N.J. Appellate Court Applies Continuous Trigger Theory in Property Damage Case and Determines “Last Pull” for Coverage
November 15, 2017 —
K. Alexandra Byrd – Saxe Doernberger & Vita, P.C.The New Jersey Superior Court, Appellate Division, published an important decision addressing several fundamental issues regarding how a commercial general liability (CGL) policy applies to long-term property damage. The court held that: (1) a continuous trigger theory of coverage may be applied to third-party liability claims involving progressive property damage caused by an insured’s allegedly defective work; (2) the “last pull” (i.e., the cutoff point) of the continuous trigger is when the “essential nature and scope” of the property damage first becomes known or could reasonably be known; and (3) the “last pull” is not when the property damage is “attributed” to the insured’s faulty work.
The underlying action in Air Master & Cooling Inc. v. Selective Ins. Co., et al. 1 concerned property damage arising out of the construction of a seven-story, 101-unit condominium building in Montclair, New Jersey. The project’s construction manager hired Air Master & Cooling, Inc. (Air Master) to perform HVAC work on the project, including installing individual HVAC equipment in each resident’s unit from 2005 to 2008. In early 2008, unit owners began complaining about water infiltration and damage to their windows, ceilings, and other portions of their units. The general contractor and developer began assessing the damage and making repairs. Eventually, in April 2010, an expert consultant performed a moisture survey of the roof and discovered 111 areas that were damaged by water infiltration. The expert report indicated that “it [was] impossible to determine when [the] moisture infiltration occurred.”
Read the court decisionRead the full story...Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C.Ms. Byrd may be contacted at
kab@sdvlaw.com
The Need to Be Specific and Precise in Drafting Settling Agreements
December 30, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCThe case of Bituminous Casualty Corp. v. Hartford Casualty Insurance Corp., 2013 WL 452374 (D. Colo. February 6, 2013) is instructive as an example of both the confusion and resulting escalation of litigation that can result from a lack of clarity in settlement negotiations. This is particularly true where parties settle outside of their insurance coverage, and/or without notifying their insurer(s), which have denied coverage.
The case involved coverage litigation following settlement of a multi-party construction defect case involving the Rivergate multi-family residential development in Durango, Colorado. The condominium owners association sued, among others, the developer (Rivergate Lofts Partners, hereafter “RLP”) and the general contractor (Genex Construction, LLC, hereafter “Genex”). This follow-on case involved the insurers for RLP (“Hartford”) and Genex (“Bituminous”). The coverage dispute was complicated by the Bituminous allegations that Hartford insured Genex in its alleged role as a manager for RLP, as part of Hartford’s insurance of RLP more generally.
The underlying facts were that Hartford denied insurance coverage and defense to Genex/Bituminous. The underlying construction defect case went to mediation, with the COA, RLP, and Genex all in attendance with their respective insurer representatives, and coverage counsel. While the evolving facts of that mediation were later disputed as to their motives, intentions, and the contemporaneous knowledge of the parties, the facts reflected in documents were fairly clear.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.W. Berkeley Mann, Jr. can be contacted at
mann@hhmrlaw.com
The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle
December 20, 2017 —
Dave Suggs - CDJ STAFFSeattle Washington is experiencing a shortage of in-city condos. Of the 27,000 units of new housing being built in downtown Seattle, 94 percent will be rentals. As housing prices are rising in the US’s fastest-growing large city, the median home price is $660,000. Dean Jones of the Seattle Magazine reports on why consumers consider condos, but home developers don’t in his article “The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle.”
Reason 1, condominiums don’t always offer high returns and can be riskier for the home developer. Reason 2, the Washington State Condo Act “overprotects” buyers of condos with over-the-top warranties that makes everyone in the industry afraid to work with condos. Reason 3, the cost of condo building is increased because of the risk of defect litigation. Reason 4, condo presale buyers are not required to deposit a percentage to invest in a new development and before closing could decide to walk away. Reason 5, there is a lot of interest in apartment buildings from investment groups.
Reason 6, investors whose goal is to own “trophy” assets in rising markets can’t wait the years it takes developers to plan and construct a new multistory community. Reason 7, since rent prices have risen 50 percent on average in the last 7 years, it’s profitable to be a landlord. Reason 8, the millennials who live and work in this tech oriented region prefer to rent because of living through the rise and fall of the housing market. Reason 9, the costs is rising each year to deliver new projects. Reason 10, high-rise zoning was adopted 2 years before the recession, so just as condo development was gearing up, apartment building took over.
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Halts Enforcement of the OSHA Vaccine or Test Mandate
January 17, 2022 —
Stephen E. Irving, Kevin J. O’Connor, Aaron C. Schlesinger & Lauren Rayner Davis - Peckar & AbramsonThe United States Supreme Court today stayed enforcement of the OSHA emergency temporary standard (ETS) requiring employers with 100 or more employees to require employees either be “fully vaccinated” against COVID-19 or submit to weekly testing. The ruling immediately stops enforcement of the rule which had gone into effect on January 10, 2022.
