Remand of Bad Faith Claim Evidences Split Among Florida District Courts
September 04, 2018 —
Michael S. Levine & Daniel Hentschel - Hunton Insurance Recovery BlogWhether an insurance bad faith claim, joined by amendment to an underlying insurance coverage action, may be removed more than a year after the original action was begun has divided federal judges in the state of Florida but has not yet been considered by the Eleventh Circuit. Now, a new opinion out of the Middle District of Florida (Jacksonville Division) has added to the debate.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Venture Sues LAX for Nonpayment
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction joint venture Walsh/Austin filed suit against the Los Angeles International Airport, claiming that “the airport failed to properly pay more than $2.4 million to an electrical subcontractor,” according to The Daily Breeze. Furthermore, SASCO, the electrical firm, alleged that they were “given inaccurate design documents that made it impossible for the company to carry out the work at the agreed-upon rate.”
The complaint, as reported by The Daily Breeze, cited “other lawsuits brought by an Orange County plastering firm and a Buena Park door company” and suggested that “eventually, all the litigation tied to nonpayment at LAX will end up in the same courtroom.”
Nancy Castles, a spokeswoman for Los Angeles World Airports, told The Daily Breeze that “the agency does not comment on pending litigation.”
Read the court decisionRead the full story...Reprinted courtesy of
Lien Waivers Should Be Fair — And Efficient
February 18, 2015 —
Christopher G. Hill – Construction Law MusingsThis week for our Guest Post Friday here at Construction Law Musings, we welcome back my good friend Scott Wolfe. Scott, a thought leader in the construction industry, combines his construction background, tech experience, entrepreneurial spirit, and legal education to bring a unique perspective to the industry’s construction payment problem. Scott is the founder of zlien, a venture-backed construction payment platform. A licensed attorney in six states, his writing has appeared in the New York Times, CFMA’s Building Profits, Supply House Times, Construction Executive, and tED Magazine. He has been a Keynote Speaker for the American Subcontractors Association annual conference, and spoken at CFMA events.
Lien waivers are perhaps the most legally and practically complicated documents exchanged in the construction industry. Unfortunately, this results in huge corporate inefficiencies, and worse, provides an opportunity for some parties to exert undue leverage over others.
Lien waivers — or lien releases, as they are commonly (but mistakenly) called — aren’t supposed to be complicated, though. They are designed to make the complex construction payment process easy and fair.
This article will address why that is, how it works, and where things have gone awry.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
National Engineering and Public Works Roadshow Highlights Low Battery Seawall Restoration Project in Charleston
April 29, 2024 —
Engineering and Public Works RoadshowCHARLESTON, SC — On Thursday, the nationwide Engineering and Public Works Roadshow stopped at the Low Battery Seawall Restoration Project in Charleston. The event highlighted the role engineers and public works professionals play in infrastructure projects like the local seawall improvements that increase coastal resiliency along the historic urban shoreline.
The event, which took place along the newly constructed battery wall section between King Street and Battery Place along Murray Boulevard, marked the latest stop of the Engineering and Public Works Roadshow – a joint effort by the American Council of Engineering Companies, the American Public Works Association, and the American Society of Civil Engineers to bring public attention to the essential role engineers and public works professionals play in making our modern world possible.
The battery project underscores the importance of innovative engineering solutions in addressing the challenges of climate change and rising sea levels. Thursday's event was also a chance to spotlight the engineering, construction, and public officials involved in the project, whose work often goes unrecognized.
About the Engineering and Public Works Roadshow: The Engineering and Public Works Roadshow is a series of nationwide events highlighting critical infrastructure projects and the skilled professionals who make them possible. It is an opportunity to learn about the importance of infrastructure investment, showcase the work of engineers and public works professionals, and celebrate these projects' positive impact on our communities. Learn more at www.infrastructureroadshow.org.
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Federal District Court Follows Majority Rule on Insurance Policy Anti-Assignment Clauses
March 20, 2023 —
Saxe Doernberger & Vita, P.C.A recent decision by the United States District Court for the District of Connecticut further confirms that Connecticut courts follow the majority rule that contractual anti-assignment clauses do not bar assignment of an insured’s claim after the loss occurred.1
The September 2022 decision in
Am. Guarantee & Liability Ins. Co. v. 51 Roses Mill LLC arose out of a fire that destroyed a property under contract for sale. At the time of the fire, the property was owned by Bridge33 Capital LLC (“Bridge33”), insured by American Guarantee & Liability Insurance Company (“American Guarantee”), and under contract for sale to 51 Roses Mill LLC (“51 Roses”). After the fire, Bridge33 assigned its insurance claim to 51 Roses. American Guarantee filed suit seeking a declaratory judgment that the assignment was invalid, or that, if it was valid, 51 Roses could only recover under the actual cash value, rather than the replacement cost value, of the lost property. 51 Roses brought counterclaims for breach of contract and bad faith and sought a declaratory judgment that it was entitled to replacement cost value under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.Saxe Doernberger & Vita, P.C. may be contacted at
coverage@sdvlaw.com
They Say Nothing Lasts Forever, but What If Decommissioning Does?
