Definitions Matter in Illinois: Tenant Held Liable Only for Damage to Apartment Unit
September 09, 2024 —
Gus Sara - The Subrogation StrategistIn Phila. Indem. Ins. Co. v. Gonzalez, No. 1-23-0833, 2024 Ill. App. Unpub. LEXIS 1372, the Appellate Court of Illinois considered whether the terms of a lease agreement limited a tenant’s liability for fire damages, a fire caused by her negligence, to her apartment unit only. The plaintiff insured the subject apartment building, which incurred damage to several units as result of a fire in the tenant’s unit. The lease defined “Premises” as the specific apartment unit occupied by the tenant and held the tenant responsible for damage caused to the Premises. While the court found that the lease permitted the plaintiff to subrogate against the tenant, it held that the lease terms limited the damages to the tenant’s apartment unit only.
In Gonzalez, the plaintiff’s insured owned a multi-unit apartment building in Chicago. In September 2019, the building owner entered into a lease agreement with the defendant for apartment Unit 601. The lease stated that Unit 601 was the “Leased Address (Premises).” Another provision stated that building owner “hereby leases to Tenant(s) and Tenant(s) hereby leases from Landlord(s) for use as a private dwelling only, the Premises, together with the fixtures and appliances (if any) in the premises…” The lease also stated that “Tenant shall be liable for any damage done to the premises as a result of Tenant’s or Tenant’s invitees, guests or others authorized to reside in the Premises [sic] direct action, negligence, or failure to inform Landlord of repairs necessary to prevent damage to the Premises.”
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Claims Made Insurance Policies
November 04, 2019 —
David Adelstein - Florida Construction Legal Updates“Claims-made policies are common in the professional liability insurance market. They “differ from traditional ‘occurrence’-based policies primarily based upon the scope of the risk against which they insure.” With claims-made policies, coverage is provided only where the act giving rise to coverage “is discovered and brought to the attention of the insurance company during the period of the policy.” In contrast, coverage is provided under an occurrence-based policy if the act giving rise to coverage “occurred during the period of the policy, regardless of the date a claim is actually made against the insured.” “The essence, then, of a claims-made policy is notice to the carrier within the policy period.”
Crowely Maritime Corp. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2019 WL 3294003 (11thCir. 2019)
The recent Eleventh Circuit Court of Appeal opinion in Crowely Maritime Corp. discussed the distinction between a claims-made insurance policy and an occurrence-based insurance policy. Professional liability policies are generally claims-made policies whereas commercial general liability policies are generally occurrence-based policies. While this opinion does not involve a construction matter, the case did concern the definition of a “claim” in a claims-made policy and whether such claim was timely reported to the insurer within the discovery period / extended reporting period.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Building Codes Evolve With High Wind Events
November 14, 2018 —
William L. Coulbourne - Construction ExecutiveDesigns for wind loads have been in building codes for a long time. Prior to the creation of the International Building Code, the three primary legacy codes had wind load provisions but they mostly dealt with wind loads on the building frame and had little load information about the building components or the exterior cladding.
Since Hurricane Andrew in 1992, building codes include more wind design information that comes from disaster investigations and wind engineering research conducted primarily at the university level. In 2000, the legacy building codes were replaced with the International Building Code (IBC). Residential buildings must comply with the International Residential Code (IRC). Both of these building code documents reference the engineering load standard, ASCE 7 Minimum Design Loads and Other Criteria for Buildings and Other Structures. This load standard has also been in existence for a long time; it now is revised every six years and the building codes revised every three years (IBC and IRC) reference ASCE 7 so the provisions in ASCE 7 become part of the building code requirements.
Reprinted courtesy of
William L. Coulbourne, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Texas Shortens Its Statute of Repose To 6 Years, With Limitations
October 02, 2023 —
Jason Daniel Feld & Roni Most - Kahana FeldEffective June 9, 2023, Texas has shortened its statute of repose from the existing 10-year statute for builders of new homes to 6-years under specific conditions. The significantly shorter statute of repose bars suits against construction contractors of detached one-and two-family homes and townhomes, filed six years after the substantial completion of such homes, where the contractor also furnished a written warranty in compliance with the statute. Notably, projects including apartments, mixed-use, and hotels are not covered by the new law. It is also noted that a grey area in the law exists as to whether condominiums will be covered by the statute. The statute of repose strictly bars the filing of any action, claim or arbitration demand regardless of when the injury was actually discovered (latent defects) and is separate and distinct from any applicable statute of limitations.
