Statutory Bad Faith and an Insured’s 60 Day Notice to Cure
April 11, 2018 —
David Adelstein - Florida Construction Legal UpdatesA recent case came out in favor of an insured and against a first-party property insurer in the triggering of a statutory bad faith action. Florida’s Fifth District Court of Appeal in Demase v. State Farm Florida Insurance Company, 43 Fla. L. Weekly D679a (Fla. 5th DCA 2018)
held that if an insurer pays a claim after the 60-day notice to cure period provided by Florida Statute s. 624.155(3), this “constitutes a determination of an insurer’s liability for coverage and extent of damages under section 624.155(1)(b) even when there is no underlying action.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Contractor Haunted by “Demonized” Flooring
December 14, 2020 —
Garret Murai - California Construction Law BlogThe most un-Halloween of Halloweens has come and gone. If you ask me though, between COVID, protests, fires, hurricanes, the passing of a Supreme Court Justice, and one of the most hotly contested elections in U.S. history, we’ve had enough scares this year to make up for it and then some.
In the next case, Sieg v. Registrar of Contractors, Case No. A156089 (September 28, 2020), 1st District Court of Appeal, one contractor, haunted by “demonized” flooring, and who couldn’t catch a break even with the talisman of a release of liability signed by the homeowner, can add one more to his list of reasons why 2020 needs to be relegated to the history books.
The Sieg Case
In January 2012, homeowners Dennis and Ana Torchia purchased wood flooring for their home in Windsor, California. Specifically, they selected Brazilian Ebony, an exotic species of unusually hard wood, for its appearance and durability.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Beverly Hills Voters Reject Plan for Enclave's Tallest Building
November 10, 2016 —
James Nash – BloombergA costly battle over development in Beverly Hills, California, ended with voters rejecting a hotel owner’s proposal to combine two planned condominium towers into a single building that would have loomed over the wealthy Southern California enclave.
With 44 percent in support and 56 percent against, Beverly Hills voters turned down plans by Beny Alagem, who owns the Beverly Hilton and is building an adjacent 170-room Waldorf Astoria, to develop a single 26-story tower next to the hotels, instead of eight- and 18-story buildings that were approved by the city council and a voter referendum in 2008. Alagem’s plan sets aside the remaining 1.7 acres (0.7 hectares) for a public park and gardens.
Read the court decisionRead the full story...Reprinted courtesy of
James Nash, Bloomberg
Environmental Law Violations: When you Should Hire a Lawyer
October 09, 2018 —
Bremer Whyte Brown & O’MearaEnvironmental law violations can have an enormous impact on your ongoing profitability. Environmental law is complicated and multifaceted, with laws at the local, state, and federal level often overlapping. In this article, we’ll discuss environmental law violations in the context of defending against an environmental law claim. In doing so, we’ll take a brief look at what environmental law is, and explore some environmental law violations cases. This should shed some light on the complex nature of environmental law litigation, and highlight the importance of securing legal representation with the scope and breadth of practice to wade into an environmental law violation case.
What is Environmental Law?
Before diving into specific environmental law violation cases, it is helpful to first provide a basic outline of what environmental law is and what different levels of environmental law exist in the United States. The most well-known environmental law exists at the federal level and is enforced by the Environmental Protection Agency (EPA). The EPA is responsible for enforcing directives that have been set forth by Congress over time. These include a variety of Acts, including the Clean Air Act and Clean Water Act.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Delaware River Interstate Bridge Shut to Assess Truss Fracture
January 26, 2017 —
Justin Rice - Engineering News-RecordThe Delaware River Bridge, which runs between Pennsylvania and New Jersey, was shut down indefinitely over the Jan. 22-23 weekend, after a large fracture was discovered in the bridge that connects the turnpikes of the two states. The fracture on a steel truss below the bridge deck on the Pennsylvania side was discovered during a routine check as part of a painting operation. Steel plates were installed to temporarily reconnect the fracture and stabilize the 1.5-mile bridge, which is located in Bucks County on I-276 and accommodates 42,000 vehicles a day. As engineers assess how the damage will impact the entire bridge, a sample from the fractured truss was sent to a forensic lab to determine the cause of the crack. A high-definition video survey is being used to monitor the bridge.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com
Interior Designer Licensure
October 11, 2017 —
David Adelstein - Florida Construction Legal UpdatesAn interior designer that provides residential interior design services does NOT need to be registered or licensed with the state. On this point, Florida Statute s. 481.229(6)(a) specifies:
(6) This part shall not apply to:
(a) A person who performs interior design services or interior decorator services for any residential application, provided that such person does not advertise as, or represent himself or herself as, an interior designer. For purposes of this paragraph, “residential applications” includes all types of residences, including, but not limited to, residence buildings, single-family homes, multifamily homes, townhouses, apartments, condominiums, and domestic outbuildings appurtenant to one-family or two-family residences. However, “residential applications” does not include common areas associated with instances of multiple-unit dwelling applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
"On Second Thought"
October 28, 2024 —
Daniel Lund III - LexologyRehearing requests are seldom granted by courts, and when they are, there’s usually something uniquely compelling in the request and the granting.
So is the case in a matter involving monies deposited in the registry of the federal court in New Orleans related to work performed on cleanup after Hurricanes Maria and Irma in the U.S. Virgin Islands. The party depositing monies – which represented subcontract sums paid to it by the general contractor – held back several hundred thousand dollars based on withholding provisions in the various contracts in play. The Court was tasked with evaluating not only a pay-when-paid provision in the subcontract of the claiming party, but also incorporation of the terms of a higher tiered contract which allowed for the withholding.
The Court initially granted summary judgment allowing the monies to be withheld. However, on request for rehearing, it was pointed up that while monies could be retained for purposes of covering attorney’s fees and costs related to litigation initiated by the plaintiff subcontractor’s vendors, there was a particular process for that withholding – and an assertion that the process was not followed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of