Change #7- Contractor’s Means & Methods (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaFirst, a little history: as you know, means, methods, techniques, sequences, and procedures are all part of the Contractor’s responsibility on a construction site. However, when the AIA A201 was last revised, in 2007, there was a provision put in for that rare time when the Contract Documents gave specific instructions concerning a particular construction method. If the Contractor viewed such instructions as unsafe, he was to give notice to the Owner and Architect, and was not to proceed with that portion of the Work without further written instructions from the Architect. If the Architect directed him to proceed, the Contractor was absolved from any risks with following that instruction. Instead, the Owner assumed the responsibility for any loss or damage.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Ohio Rejects the Majority Trend and Finds No Liability Coverage for a Subcontractor’s Faulty Work
December 11, 2018 —
Shannon M. Warren - The Subrogation StrategistIn Ohio N. Univ. v. Charles Constr. Servs., 2018 Ohio LEXIS 2375 (No. 2017-0514, October 9, 2018), the Supreme Court of Ohio was recently called upon to determine if a general contractor’s Commercial General Liability (CGL) insurance policy provided coverage for defective work completed by its subcontractor. Rejecting the majority trend, the court held that, because the subcontractor’s faulty work was not an “occurrence” caused by an accident – i.e. a fortuitous event – within the meaning of the contractor’s CGL policy, the insurer did not have to defend or indemnify the contractor with respect to the plaintiff’s claims.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
Partner Vik Nagpal is Recognized as a Top Lawyer of 2020
June 29, 2020 —
Bremer Whyte Brown & O'Meara LLPPlease join us in congratulating San Diego Partner
Vik Nagpal for being recognized as a Top Lawyer of 2020 by San Diego Magazine! San Diego Magazine works with Martindale-Hubbell to choose top lawyers who have reached the highest level of ethical standards and professional excellence. Vik Nagpal was evaluated and given the highest ratings by the colleagues using a peer reviewed
Vik Nagpal is the managing partner of Bremer Whyte Brown & O’Meara LLP’s San Diego offices, as well as directing the firm’s business development.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Loose Bolts Led to Sagging Roof in Construction Defect Claim
February 10, 2012 —
CDJ STAFFThough the sagging roof is neither leaking nor a safety hazard, the town of Waynesville, North Carolina is suing the builder of its new fire station, as reported in the Smoky Mountain News. The engineers who examined the roof found a substantial number of loose bolts in the roof trusses. Additionally, the trusses themselves have become bent.
Tom Galloway, Waynesville’s Town Manager said “it needs to be remedied and fixed.” He said that the builder, Construction Logic, “never indicated a willingness to fix the roof.” The town is seeking the cost of repair, which Galloway estimated could be $400,000, and an additional $30,000 in damages. The suit states that Construction Logic failed to follow the plan specifications for the roof.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Statement on Devastating Tornado Damages Throughout U.S.
December 20, 2021 —
Tom Smith, Executive Director - American Society of Civil Engineers (ASCE)WASHINGTON, DC. – We are deeply saddened by the tragic tornado storms that ravaged six states across the Midwest and Southeastern portions of the U.S. last Friday evening, resulting in loss of life in five of those six states. Even though warnings were issued throughout the region, storms of this magnitude can be difficult to prepare for. Nevertheless, as civil engineers, our mission is to continually advance the design and construction of safe, reliable, and resilient building structures and infrastructure systems to mitigate the damage caused by storms.
ASCE 7 — a nationally-adopted, consensus-based engineering standard that is the primary reference of structural design requirements in all U.S. building codes — was recently updated to include a new chapter for tornado loads in the 2022 edition. The new tornado provisions in ASCE 7-22 were a result of a decade-long effort in partnership with the National Institute of Standards and Technology following the 2011 Joplin, MO Tornado. ASCE 7-22 provides updated design requirements for a variety of structures, including many of the types impacted by Friday's storms.
In an effort to assist, the Structural Engineering Institute of ASCE is currently offering free access to a report issued after the Joplin, MO tornado in 2011 that killed more than 150 people.
