Sometimes a Reminder is in Order. . .
June 21, 2021 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Court of Appeals Issues Decision Regarding Second-Tier Subcontractors and Pre-Lien Notice
February 06, 2023 —
Travis Colburn - Ahlers Cressman & SleightVelazquez Framing, LLC (“Velazquez”) v. Cascadia Homes, Inc. (“Cascadia”) is a Court of Appeals, Division 2 case where the primary issue on appeal was whether a second tier subcontractor was required to provide pre-lien notice under RCW 60.04 for its labor.
The defendant, Cascadia, was the general contractor that planned to build a home on property it owned in Lakewood, Washington.[1] High End Construction, LLC (“High End”), submitted a bid to Cascadia for framing work on the home. High End began work on Cascadia’s home, but later subcontracted with Velazquez to complete the framing work.[2] Velazquez did not submit a prelien notice for its work on Cascadia’s home, and Cascadia claimed it was unaware that High End subcontracted with Velazquez for framing at the project.
High End invoiced Cascadia and was paid for its work, but High End never paid Velazquez. Subsequently, Velazquez recorded a lien for both labor and materials, and later filed a complaint to foreclose its lien. Cascadia, due to the fact Velazquez did not provide it with prelien notice, moved for summary judgment, arguing prelien notice was required under RCW 60.04.031(1)[3] and the labor portion of a lien cannot be segregated where a subcontractor’s lien includes both labor and materials. Velazquez argued that no prelien notice was required under RCW 60.04.021[4] and RCW 60.04.031 and claimed that subcontractors can segregate the labor portion from the materials portion. The trial court granted Cascadia’s motion and ruled Velazquez did not fall within one of the exceptions for prelien notice in RCW 60.04.031(2), and therefore, could not enforce the lien. Velazquez appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Chinese Billionaire Developer Convicted in UN Bribery Case
August 02, 2017 —
Bob Van Voris - BloombergA Chinese developer was convicted of charges he paid bribes to win backing for a United Nations conference center that he hoped to build in Macau.
A jury in Manhattan on Thursday found the developer, billionaire Ng Lap Seng, guilty of all six charges he faced, including conspiracy, bribery and money laundering, in the biggest UN corruption scandal since the oil-for-food program in the early 2000s. Prosecutors claimed Ng funneled hundreds of thousands of dollars to former UN General Assembly President John Ashe and other officials.
Read the court decisionRead the full story...Reprinted courtesy of
Bob Van Voris, Bloomberg
Disrupt a Broken Industry—The Industrial Construction Sandbox
November 23, 2020 —
Brian Sayre - Construction ExecutiveThe existing built environment structure—arguably—is antiquated and must be disrupted to meet the rapidly changing demands of the industry. The built environment struggles with labor shortages, addressing demand, sustainability needs, cost controls, affordability and efficiency gains. Even with the advancement of emerging technology trends, the construction industry still lags behind more technologically advanced verticals.
What’s missing? Something is needed beyond incremental change that will truly disrupt the industry, increase the value of other innovations and tackle industry challenges.
The answer is industrialized construction technology with offsite manufacturing as the cornerstone. Technology innovation becomes exponentially more valuable when placed in this context. Shadow Ventures, a venture capital firm focused on the built environment, set out to test these theories with verifiable research published this year in a report titled, “Disrupt a Broken Industry—The Industrial Construction Sandbox.”
Reprinted courtesy of
Brian Sayre, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Amendments to California Insurance Code to Require Enhanced Claims Handling Requirements for Claims Arising Out Of Catastrophic Events
September 04, 2019 —
Jon A. Turigliatto, Esq. & Ravi R. Mehta, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinSenator Bill Dodd, who represents Napa County and surrounding areas in the California Senate, has recently introduced Senate Bill 240, known colloquially as The Insurance Adjuster Act of 2019. S.B. 240 would amend the California Insurance Code to streamline and organize claim processing, particularly during a state of emergency / catastrophic events. The proposal is in response to a series of devastating wildfires which ravaged the Sonoma County and Napa Valley wine country during the 2017 fire season (Atlas, Tubbs, and Nun fires). Many of Senator Dodd’s constituents reported difficulty in navigating the claim process due to multiple claim professionals handling a single claim, many of whom were outside of California, and many of whose capabilities were challenged.
