New Braves Stadium Is Three Months Ahead of Schedule, Team Says
September 03, 2015 —
Michael Buteau – BloombergConstruction of the new $1.1 billion home of Major League Baseball’s Atlanta Braves is about three months ahead of schedule, according to team executives.
“We’ve built a really solid, aggressive, efficient plan,” Mike Plant, head of the team’s business operations, said in an interview Thursday during a brick-laying ceremony. “No one has ever built a ballpark of this scale and scope in 39 months, and we’re going to do it in 36.”
The 41,500-seat stadium, 14 miles northwest of Turner Field and known as SunTrust Park, will be about 20 percent smaller than the existing ballpark and could be completed by mid-November 2016, Plant and Braves Chairman Terry McGuirk said. The complex will include a 250-room Omni hotel, a nine-story corporate office for Comcast Corp. and the Roxy Theatre, a 4,000-seat music venue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Buteau, Bloomberg
New York Appellate Team Obtains Affirmance of Dismissal of Would-Be Labor Law Action Against Municipal Entities
August 12, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (July 11, 2024) - In Charlot v. City of New York, ___ A.D.3d ___, 2024 NY Slip Op 03161 (2d Dep’t 2024), New York Associate Dean Pillarella, a member of the Appellate Practice, recently obtained an affirmance of the lower court’s dismissal of the plaintiff’s action against the City of New York (“the City”) for failure to timely serve a notice of claim. New York Partner Meghan Cavalieri, a member of the Construction Practice, and her team authored and argued the initial motion to dismiss.
The plaintiff alleged to have sustained injuries as a result of a construction-site accident on December 8, 2020, on City-owned property in the course of the construction of a school by the New York City School Construction Authority. N.Y. General Municipal Law (“GML”) § 50-e(1)(a), requires service of a notice of claim within 90 days after the claim arises as a condition precedent to the commencement of a tort action. The plaintiff served no notice of claim until June 2021 and commenced an action in January 2022, alleging violations of N.Y. Labor Law §§ 240(1), 241(6), and 200. Given the plaintiff’s failure to comply with GML § 50-e(1)(a), Meghan and her team rejected the notices of claim as untimely. The plaintiff then moved for leave to deem the notices of claim timely served nunc pro tunc. In response, Meghan and her team opposed the motion and cross-moved to dismiss the action.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Construction Defect Suit Can Continue Against Plumber
June 28, 2013 —
CDJ STAFFThe Kansas Court of Appeals has reversed a district court ruling that a homeowner’s suit against a plumber was barred under the economic loss doctrine. However, subsequently the Kansas Supreme Court “refused to extend the economic loss doctrine to homeowner claims against construction contractors.” In light of this, the appeals court sent the case back to the lower court.
The case, Coker v. Siler, was brought by Gregory Coker, who had bought a home from J.M.C. Construction. JMC purchased an unfinished house from Michael D. Siler in August 2006. As part of the completion process, John M. Chaney, the president of JMC, installed the water line into the residence. Mr. Coker bought the home in September 2007.
Starting in April 2008, Mr. Coker noticed that his water bills had increased. Mr. Coker could find “no evidence of a leak above the ground,” so he contacted JMC Construction. Mr. Chaney had R.D. Johnson Excavation dig up the water line, after which a gap was discovered that had been allowing water to flow under the foundation. In addition to the higher water bills, an engineer determined that the water “resulted in cracks in the wall and uneven doors.”
Mr. Coker sued, Siler, J.M.C. and Chaney for negligence, breach of implied warranty, strict liability, and breach of express warranty. J.M.C. and Chaney requested a summary judgment. The court dismissed Mr. Coker’s claims of negligence, strict liability, and breach of implied warranty on the basis of the economic loss doctrine, rejecting a petition from Mr. Coker to reconsider. The court, however, allowed Mr. Cocker to proceed with his claim of express warranty. In December, 2011, Mr. Coker accepted an offer from J.M.C. of $40,000.
Mr. Coker then appealed the summary judgment, making the claim that while the court’s decision was based on Prendiville v. Contemporary Homes, Inc., this has now been overruled by David v. Hett. In this case, “the court ultimately found the rationale supporting the economic loss doctrine failed to justify a departure from a long time of cases in Kansas that establish a homeowner’s right to assert claims against residential contractors.” The appeals court concluded that “although the district court properly relied on the law as it existed at the time of its ruling, the intervening change in the law necessarily renders the conclusion reached by the district court erroneous as a matter of law.”
In sending this case back to the district court, the appeals court noted that the lower court will need to determine if the “defendant accused of negligence did not have a duty to act in a certain manner towards the plaintiff,” in which case “summary judgment is proper. Mr. Coker claims that Mr. Chaney did indeed have this duty.
Further, Mr. Coker claimed that Mr. Chaney had a duty arising out of implied warranty. The appeals court questioned whether the district court properly applied the economic loss doctrine to this claim, because despite being president of the construction company, Mr. Chaney “in his individual capacity as a plumber performing work for Coker, was not a party to the J.M.C. contract.” The court found that “Coker’s claim that Chaney breached an implied duty within such a contract fails as a matter of law.”