Today’s order raises significant doubt as to whether the ETS requirement will ever take effect in its current form. A 6 to 3 majority of the Supreme Court justices issued the profound statement that the parties opposed to the rule “are likely to succeed on the merits of their claim that the Secretary lacked authority to impose the mandate.” The Court went on to state that the OSH Act does not authorize the agency to “set . . . broad public health measures,” such as the found in the current emergency standard.
Reprinted courtesy of
Stephen E. Irving, Peckar & Abramson,
Kevin J. O’Connor, Peckar & Abramson,
Aaron C. Schlesinger, Peckar & Abramson and
Lauren Rayner Davis, Peckar & Abramson
Mr. Irving may be contacted at sirving@pecklaw.com
Mr. O'Connor may be contacted at koconnor@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Davis may be contacted at ldavis@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
In Oregon Construction Defect Claims, “Contract Is (Still) King”
April 25, 2012 —
CDJ STAFFWriting in Oregon’s Daily Journal of Commerce, David Anderson looks at the aftermath of the case Abraham v. T. Henry Construction, Inc. In that case, Anderson notes that “the homeowners hired a contractor to build their house, and subsequently discovered extensive water damage” “after expiration of the time to sue for breach of contract.” The homeowners claimed negligence. Oregon’s Supreme Court concluded that “homeowners only had to prove that the contractor negligently caused reasonably foreseeable harm to the homeowner’s property.”
Anderson views this decision as leading to two risks for contractors. “First, contractors can be held liable in tort for breaching building code standards; second, they can be held liable for violating the often-difficult-to-define ‘reasonable care’ standard.” But here, “contract can be king.” The Oregon Supreme Court noted that the contractor “could have avoided exposure to the general ‘reasonable care’ standard by more carefully defining its obligations in the original construction contract.”
He notes that contractors who fail to define their obligations or use generic definitions “may be exposing themselves to a more vague scope of liability.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Legislature Kills SB 20-138 – A Bill to Extend Colorado’s Statute of Repose
June 22, 2020 —
David M. McLain – Colorado Construction LitigationAs previously reported, SB 20-138, “Concerning Increased Consumer Protection for Homeowners Seeking Relief for Construction Defects,” would have extended the Colorado statute of repose applicable to construction defect claims. Senate Bill 20-138, if enacted, would have:
- Extended Colorado’s statute of repose for construction defects from 6+2 years to 10+2 years;
- Required tolling of the statute of repose until the claimant discovers not only the physical manifestation of a construction defect, but also its cause; and
- Permitted statutory and equitable tolling of the statute of repose.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Real Estate & Construction News Roundup (4/24/24) – Omni Hotels Hit with Cyberattack, Wisconsin’s Low-Interest Loans for Home Construction, and Luxury Real Estate Sales Increase
May 20, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, alternative lenders take the lead in CRE loans, construction workers worry about artificial intelligence, prospective homeowners express concerns about climate risks, and more!
- Even as overall real estate sales fell 4% nationwide in the first quarter, luxury real estate sales increased more than 2%, posting their best year-over-year gains in three years. (Robert Frank, CNBC)
- As many banks cut back from commercial real estate loans amid rising interest rates and a regional banking crisis that exploded in early 2023, a number of alternative lenders jumped in to lead the way. (Andrew Coen, Commercial Observer)
- Workers in construction and other industries are worried about artificial intelligence, and it’s keeping their companies from moving forward more decisively with the surging technology. (Matthew Thibault, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Powering Goal Congruence in Construction Through Smart Contracts
February 22, 2021 —
Michael Matthews - Construction ExecutiveThe $814 billion U.S. commercial construction market requires a unique assembly of designers, contractors, subcontractors and suppliers to work together in a highly orchestrated manner to make sure that the right labor, material, equipment, tools and information all comes together at the right place and time. Alignment and coordination between companies is critical for a project to be successful; completed safely, on time, on budget and resulting in an asset that performs as designed.
Yet the industry is slowed by an operating model bogged down by transactional and informational barriers that destroys value across the construction supply chain. Companies are connected through contracts and purchase orders that are undercut by mistrust that yields adversarial relationships and conflicting priorities that result in restricted transparency, elongated payment cycles and an abundance of resource-sucking reconciliations, audits and disputes.
With margins already razor thin, company protectionism cascades down from owners, developers and operators to contractors, subcontractors and suppliers with each player focused on optimizing their piece at the expense of the whole. Perhaps this is part of the reason 98% of megaprojects experience cost overruns or delays, 95% of projects are unable to meet even one business objective; and 70% of all construction projects are not completed within 10% of the proposed budget.
Reprinted courtesy of
Michael Matthews, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of