Up in Smoke - 5th Circuit Finds No Coverage for Hydrochloric Acid Spill Based on Pollution Exclusion
October 19, 2020 —
Kerianne E. Kane & David G. Jordan - Saxe Doernberger & VitaThe Fifth Circuit Court of Appeals recently held that an insurer was not obligated to pay damages associated with a hydrochloric acid spill based on a pollution exclusion in the policy.
In Burroughs Diesel, Inc. v. Travelers Indemnity Co. of America,1 a trucking company sued its property insurer, Travelers Indemnity Company of America (“Travelers”) when it refused to pay a claim for a storage tank leak which resulted in over 5,000 gallons of hydrochloric acid entering the property and causing significant damage to buildings, vehicles, tools, and equipment. The acid was initially dispensed in liquid form, but quickly became a cloud that engulfed the property. Travelers denied coverage for the claim based on the pollution exclusion because “acids” fell within the policy’s definition of “pollutants.”
The trucking company sued Travelers in the United States District Court for the Southern District of Mississippi, alleging breach of contract and breach of good faith and fair dealing for refusing to pay the claim. The trucking company argued that coverage was warranted because there is an exception to the pollution exclusion if “the discharge, dispersal, seepage, migration, release or escape is itself caused by any of the ‘specified causes of loss,’” and the hydrochloric acid cloud was a form of “smoke,” which is a specified cause of loss covered by the policy. The District Court entered summary judgment in favor of Travelers, finding that the trucking company failed to demonstrate that an exception to the pollution exclusion applied. The trucking company appealed to the Fifth Circuit Court of Appeals.
Reprinted courtesy of
Kerianne E. Kane, Saxe Doernberger & Vita and
David G. Jordan, Saxe Doernberger & Vita
Ms. Kane may be contacted at kek@sdvlaw.com
Mr. Jordan may be contacted at dgj@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Affirms Dismissal Secured by Lewis Brisbois in Coverage Dispute Involving San Francisco 49ers’ Levi Stadium
May 31, 2021 —
Kristen Perkins & Jordon Harriman - Lewis Brisbois NewsroomFort Lauderdale Partner and Vice Chair of Lewis Brisbois’ Insurance Coverage & Bad Faith Litigation Practices Kristen D. Perkins and Los Angeles Partner Jordon E. Harriman had their district court victory confirmed by the U.S. Court of Appeals for the Ninth Circuit when it affirmed the lower court’s ruling that Lewis Brisbois’ client, an excess insurer, had no duty to defend or indemnify a construction joint venture in a lawsuit filed by San Francisco 49ers fans.
Underlying Case and Lewis Brisbois’ Successful Motion to Dismiss
In the underlying matter, 49ers fans filed a proposed class action against the team, alleging that the team’s home venue, Levi Stadium, violated the Americans with Disabilities Act and the state's Unruh Civil Rights Act because it contained physical barriers that hindered access for disabled people. The 49ers subsequently filed a third-party complaint against the construction joint venture that built the stadium, contending that the joint venture’s negligence caused the inaccessibility, and that if the team was held liable for the fans' claims, the joint venture should be obligated to indemnify the team under the terms of the stadium contract.
Reprinted courtesy of
Kristen Perkins, Lewis Brisbois and
Jordon Harriman, Lewis Brisbois
Ms. Perkins may be contacted at Kristen.Perkins@lewisbrisbois.com
Mr. Harriman may be contacted at Jordon.Harriman@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Herman Russell's Big Hustle
May 20, 2024 —
Maggie Murphy - Construction Executive“Any person that I knew of in the city of Atlanta who did anything ran it by Herman before they did anything else.”
These are the words of Anthony Dixon, senior project manager and 47-year veteran employee with H. J. Russell & Company. But ask anyone who knows anything about H. J. Russell, and they’ll say the same thing: The story of the company is the story of Herman J. Russell himself.
From humble beginnings in Atlanta’s Summerhill neighborhood came a young man with an unbreakable entrepreneurial spirit, who used that drive to forge an unlikely path to success in the Jim Crow–era South. What began as a plastering company in 1952 is today one of the largest Black-owned contractors in the United States, with Herman’s children—Donata Russell Ross, H. Jerome Russell and Michael B. Russell Sr.—at the helm (a natural fit for the family-focused firm).
Over its 72-year history, H. J. Russell has grown exponentially, contracted when necessary and persevered through segregation, the turbulence of the Civil Rights Movement and multiple economic downturns. Now, in the next five years, they’re poised to become a billion-dollar company.
But long before any of that, there was just a boy and a dream.
Reprinted courtesy of
Maggie Murphy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Effective July 1, 2022, Contractors Will be Liable for their Subcontractor’s Failure to Pay its Employees’ Wages and Benefits
July 25, 2022 —
Edward O. Pacer & David J. Scriven-Young - Peckar & AbramsonOn June 10, 2022, Illinois Governor J.B. Pritzker signed two House Bills that amend the Illinois Wage Payment & Collections Act, 820 ILCS 115 et. seq. (“Wage Act”), to provide greater protection for individuals working in the construction trades against wage theft in a defined class of projects. Pursuant to this new law, every general contractor, construction manager, or “primary contractor,” working on the projects included in the Bill’s purview will be liable for wages that have not been paid by a subcontractor or lower-tier subcontractor on any contract entered into after July 1, 2022, together with unpaid fringe benefits plus to attorneys’ fees and costs that are incurred by the employee in bringing an action under the Wage Act.
