & Abramson, P.C. and
Charles F. Kenny, Peckar & Abramson, P.C.
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Kenny may be contacted at ckenny@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
FDOT Races to Re-Open Storm-Damaged Pensacola Bridge
April 12, 2021 —
Jim Parsons - Engineering News-RecordBuffeted by hurricanes, northwest Florida’s largest-ever infrastructure effort is finally seeing the light at the end of the storm. The three-mile-long bridge across Pensacola Bay is expected to reopen to traffic this spring after an ongoing replacement effort abruptly became an emergency repair job as well.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Clock is Ticking: Construction Delays and Liquidated Damages
September 18, 2023 —
Tiffany Harrod - ConsensusDocsWith the on-going shortage of construction workers in the industry and other factors ranging from weather to procurement problems, the threat of project delay is real. When a contract contains a liquidated damages clause for assessing project delays, real financial consequences for contractors can result. Courts have long allowed parties to apportion contractual risks as they deem appropriate especially in the commercial context where the parties are considered to be sophisticated even if their bargaining power is not equal. Liquidated damage provisions such as those for delay that are found in construction contracts are not unusual but they must be crafted in such a way as to be enforceable and not violate public policy.
A liquidated damage clause in a construction contract is a customary way for the parties to deal with the possibility of delay in the completion of a project and the potential losses flowing from the delay.[
1] In their most basic form, the party in breach, which is more often than not the contractor, is obligated to pay the non-breaching party, usually the project owner, some fixed sum of money for the period that exceeds the designated completion date that was agreed upon in advance and memorialized in the contract. (It is after all no secret that these provisions are primarily for the owner’s benefit.) The non-breaching party is then compensated for losses associated with the delay without the time and expense of having to prove in either a civil suit or an arbitration proceeding what the actual damages are. This option is particularly attractive to project owners because the liquidated damages assessment can simply be withheld from payments owed to the contractor once the agreed-upon completion date has been passed.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Harrod, Peckar & AbramsonMs. Harrod may be contacted at
tharrod@pecklaw.com
Novation Agreements Under Federal Contracts
November 29, 2021 —
Hal Perloff - Construction ExecutiveA unique aspect of doing business with the federal government is the built-in limits on a contractor’s right to assign the contract or the right to payment under the contract to third parties. The Anti-Assignment Act (41 U.S.C. § 6305) prohibits the transfer of a government contract or interest in a government contract to a third party. An assignment of a contract in violation of this law voids the contract except for the government’s right to pursue a breach of contract remedies.
What’s a contractor to do when it is acquired/merged with another firm, is restructured or goes through a variety of other types of corporate transaction? The Federal Acquisition Regulations recognize that firms involved in government contracts get bought and sold from time to time and includes procedures for the novation of contracts in certain situations to avoid a potential violation of the Anti-Assignment Act.
What Is a Novation?
A novation is a three-party agreement between the United States, the original contractor and the new contractor offering to assume the government contract. The purpose the novation is to allow the government to recognize a new contractor as the successor-in-interest to a government contract and avoid a violation of the Anti-Assignment Act.
Reprinted courtesy of
Hal Perloff, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Perloff may be contacted at
hal.perloff@huschblackwell.com
A Matter Judged: Subrogating Insurers Should Beware of Prior Suits Involving the Insured
March 25, 2024 —
Gus Sara - The Subrogation StrategistIn New Jersey Mfrs. Ins. Co. v. Lallygone LLC, No. A-2607-22, 2024 N.J. Super. Unpub. LEXIS 120, the Appellate Division of the Superior Court of New Jersey (Appellate Division) considered whether New Jersey Manufacturers Insurance Company (the carrier) could bring a subrogation action after its insured, Efmorfopo Panagiotou (the insured), litigated and tried claims related to the same underlying incident with the same defendant, Lallygone LLC (the defendant). The Appellate Division affirmed the trial court’s finding that the prior lawsuit extinguished the carrier’s claims.
In Lallygone LLC, the insured hired the defendant to renovate a detached garage on his property. In March 2022, while the defendant’s employees were removing existing concrete slabs, the garage collapsed. After the incident, the insured stopped paying the defendant. In addition, the insured filed a claim with the carrier, which ultimately paid the insured over $180,000 for the damage under its property policy. The carrier sent a subrogation notice letter to the defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
BHA at The Basic Course in Texas Construction Law
October 21, 2015 —
CDJ STAFFBert L. Howe & Associates, Inc., (BHA) is proud to be partnering with the State Bar of Texas, Construction Law Section, as a sponsor and exhibitor at The Basic Course in Texas Construction Law to be held November 12 & 13, 2015 at The Westin Austin at The Domain.
With offices in San Antonio and Houston, Bert L. Howe & Associates, Inc., offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in over 5,500 cases. BHA’s staff encompasses a broad range of licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of developers, general contractors and subcontractors.
BHA’s experience covers the full range of construction defect litigation, including single and multi-family residential (including high-rise), institutional (schools, hospitals and government buildings), commercial, and industrial claims. BHA also specializes in coverage, exposure, premises liability and delay claim analysis.
As the dynamic litigation climate in Texas continues to change, and as the number of construction defect and other construction-related cases continues to rise and become more sophisticated, it is more important than ever for contractors and builders to be aggressive in preparing for claims before they are made, and in defending against those claims once they are filed.
Since 1993, Bert L. Howe & Associates, Inc., has been an industry leader in providing construction consulting services, and has been a trusted partner with builders and insurance carriers, both large and small, in Texas and across the Western United States.
Register for the Basic Course...
Read the court decisionRead the full story...Reprinted courtesy of