No Signature? Potentially No Problem for Sureties Enforcing a Bond’s Forum Selection Clause
March 21, 2022 —
Brian C. Padove - ConsensusDocsOne of the foundational tenets of contract law is that a party may only be bound by terms they agree to, or in other words, if the party did not sign a contract, that party cannot be bound by the terms thereof. While this principle is generally unwavering, there are certain situations in which a non-signatory to a contract may still be bound by the terms of a contract.
In particular, this non-signatory issue may arise when a payment bond claimant makes a bond claim, subsequently files a lawsuit, but the bond contains a forum selection clause different than the venue of the lawsuit and the surety seeks to enforce the bond’s forum selection clause. For example, the claimant may have filed its lawsuit against the surety in federal court, even though the bond provides language specifically mandating that no lawsuit shall be commenced by any claimant other than in a state court where the project is located. Thus, the question then becomes, can the surety enforce the forum selection clause against the claimant when the claimant did not sign the bond and/or never agreed to the terms thereof? The short answer, it depends (yes, that is a very lawyer-like answer). Given recent case law over the past decade, however, the surety has a strong argument in favor of enforcement of the forum selection clause.
Read the court decisionRead the full story...Reprinted courtesy of
Brian C. Padove, Watt, Tieder, Hoffar & Fitzgerald, LLP (ConsensusDocs)Mr. Padove may be contacted at
bpadove@watttieder.com
OSHA Issues New Rules on Injury Record Keeping
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorOn July 28, 2015, OSHA issued proposed rules seeking to clarify an employer’s ongoing obligation to make and maintain accurate records of work-related injuries and illness. The new rules were drafted in response to the U.S. Court of Appeals decision in AKM LLC, d/b/a Volks Constructors v. Secretary of Labor, in which a contractor successfully argued that OSHA’s citation was issued well beyond the six month limitation period.
OSHA’s Injury Record Keeping Obligations
The Occupational Safety and Health Act requires each employer to make, keep and preserve records of workplace injuries and illnesses. 29 U.S.C. § 658(c). OSHA has promulgated a set of regulations which require employers to record information about work-related injuries and illnesses in three ways. Employers must prepare an incident report and a separate injury log “within seven (7) calendar days of receiving information that a recordable injury or illness has occurred,” 29 C.F.R. § 1904.29(b)(3), and must also prepare a year-end summary report of all recordable injuries during the calendar year, id. § 1904.32(a)(2). An employer “must save” all of these documents for five years from the end of the calendar year those records cover. 29 C.F.R. § 1904.33(a).
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Oregon Duty to Defend Triggered by Potential Timing of Damage
June 28, 2013 —
CDJ STAFFThe Oregon Supreme Court has concluded that if it is possible that damage could have occurred prior to the completion of the project, then the policies in effect at that time are triggered. John Green of Farella Braun + Martel LLP writes that “we have long argued that, since the duty to defend exists if there is any ‘potential’ of covered liability, there is a potential that damage happened before that project was completed, or at any time after completion, triggering all policies in that time frame.” The Oregon court concluded that if property damage could have happened during construction, the insuerer had a duty to defend and “the insured had no burden to establish any additional facts to support that potential.”
Read the court decisionRead the full story...Reprinted courtesy of
Plehat Brings Natural Environments into Design Tools
May 01, 2019 —
Aarni Heiskanen - AEC BusinessNatural elements are an essential part of the built environment. However, BIM tools offer almost no support to landscape architecture. Plehat is introducing a new solution that helps architects and decision-makers to understand the dynamics of nature and make smart design choices.
Plehat used photogrammetric 3D models of Uunisaari islands, to the south of Helsinki. The experimenters modeled the buildings and the plants on the island and used game engine software to create a virtual reality (VR) experience. They called the app the “Landscape Time Machine”. The technology solution they developed paved the way for new software that the company will launch later this year.
In 2018, Plehat, a landscape design startup, received funding from the Finnish national KIRA-digi digitalization project to carry out a test. The experimentation demonstrated how seasonal changes and weather conditions affect plants, and how the environment can be visualized and analyzed virtually.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
So You Want to Arbitrate? Better Make Sure Your Contract Covers All Bases
August 16, 2021 —
Stephanie Nolan Deviney - ConsensusDocsAs a General Contractor, you may prefer to arbitrate any contractual disputes rather than engage in protracted litigation. Many Courts favor arbitration clauses and will enforce them if there is a sufficient reason to do so. However, there are several issues that a General Contractor should consider when including an arbitration clause in its construction agreement with its client. When an arbitration clause is not properly crafted, questions can arise as to who must arbitrate? Who decides whether to arbitrate? Who selects the arbitrator? What will the subject matter of the arbitration be? A look at a recent case in Pennsylvania highlights the need for properly crafted arbitration clauses.
A Recent Case Highlights The Importance Of Arbitration Clauses
In TEC Construction, LLC v. Greg Rich and Lora Rich filed in the Court of Common Pleas, Allegheny County, Pennsylvania, TEC Construction, LLC (“TEC”) and Greg and Lora Rich (the “Riches”), entered into a Construction Agreement with an arbitration clause. Specifically, the parties to the Construction Agreement, TEC and the Riches, agreed to arbitrate any disputes with the American Arbitration Association. Five subcontractors completed the work under the Construction Agreement but none of the subcontractors agreed to arbitrate.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Nolan Deviney, Fox Rothschild LLP (ConsensusDocs)Ms. Deviney may be contacted at
sdeviney@foxrothschild.com
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Scotiabank Is Cautious on Canada Housing as RBC, BMO Seek Action
April 12, 2021 —
Shelly Hagan & Erik Hertzberg - BloombergBank of Nova Scotia, Canada’s third-largest lender, waded into the burgeoning debate over whether Justin Trudeau’s government should take immediate steps to cool the nation’s hot housing market, issuing a report that cautioned against rushing to implement new constraints.
In a report released Sunday, Scotiabank’s chief economist Jean-Francois Perrault said the recent run-up in home prices nationally over the past year was in large part driven by sluggish supply that failed to keep up with higher demand -- a trend that could reverse itself as new sellers enter the market in coming weeks. If the government does decide to take action, it should target housing speculators, he said.
Reprinted courtesy of
Shelly Hagan, Bloomberg and
Erik Hertzberg, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Massive Redesign Turns Newark Airport Terminal Into a Foodie Theme Park
March 05, 2015 —
Belinda Lanks – BloombergYou wait on what looks like a Soviet bread line. You show your I.D. to a guard. You take off your shoes, empty your pockets, and surrender to a digital scanner.
Fortunately, there’s always a bevy of gleaming cocktail bars and foodie outposts welcoming you to the other side.
No? Get ready. That’s the plan for United Airlines’ Terminal C at Newark Liberty International Airport—a $120 million redesign that includes 55 dining venues with enough celebrity-chef cameos to rival the glitziest of Las Vegas casinos. Instead of the usual McDonald’s, TCBY, and Sbarro, there will be restaurants serving up far-ranging cuisine, from authentic ramen and tacos to gourmet, Neapolitan-style pizza and Swedish meatballs. Since the terminal must remain in operation, all the structures will be assembled off-site and dropped in next year to keep construction time to a minimum.
Read the court decisionRead the full story...Reprinted courtesy of
Belinda Lanks, Bloomberg