Joplin, Missouri, Tornado of May 22, 2011: Structural Damage Survey and Case for Tornado-Resilient Building Codes presents the observations, findings, and recommendations of an engineering reconnaissance team that surveyed residential structures and schools in the tornado path shortly after the event. The EF 5 tornado cut a seven-mile swath through Joplin, Missouri; it destroyed more than 5,000 buildings and killed more than 150 people.
We will continue to keep those who have been affected in our hearts and thoughts, and we share our heartfelt sympathies.
For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
The Clock is Ticking: Construction Delays and Liquidated Damages
September 18, 2023 —
Tiffany Harrod - ConsensusDocsWith the on-going shortage of construction workers in the industry and other factors ranging from weather to procurement problems, the threat of project delay is real. When a contract contains a liquidated damages clause for assessing project delays, real financial consequences for contractors can result. Courts have long allowed parties to apportion contractual risks as they deem appropriate especially in the commercial context where the parties are considered to be sophisticated even if their bargaining power is not equal. Liquidated damage provisions such as those for delay that are found in construction contracts are not unusual but they must be crafted in such a way as to be enforceable and not violate public policy.
A liquidated damage clause in a construction contract is a customary way for the parties to deal with the possibility of delay in the completion of a project and the potential losses flowing from the delay.[
1] In their most basic form, the party in breach, which is more often than not the contractor, is obligated to pay the non-breaching party, usually the project owner, some fixed sum of money for the period that exceeds the designated completion date that was agreed upon in advance and memorialized in the contract. (It is after all no secret that these provisions are primarily for the owner’s benefit.) The non-breaching party is then compensated for losses associated with the delay without the time and expense of having to prove in either a civil suit or an arbitration proceeding what the actual damages are. This option is particularly attractive to project owners because the liquidated damages assessment can simply be withheld from payments owed to the contractor once the agreed-upon completion date has been passed.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Harrod, Peckar & AbramsonMs. Harrod may be contacted at
tharrod@pecklaw.com
Resulting Loss From Faulty Workmanship Covered
May 20, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Washington Supreme Court found there was coverage for resulting loss despite the original faulty contraction, an exclusion in the policy. Gardens Condominium v. Farmers Ins. Exchange, 544 P.3d 499 (Wash. 2024).
Farmers issued a policy to Gardens Condominium providing coverage for loss or damage caused by a "Covered Cause of Loss." "Covered Cause of Loss" was defined as any risk of direct physical loss. However, a loss was not covered if it was caused by an excluded event. The policy further provided that damage was caused by an excluded event if that event "initiates a sequence of events that results in loss or damage, regardless of the nature of any intermediate or final event in that sequence." The policy excluded coverage for faulty, inadequate, or defective design, specifications, workmanship, repair, construction, or renovation. The faulty workmanship exclusion also contained a resulting loss exception: "[I]f loss or damage caused by a Covered Cause of Loss results, we will pay for that resulting loss or damage."
Gardens found damage to the building that was caused by faulty design and construction of the building's roof. There was insufficient interior vents and the design of the rafters and joists prevented need ventilation Water vapor condensed on the underside of the roof sheathing, causing damage. Gardens redesigned and repaired the roof assembly to increase ventilation and eliminate condensation by installing sleepers on top of the joists.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Can Businesses Resolve Construction Disputes Outside of Court?
August 19, 2024 —
Scott L. Baker - Los Angeles Litigation BlogTime is of the essence in any construction project. So, if a dispute arises at any point, business owners generally wish to avoid the chance of a time-consuming case going to court.
Can California construction businesses
manage these disputes effectively outside of court? It is possible in some cases. Business owners should carefully consider these three steps.
1. Go Back to the Contract
Even if the contract is at the center of the dispute, it is important to refer to any details regarding dispute resolution included within the document. It is common for contracts to have some form of a dispute resolution clause. In such a case, both parties should follow the steps outlined in that agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com