Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Clean Air, Clean Water, Endangered Species and Deliberative Process Privilege
April 19, 2021 —
Anthony B. Cavender - Gravel2GavelThe federal courts have issued some significant environmental law rulings in the past few days.
THE U.S. SUPREME COURT
U.S. Fish and Wildlife Service v. Sierra Club, Inc.
On March 4, 2021, the court held that the deliberative process privilege of the Freedom of Information Act shields from disclosure in-house draft governmental biological opinions that are both “predecisional” and deliberative. According to the court, these opinions, opining on the Endangered Species Act (ESA) effects on aquatic species of a proposed federal rule affecting cooling water intake structures—which was promulgated in 2019—are exempt from disclosure because they do not reflect a “final” agency opinion. Indeed, these ESA-required opinions reflect a preliminary view, and the Services did not treat them as being the final or last word on the project’s desirability. The Sierra Club, invoking the FOIA, sought many records generated by the rulemaking proceeding, and received thousands of pages. However, the Service declined to release the draft biological opinions that were created in connection with the ESA consultative process.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Florida’s Statute of Limitations / Repose for Actions Founded on Construction Improvement Modified
April 25, 2023 —
David Adelstein - Florida Construction Legal UpdatesOn April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified. This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.
At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.) Important things to note:
- Statute of Repose. The statute of repose has been reduced from 10 years to 7 years. There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Adaptive Reuse: Creative Reimagining of Former Office Space to Address Differing Demands
March 27, 2023 —
Cait Horner, Allan C. Van Vliet & Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law BlogEmpty office buildings downtown. A housing shortage in almost every major market. Is there a way to address both issues at once by converting historic but underutilized office buildings into apartments and condos in city centers? It’s an idea that has been discussed, and in some cities, implemented in recent years. But while the idea seems simple enough—repurpose existing office space for residential and mixed-use projects—there are some real challenges limiting the feasibility of large-scale office to residential conversion.
The commercial real estate market is facing an uncertain future. Even as some companies have started requiring that their workers return to the office, many continue to operate under their hybrid or fully remote working models, which companies may commit to permanently. And while some big cities have seen office occupancy levels increase in the past few months (CBRE notes that Austin and Houston both saw occupancy levels above 60% in January, up around 25% from 2022 levels), the ongoing impact of COVID-19 and uncertainty in the global financial markets are keeping many office buildings empty in major cities around the country. Those tenants who are returning to the office are focusing their search for office space on high-quality, sustainable, amenity-filled spaces to entice workers to return to the office. This flight to quality leaves some older and, in many cases, architecturally relevant, office buildings behind. As a result, there are growing opportunities for the potential adaptive reuse of these existing underutilized structures.
Reprinted courtesy of
Cait Horner, Pillsbury,
Allan C. Van Vliet, Pillsbury and
Adam J. Weaver, Pillsbury
Ms. Horner may be contacted at cait.horner@pillsburylaw.com
Mr. Van Vliet may be contacted at allan.vanvliet@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Umbrella Policy Must Drop Down to Assist with Defense
May 12, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that an umbrella carrier was obligated to assist the general liability insurer in defending the insured. Am. States Ins. Co. v. Insurance Company of the State of Pennsylvania, 2016 U.S. Dist LEXIS 38128 (E.D. Cal. March 23, 2016).
Sierra Pacific Industries obtained rights to timber harvesting operation on a parcel of land in northern California. Sierra hired Howell's Forest Harvesting to perform certain timber harvest operations under the terms of a logging agreement. The logging agreement required Howell to obtain a CGL policy and to name Sierra as an additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Does a Contractor (or Subcontractor) Have to Complete its Work to File a Mechanics Lien
January 10, 2018 —
Wally Zimolong - Zimolong LLCYes. There seems to be common misconception that a contractor, subcontractor, or supplier, has six months
from its last day of work on the project to file a mechanics lien. I frequently see mechanics liens whereby the claimant states “Claimants last day of work on the project was X.” However, Section 1502 (49 P.S. Section 1502) of the Pennsylvania Mechanics Lien is clear that a lien must be filed within six month of “the completion of his work.” Under the Lien Law, “completion of the work” is a defined term and means “means performance of the last of the labor or delivery of the last of the materials required by the terms of the claimant’s contract or agreement, whichever last occurs.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Texas LGI Homes Goes After First-Time Homeowners
May 13, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Big Builder, while many consumers have “gone to rentals…as the homeownership rate fell,” that hasn’t stopped Texas-based builder LGI Homes from marketing to the entry-level buyer: “We do not believe that we’re becoming a renter society,” Eric Lipar, LGI CEO told Big Builder. “We believe there is a need and a desire for homeownership.”
“The real growth will be powered by an aggressive sales and marketing operation that aims to pull renters out of their apartments (or single-family rentals) and into LGI homes,” reported Big Builder. “So far this pitch has worked in Texas (Dallas, Houston, San Antonio, and Austin), in addition to Phoenix and Tampa, Fla.”
Read the court decisionRead the full story...Reprinted courtesy of
Accident/Occurrence Requirement Does not Preclude Coverage for Vicarious Liability or Negligent Supervision
June 06, 2018 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn Liberty Surplus Ins. Corp. v. Ledesma & Meyer Construction Co., Inc. (No. S236765, filed 6/4/18) (L&M), the California Supreme Court ruled that the liability insurance requirement that injury be caused by an “occurrence,” defined as an “accident,” does not preclude coverage of an employer’s independent tort liability for injury deliberately caused by its employee.
In L&M, Liberty insured a construction company that contracted to manage a construction project at a middle school in San Bernardino, California. A 13-year-old student subsequently sued the company in state court, alleging that she had been sexually molested by a company employee, Hecht. Among others, she alleged a cause of action for negligent hiring, retention and supervision of the employee. The construction company tendered to Liberty, which defended the employer under a reservation of rights while seeking declaratory relief in federal court. The district court granted summary judgment for Liberty, ruling that the injury was not caused by an “occurrence.” On appeal, the 9th Circuit Court of Appeals certified the question to the California Supreme Court as a matter of state law.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of