Appellate Attorney’s Fees and the Significant Issues Test
June 29, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe significant issues test to determine the prevailing party in construction lien actions (which, by the way, also applies to breach of contract actions) applies to appellate attorney’s fees too! Under this test, the trial court has discretion to determine which party prevailed on the significant issues of the case for purposes of attorney’s fees. The trial court also has discretion to determine that neither party was the prevailing party for purposes of attorney’s fees.
In a recent decision, Bauer v. Ready Windows Sales & Service Corp., 42 Fla. L. Weekly D1417a (Fla. 3d DCA 2017), there were competing motions for appellate attorney’s fees. Both parties believed they should be deemed the prevailing party under Florida Statute s. 713.29 (statute that authorizes prevailing party attorney’s fees under Florida’s Construction Lien Law). The appellate court held that neither party was the prevailing party under the significant issues test: “[W]e conclude that each party lost on their appeal, while each party successfully defended that part of the judgment in their favor on the other party’s cross-appeal. Because both parties prevailed on significant issues, this Court finds that appellate fees are not warranted for either party.”
Bauer, supra. Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Real Estate & Construction News Roundup (7/2/24) – Increase in Commercial Property Vacancy Rates, Trouble for the Real Estate Market and Real Estate as a Long-Term Investment
July 31, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the evolution of stadium construction, an increase in legal and legislative action affecting the multifamily sector, and growing concerns for owners of office space.
- The work-from-home trend will likely push up the commercial property vacancy rate in 2026 to a peak average of 24%, or 4 percentage points higher than the first quarter of this year. (Jim Tyson, CFO Dive)
- In recent years, stadium construction has evolved to focus more on cultivating the game day experience with some multibillion-dollar projects breaking ground, as existing venues get renovations. (Zachary Phillips, Construction Dive)
- A number of prominent issues affecting the multifamily industry, including rent control, fees and antitrust concerns, have been subject to increasing levels of legal and legislative action over the past year. (Mary Salmonsen, Multifamily Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Home Builders and Developers Beware: SC Supreme Court Beats Up Hybrid Arbitration Clauses Mercilessly
November 15, 2022 —
Matthew Devries - Best Practices Construction LawToday’s guest post is by one of my favorite construction lawyers and friends, Burr partner Ned Nicholson in our Columbia, SC office. Ned regularly represents clients in construction defect and compensation claims, manufacturer/dealer disputes, and insurance coverage lawsuits. He is also a South Carolina certified mediator. Ned can be reached at nnicholson@burr.com or (803) 799-9800.
If you are a homebuilder, residential housing developer, construction industry insurer, or any one of the many participants in the industry providing affordable and decent housing for the citizens of South Carolina, you are already aware that South Carolina courts have for decades prioritized the promotion of consumer (i.e., home buyer) rights, usually at the expense of the providers of housing. There is nothing inherently wrong with that; the goal is laudable. But as in so many things, the implementation has been extremely costly for the residential construction industry as a savvy plaintiff’s bar has taken advantage of grey areas that are inevitably created in our judicial system.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Devries, Burr & Forman LLPMr. Devries may be contacted at
mdevries@burr.com
“For What It’s Worth”
October 21, 2024 —
Daniel Lund III - LexologyThe legal doctrine of quantum meruit is essentially referring to recovering “for what it’s worth,” incorporating the Latin phrase for “as much as one has deserved.”
Quantum meruit recovery occurs when there is no contract between parties for the particular item for which recovery is sought. Hence, quantum meruit recovery is generally a means of last resort to endeavor to make oneself whole.
So, it was for a subcontractor seeking nearly $14,000,000 for work it performed on a construction project in Portsmouth, New Hampshire. The subcontractor sued on contract as well as quantum meruit/unjust enrichment. The court initially dismissed the quantum meruit/unjust enrichment claims – because there was a contract claim – whereupon the contract claim was dismissed on summary judgment: the subcontractor failed to timely submit change proposals and, consequently, “lost contract remedies available to recover amounts it sought in the change proposals.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Six Inducted into California Homebuilding Hall of Fame
February 04, 2013 —
CDJ STAFFThe California Homebuilding Foundation has inducted six industry leaders into their Homebuilding Hall of Fame, in recognition of both their professional accomplishments and their philanthropic and volunteer activities.
The six homebuilders to be honored are Sherman S. Haggerty of Lennar Corp., Joe Head of the SummerHill Land Division of SummerHill Homes, Robert B. MacLeod of Newland Real Estate Group, John J. Ryan Jr. of Brookfield Homes Bay Area, Tom Sudberry of Sudberry Properties, and Bill Watt of Baywood Development Group.
Read the court decisionRead the full story...Reprinted courtesy of
All Aboard! COVID-19 Securities Suit Sets Sail, Implicates D&O Insurance
April 27, 2020 —
Lorelie S. Masters, Michael S. Levine & Geoffrey B. Fehling - Hunton Insurance Recovery BlogIn a prior post, we predicted that novel coronavirus (COVID-19) risks could implicate D&O and similar management liability coverage arising from so-called “event-driven” litigation, a new kind of securities class action that relies on specific adverse events, rather than fraudulent financial disclosures or accounting issues, as the catalyst for targeting both companies and their directors and officers for the resulting drop in stock price. It appears that ship has sailed, so to speak, as Kevin LaCroix at D&O Diary reported over the weekend that a plaintiff shareholder had filed a securities class action lawsuit against Norwegian Cruise Line Holdings, Ltd. alleging that the company employed misleading sales tactics related to the outbreak.
The lawsuit alleges that the cruise line made false and misleading statements or failed to disclose in its securities filings sales tactics by the company that purported to provide customers with unproven or blatantly false statements about COVID-19 to entice customers to purchase cruises. Those allegations rely on two news articles reporting on the company sales practices in the wake of COVID-19: a March 11, 2020 Miami New Times article quoting leaked emails in which a cruise employee reportedly asked sales staff to lie to customers about COVID-19 to protect the company’s bookings; and a March 12, 2020 Washington Post article entitled, “Norwegian Cruise Line Managers Urged Salespeople to Spread Falsehoods about Coronavirus.” The lawsuit alleges that the company’s share price was cut nearly in half following these disclosures.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Lorelie S. Masters,
Michael S. Levine and
Geoffrey B. Fehling
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Seattle Independent Contractor Ordinance – Pitfalls for Unwary Construction Professionals
October 09, 2023 —
Travis Colburn - Ahlers Cressman & SleightChapter 14.34 of the Seattle Municipal Code is a relatively new ordinance that can affect the parties to a construction contract for work performed within the City of Seattle’s city limits. The Independent Contractor Protection Ordinance (“ICPO”) was enacted to provide self-employed persons, or entities composed of not more than one person, regardless of corporate form, recourse for timely payment for work performed. The ICPO applies to contracts of $600[i] or more between an independent contractor and a hiring entity where the work, in whole or in part, is known to be performed within the City of Seattle’s city limits.[ii] The ICPO cannot be waived by parties to a contract.[iii]
Historically, the primary legal recourse for non-payment or late payment for work performed under a contract involves an expensive breach of contract action, and one reason the ICPO was enacted was to give greater protection to a growing number of Washington independent contractors who report problems with timely and accurate payment.
The ICPO affects “hiring entities” or any individual, partnership, association, corporation, business trust, or any entity, person or group of persons, or a successor thereof, that hires independent contractors to provide services within the scope of a hiring entity’s business or commercial activities. In the construction context, most general contractors, subcontractors, design professionals, and design consultants should be aware of this ordinance, as well as certain owners[iv] and development-side entities.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com