S.B. 240 would direct the Department of Insurance to issue annual notices setting forth legal developments as they relate to property insurance policies, including best practices for evaluating damage caused by an emergency, and requires out-of-state claims professionals to certify, under penalty of perjury, that they have read these notices along with claim adjusting literature also prepared by the Department of Insurance.
S.B. 240 would also require insurers to designate a primary point of contact for their customers during a state of emergency until the claim is closed or litigation is initiated. While the proposed legislation would not prohibit multiple claims professionals handling a single claim, it would provide for training standards issued by the Department of Insurance on how best to handle claims in a state of emergency.
Further, S.B. 240 would require claims professionals who are not licensed in California (1) to be supervised by a licensed California claims professional, and (2) to read and understand the annual emergency claim adjusting literature issued by the Department of Insurance within 15 calendar days of beginning adjusting of claims in California.
The bill passed the Senate by unanimous vote and is pending in the Assembly. The bill is also supported by Insurance Commissioner Ricardo Lara. Accordingly, the bill is expected to pass the Legislature. Once enacted, S.B. 240 would significantly elevate claim adjusting requirements related to emergencies, such as natural disasters, by placing greater oversight in the Department of Insurance, and greater responsibility on claims professional within and outside of California. How pragmatic these requirements are and what practical impact they will have on the industry are developments which we will follow and provide further commentary as this bill makes its way through the California legislature and into the California Insurance Code.
Reprinted courtesy of
Jon A.Turigliatto, Chapman Glucksman Dean Roeb & Barger and
Ravi R. Mehta, Chapman Glucksman Dean Roeb & Barger
Mr. A.Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Mehta may be contacted at rmehta@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Attorney’s Fees on Attorney’s Fees
June 13, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn a recent
case, the appellate court held that the attorney’s fees provision in the contract was NOT broad enough to entitle the prevailing party to recover attorney’s fees for litigating the amount of attorney’s fees. This is known as “fees on fees” which is when you can recover your prevailing party attorney’s fees when you are fighting over the quantum that should be awarded to you as the prevailing party.
The attorney’s fees provision at-issue stated:
“In any lawsuit to enforce the Lease or under applicable law, the party in whose favor a judgment or decree has been rendered may recover its reasonable court costs including attorney’s fees from the non-prevailing party.”
Language similar to this language can be found in many contracts as a prevailing party attorney’s fees provision.
However, this provision was NOT broad enough to recover “fees on fees.” As explained in
this article, if this is a consideration, you can negotiate or include this provision into your construction contract by expanding the scope of the prevailing party attorney’s fees provision to clarify that it entitles the prevailing party to recover attorney’s fees in litigating the amount of attorney’s fees.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Potential Coverage Issues Implicated by the Champlain Towers Collapse
March 21, 2022 —
Theresa A. Guertin & Holly A. Rice - Saxe Doernberger & Vita, P.C.In June 24, 2021, the Champlain Towers South in Surfside, Florida collapsed, killing nearly 100 individuals (the “Collapse”). As experts uncover more information regarding the cause of the Collapse, those individuals who have filed lawsuits as well as the potentially culpable defendants are looking to insurers for coverage of their bodily injury and property damage claims.
Contractors, engineers, and other professionals are or anticipate being sued for their roles in the Collapse. Those professionals have professional liability policies and/or director and officer liability policies. Likewise, the condominium association’s commercial general liability (CGL) policies and its business property policy may have a duty to defend and/or indemnify their insureds as well. Finally, individual unit owners/renters may look to their homeowners’ insurance, auto insurance, health insurance, and/or life insurance policies for coverage.1
The potential breadth of insurance coverage issues raised by the Collapse is beyond the scope of this article. The article will consider some concerns that could impact insurance coverage under a standard CGL policy in the case of a building collapse.
Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita, P.C. and
Holly A. Rice, Saxe Doernberger & Vita, P.C.
Ms. Guertin may be contacted at TGuertin@sdvlaw.com
Ms. Rice may be contacted at HRice@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of