These amendments to the Wage Act apply to a primary contractor engaged in “erection, construction, alteration, or repair of a building structure, or other private work.” However, there are important limitations to the amendment’s applicability. The amendment does not apply to projects under contract with state or local government, or to general contractors that are parties to a collective bargaining agreement on a project where the work is being performed. Additionally, the amendment does not apply to primary contractors who are doing work with a value of less than $20,000, or work that involves only the altering or repairing of an existing single-family dwelling or single residential unit in a multi-unit building.
Reprinted courtesy of
Edward O. Pacer, Peckar & Abramson and
David J. Scriven-Young, Peckar & Abramson
Mr. Pacer may be contacted at epacer@pecklaw.com
Mr. Scriven-Young may be contacted at dscriven-young@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Micropiles for bad soil: a Tarheel victory
March 14, 2011 —
Melissa BrumbackDespite foundation challenges, construction is almost complete on the expansion at University of North Carolina’s Kenan stadium. The project started with a deep foundation system from design-build contractor GeoStructures. Known as the Carolina Student-Athlete Center for Excellence, the addition was built on a parcel with a knotty mix of fill soils, subsurface boulders and varying depths to rock. To achieve uniform foundation support, GeoStructures designed a Micropile system (also known as a Mini pile system) which could be drilled into the variable ground conditions.
Read the full story...
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl law.com.
Read the court decisionRead the full story...Reprinted courtesy of
“Time Is Money!” In Construction and This Is Why There Is a Liquidated Damages Provision
February 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn construction, the adage “Time is Money!” rings true for all parties involved on a project. This includes an owner of a project that wants a project completed on time, i.e., by a substantial completion date. While substantial completion is often defined as when an owner can use a project for its intended purpose, this intended purpose typically equates to beneficial occupancy (in new construction) and other factors as identified in the contract.
The best mechanism for an owner to reinforce time and the substantial completion date is through a liquidated damages provision (also known as an LD provision) that includes a daily monetary rate for each day of delay to the substantial completion date.
A liquidated damages provision is not designed, and should NEVER be designed, to serve as a penalty because then it would be unenforceable. Instead, it should be designed to reasonably compensate an owner for delay to the substantial completion date that cannot be ascertained with any reasonable degree of certainty at the time the contract is being negotiated and executed. (Liquidated damages are MUCH easier to prove than actual damages an owner may incur down the road.) As an owner, you don’t really want to assess liquidated damages because that means the project is not substantially completed on time. And, in reality, a timely completed and performing project should always be better and more profitable than a late and underperforming project. However, without the liquidated damages provision, there isn’t a great way to hold a contractor’s feet to the fire with respect to the substantial completion date.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Exponential Acceleration—Interview with Anders Hvid
December 01, 2017 —
Aarni Heiskanen - AEC BusinessAnders Hvid is a Danish consultant, speaker, and author. He talks about digital disruption, exponential acceleration, and paradigm shifts that are taking place in a world that is moving from local and linear into global and exponential.
“I have a background in social studies. My interest is in humans, and systems in which they work together. I’ve always had a deep fascination with technology and how it influences our society, our jobs, our democracies, and systems,” Anders says. He visited Singularity University back in 2010, and that experience made a lasting impression on him. “It freaked me out, to be honest, and it opened my eyes to how important technology is.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
New 2021 ALTA/NSPS Land Title Survey Standards Effective February 23, 2021
March 01, 2021 —
Emily K. Bias & Josh D. Morton - Gravel2Gavel Construction & Real Estate BlogThe “Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys” is a document jointly promulgated by the American Land Title Association (ALTA), representing the title insurance industry, and the National Society of Professional Surveyors (NSPS), representing professional land surveyors, which describes the uniform minimum standards with which surveyors must comply when preparing a survey to be used by a title insurance company for the purpose of deleting the general survey exception from ALTA title policy forms. The first such set of standards was developed in 1962 and has since been revised 10 times. The standards are currently updated every five years and are relied on by real estate professionals, including purchasers, lenders, title insurers and their attorneys, nationwide. In October 2020, a joint committee comprising representatives of both ALTA and NSPS adopted the “2021 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys,” which will become effective on February 23, 2021. The significant changes between the 2021 standards and the previous 2016 standards are summarized below.
Survey Matters
The 2021 standards clarify that only survey-related matters must be summarized on the survey. This revision was intended to foreclose a practice common among some institutional lenders to require that the survey list all items shown in Schedule BII of the title commitment on the face of the survey regardless of whether those items may in fact be survey related. The 2021 standards also add a requirement that the surveyor include a note specifying whether the location of a right of way, easement or other survey-related matter is shown on the survey. This change incorporates common lender and purchaser requirements that were not previously enumerated in the survey standards.
Reprinted courtesy of
Emily K. Bias, Pillsbury and
Josh D. Morton, Pillsbury
Ms. Bias may be contacted at emily.bias@pillsburylaw.com
Mr. Morton may be contacted at josh.morton@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of