June 10, 2019 —
Stella Pulman - Gravel2Gavel Construction & Real Estate Law BlogThe looming decommissioning liabilities of offshore energy producers have been a focus of the federal government in recent years. One recent case out of the U.S. Court of Federal Claims, Taylor Energy v. United States, highlights the tension between the federal government’s desire to maintain financial security for decommissioning activities, and that of an operator whose security is tied up indefinitely while the government awaits technological advances to allow for safe decommissioning.
The case relates to a trust agreement between Taylor Energy and the United States, established to secure Taylor’s decommissioning liabilities for 28 wells in the Gulf of Mexico. Taylor completed certain decommissioning work for which it was reimbursed by the trust. However, with over $400 million remaining in the trust, Taylor and the Bureau of Safety and Environmental Enforcement (BSEE) concluded that the ecological benefits of further decommissioning would be outweighed by the ecological risks. But despite recognizing that the limitations of current technology made the environmental impacts of further decommissioning work unjustifiable, the BSEE declined to release Taylor from its decommissioning obligations and instead decided to await “changes in technology and a better understanding of the undersea environment.” Because Taylor’s decommissioning obligations remained in place, the U.S. refused to release the remaining funds in the trust.
Taylor claimed that the United States should release the remaining funds in the trust because “decommissioning the remaining wells is not ‘currently technologically feasible.’” Taylor asserted that Louisiana law applied to the trust agreement, and that under Louisiana law every contract must be completed within an ascertainable term. By holding the trust funds until decommissioning was complete, Taylor argued that the government was essentially holding the funds in perpetuity given the technological infeasibility of completing decommissioning. Taylor also asserted that the agreement was premised on an impossibility (the full decommissioning of the wells), and/or a mutual mistake of the parties (that the wells could be decommissioned).
Read the court decisionRead the full story...Reprinted courtesy of
Stella Pulman, PillsburyMs. Pulman may be contacted at
stella.pulman@pillsburylaw.com
Real Estate Developer Convicted in $1.3 Billion Tax Case After Juror Removed
October 17, 2023 —
David Voreacos - BloombergA real estate developer was convicted for promoting $1.3 billion in fraudulent tax deductions after a judge removed a deliberating juror who told the judge she was “standing up for White people.”
Jack Fisher was found guilty Friday in Atlanta federal court of selling tax deductions to wealthy individuals using so-called syndicated conservation easements, which offer tax breaks for the promise to avoid developing land. Prosecutors said Fisher relied on exaggerated appraisals and backdated documents in the scheme, which earned him tens of millions of dollars.
Jurors also convicted a lawyer who worked with Fisher, James Sinnott. Attorneys for Fisher and Sinnott didn’t immediately respond to a request for comment.
The nine-week trial nearly came undone by conflicts over race and class within the jury, which began deliberating on Sept. 14. Last week, jurors told US District Judge Timothy Batten they were “hopelessly hung.” Jurors also complained that Juror 26, a White woman, refused to deliberate.
Read the court decisionRead the full story...Reprinted courtesy of
David Voreacos, Bloomberg
Sales of U.S. Existing Homes Rise to One-Year High
October 22, 2014 —
Michelle Jamrisko – BloombergSales of previously owned homes climbed in September to the highest level in a year, pointing to growing confidence in the U.S. economy as employment firms.
Purchases advanced 2.4 percent to a 5.17 million annual rate, the National Association of Realtors reported today in Washington. Demand was up 1.9 percent compared with the same month last year before adjusting for seasonal patterns.
Americans are returning to the real-estate market as employers have added 2 million workers to payrolls so far this year. Sales stand to get an additional boost in the final months of 2014 as the drop in mortgage rates caused by slowing growth in Europe and emerging nations makes properties more affordable for first-time buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, BloombergMs. Jamrisko may be contacted at
mjamrisko@bloomberg.net