The New Texas Statute of Repose Law
Under the
Texas Civil Practice & Remedies Code § 16.009, persons who construct or repair improvements to real property cannot be sued for defective or unsafe conditions of the property or deficiencies in the construction or repair of the improvement later than 10 years after substantial completion of the improvement, except in certain narrow circumstances. This statute is known as the “statute of repose.” The statute applies not only to suits for construction defects, but also personal injury, wrongful death, contribution, and indemnity.
Reprinted courtesy of
Jason Daniel Feld, Kahana Feld and
Roni Most, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractors Have Remedies, Even if “Pay-if-Paid” Provisions are Enforced
February 19, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCIn a recent case in Kentucky[1], a sub-tier subcontractor sued the general contractor and owner for failure to pay for extra work. At the trial, the court held the subcontractor was entitled to recover under the theories of implied contracts and unjust enrichment, even though the subcontract contained a “pay-if-paid” clause. All parties appealed. In particular, the general contractor asserted that the pay-if-paid provision in the subcontract precluded recovery by the subcontractor. The issue was petitioned to the Supreme Court of Kentucky.
The question to be resolved by the Supreme Court of Kentucky was whether a pay-if-paid provision was enforceable as between a general contractor and subcontractor, and if so, whether the subcontractor could nevertheless pursue the owner directly for payment notwithstanding a lack of privity between the owner and subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
The Anatomy of a Construction Dispute Stage 2- Increase the Heat
January 21, 2015 —
Christopher G. Hill – Construction Law MusingsLast week we discussed the groundwork and circumstances of a construction claim. This week’s post will discuss the next steps, hopefully short of full blown arbitration or litigation that you, as a construction company, can pursue presuming your claim has been properly preserved.
If your contract requires certain steps such as informal resolution attempts or other items, these are the first things that must be done while still preserving your rights to pursue all remedies available. Instituting such contractually required resolution steps can and should be the first “notch” on the dial of increased pressure on the Owner, General Contractor or possibly Subcontractor against whom you have a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Exploring the Future of Robotic Construction with Dr. Thomas Bock
November 06, 2023 —
Aarni Heiskanen - AEC BusinessIn
this episode of the AEC Business podcast, host Aarni Heiskanen interviews Dr. Thomas Bock, a renowned expert in construction robotics. With 45 years of experience in the field and multiple books on the topic, Thomas shares his insights and expertise.
Tune in to learn more about his professional journey and the advancements in construction robotics.
An unconventional professional journey
Thomas’s journey in construction robotics began when he built his own house as a student. The labor-intensive process led him to explore the potential of robotics in construction. He studied civil engineering and architecture simultaneously, gaining a multidisciplinary understanding of the field. His interest in robotics grew when he saw the first welding robot at a Daimler-Benz factory in Stuttgart. This encounter sparked his curiosity and led him to question why robots couldn’t be used for assembling walls and buildings.
The Illinois Institute of Technology (IIT) in Chicago was one of Thomas’s destinations during his journey. There he studied under professors who had worked on iconic architectural projects. He also learned about Japanese companies like Toyota and Sekisui, which were producing houses using innovative methods. Intrigued by these advancements, Thomas secured a scholarship to study in Japan, where he discovered that the country was ahead of what he had known in the United States.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Comply with your Insurance Policy's Conditions Precedent (Post-Loss Obligations)
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesI am of the opinion that if your property insurer requests a sworn proof of loss, furnish one with the assistance of counsel (preferably). Ignoring the insurer’s request or refusing to comply with insurer’s request is NOT value-added; it is simply placing you at a disadvantage based on the insurer’s argument that you, as the insured, materially breached the policy. I generally find no value having to confront this expected argument. Instead, I find value making an effort to comply with post-loss obligations including the insurer’s request to submit a sworn proof of loss. Working with counsel can help you comply with post-loss obligations (conditions precedent) while not weakening the value or merits of your claim.
By way of example, in Edwards v. Safepoint Ins. Co., 46 Fla. L. Weekly D1086a (Fla. 4th DCA 2021), the insured did not provide its property insurer with the requested sworn proof of loss. The insurer moved for summary judgment that the insured’s failure to submit the sworn proof of loss was a material breach of the policy that rendered the policy ineffective. The trial court agreed and granted summary judgment. The Fourth District Court of Appeal affirmed explaining “[a] total failure to comply with policy provisions made a prerequisite to suit under the policy may constitute a breach precluding recovery from the insurer as a matter of law. If, however, the insured cooperates to some degree or provides an explanation for its noncompliance, a fact question is presented for resolution by a jury.” Edwards, supra, quoting Haiman v. Federal Ins. Co., 798 So.2d 811, 812 (Fla. 4th DCA 2001).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com