However, the court did uphold Cocker’s claim of a contractor liability for injury to a third party, noting that “Chaney owed Coker a legal duty independent of Coker’s contact with J.M.C.” The appeals court left it to the district court to determine if the defect that caused the damage was present when the house left J.M.C.’s possession.
The case was reversed and remanded “with directions to reinstate Coker’s claim of negligence against Chaney in his individual capacity as a plumber.”
Read the court decisionRead the full story...Reprinted courtesy of
Curtain Wall Suppliers Claim Rival Duplicated Unique System
February 28, 2022 —
Annemarie Mannion - Engineering News-RecordChicago-area construction material suppliers that hold patents for a curtain wall system used in high-rise construction projects are suing a rival, claiming it created a knock-off of the system based on a former employee’s knowledge and put the system to use on construction projects.
Reprinted courtesy of
Annemarie Mannion, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Stuck in Seattle: The Aggravating Adventures of a Gigantic Tunnel Drill
April 01, 2015 —
Karen Weise – BloombergAbout 20 workers wearing hard hats and reflective vests clump together on the edge of a chasm near Seattle’s waterfront, peering down a hole 120 feet deep and 83 feet wide. The last men have been craned out of the pit in a yellow metal cage. Gulls squawk. A TV news helicopter hovers overhead.
A dozen journalists stand nearby on the bed of a truck. We’re here to see Bertha, one of the world’s biggest tunneling machines. Or at least a piece of her. A 240-foot crane is about to haul a 540,000-pound steel shield out of the ground, 20 months after Bertha started digging a highway. Almost imperceptibly, the crane starts rising.
The event, on a Thursday in mid-March, is part of a massive rescue mission to fix the $80 million machine. She broke abruptly in December 2013 after boring through just 1,000 feet, one-ninth of her job. Her seals busted, and her teeth clogged with grit and pieces of an 8-inch steel pipe left over from old groundwater tests. She stopped entirely.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Weise, BloombergMs. Weise may be contacted at
kweise@bloomberg.net
Business Insurance Names Rachel Hudgins Among 2024 Break Out Award Winners
April 22, 2024 —
Hunton Insurance Recovery BlogWe are pleased to announce that counsel
Rachel E. Hudgins has been recognized as one of Business Insurance’s 2024 Break Out Award winners. The magazine’s Break Out Awards honor 40 top professionals each year from a competitive field of nominees who have under 15 years’ experience in the insurance and risk management sector and are “on track to be the next leaders in the risk management and property/casualty insurance field.”
Clients describe Rachel as their “chief contact for high-exposure coverage work.” She meets clients where they are with a curiosity and interest in their business strategies, as well as an ability to distill complex insurance concepts into digestible terms. Rachel also has depth of experience in coverage litigation. She has litigated hundreds of insurance coverage and bad faith claims in state and federal courts across the country and US territories.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Court Agrees to Stay Coverage Matter While Underlying State Action is Pending
October 29, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court granted the insured's motion to stay the coverage action while the construction defect case was pending in state court. Auto Owners Ins. Co. v. Essex Homes Southeast, Inc., 2014 U.S. Dist. LEXIS 133120 (D. S.C., Sept. 23, 2014).
The homeowners sued Essex Homes in state court for construction defects in a home built and sold to them by Essex Homes. The suit sought damages for property damage based on negligence, breach of implied warranty, and breach of express warranties arising out of the alleged construction defects. The complaint alleged that a water leak in the house caused water damage and resulted in mold growth that was not discovered for several years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
OSHA’s Multi-Employer Citation Policy: What Employers on Construction Sites Need to Know
September 09, 2019 —
Phillip C. Bauknight - Construction ExecutiveMulti-employer worksites are a frequent occurrence in the construction industry as employees from various companies often occupy the same site while a project is being completed. While the need for employees from different companies may be necessary to perform the various tasks required by a project, the presence of multiple employers, and their employees, on the same worksite can result in an increased risk of safety hazards.
Companies performing construction work should be, and generally are, aware of OSHA’s ability to issue citations for workplace safety violations. What many companies may not know, however, is that OSHA’s ability to cite employers is not limited to workplace conditions that are unsafe only to that employer’s direct employees. Rather, OSHA also has the ability to cite an employer, and often does issue such citations, for conditions that could result in injury or death to another company’s employees.
The policy which provides OSHA with this citation ability is CPL 02-00-124 and is called the Multi-Employer Citation Policy (the “Policy”). Under the language of the Policy, OSHA has the ability to cite multiple employers for violations of the Occupational Safety and Health Act for the same hazardous workplace condition. Critically, responsibilities under the Policy do not depend on the employer’s job title but are determined by the employer’s role.
Reprinted courtesy of
Phillip C. Bauknight, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of