Professional Services Exclusion Bars Coverage Where Ordinary Negligence is Inseparably Intertwined With Professional Service
August 17, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Energy Ins. Mutual Ltd. v. Ace American Ins. Co. (No. A140656, filed 7/11/17, ord. Pub. 8/10/17), a California appeals court found that a professional services exclusion barred coverage for wrongful death and other claims blamed on pipeline inspectors’ failure to identify and properly mark a gas pipeline that was ruptured during construction of another pipeline, resulting in an explosion and fire.
In Energy Ins. Mutual, a pipeline owner hired two temporary construction inspectors through a staffing company. The inspectors had to ensure compliance with engineering and safety standards, practices and procedures for pipeline construction, and understand construction drawings and blueprints. They worked together with one of the owner’s employees to perform daily surveillance to ensure the integrity of the pipeline and avoid third party damage.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?
March 11, 2024 —
Christopher G. Hill - Construction Law MusingsRemember BAE Systems and Fluor? This post is the third here at Construction Law Musings relating to this case which is a seemingly never-ending source for content. In the prior post discussing this case, the Court found that Va. Code 1-4.1:1 which bars waiver of a right to payment before work is performed did not apply because Fluor had provided work before execution of the contract or any change orders.
In the most recent opinion in this long-running litigation, and after a motion to reconsider by Fluor that was granted, the Court re-examined this finding along with the contractual language found in the Limitation of Damages (LOD) clause and came to the opposite conclusion regarding certain change orders that remained unpaid by BAE.
The Court first looked to the language of the contract itself and specifically the language in the LOD provision that states “Except as otherwise provided in this Subcontract.” The Court then looked at the change order provision and its typical equitable adjustment language and the mandatory nature of the equitable adjustment language. The Court found that the LOD provisions did not apply to change orders both because price increases due to change orders are not “damages” and because of the exception language in the LOD provision itself.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Consumer Protection Act Whacks Seattle Roofing Contractor
July 21, 2011 —
Douglas Reiser, Builders Council BlogIt’s been over 1 year since we last visited the CertainTeed Corp. v. Seattle Roof Brokers lawsuit. After my original post, the contractor, James Garcia, appeared at Builders Counsel in a comment to defend himself. It appears that 1 year later, the court decided to side with CertainTeed and award them significant attorneys’ fees. Ready for the whole story? Its a pricey one.
Back in July 2010, good friend Mike Atkins (Seattle Trademark Attorney) authored a post about a Seattle roofing contractor who had been sued for false advertising on his website. The lawsuit was raised by CertainTeed, a roofing material producer, whose products were the target of a Seattle contractor’s ire. Seattle Roof Brokers, owned by James Garcia, published content on its website, remarking that CertainTeed products have a history of “premature failure” and that they “will fail?.resale inspection after 15-20 years.”
CertainTeed filed its action to obtain an injunction and damages under the Consumer Protection Act.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Nashville Stadium Bond Deal Tests Future of Spectator Sports
December 14, 2020 —
Amanda Albright & Danielle Moran - BloombergAmerica’s country-music capital is making a bet on the world’s most popular sport.
A Nashville, Tennessee agency is selling $225 million of bonds to finance the construction of a 30,000-seat Major League Soccer stadium in Music City, anticipating it could be a boon once spectator sports emerge from the pandemic. Local officials have faith that it will: the Metropolitan Government of Nashville and Davidson County agreed to step in if revenue from the stadium isn’t enough to cover the debt payments, insulating bondholders from risk.
Reprinted courtesy of
Amanda Albright, Bloomberg and
Danielle Moran, Bloomberg
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Megaproject Savings Opportunities
April 15, 2014 —
Beverley BevenFlorez-CDJ STAFFJoel Levy in Construction Digital interviewed Christopher Dann, a Partner of Booz & Company’s Energy, Chemicals and Utilities practice, regarding how to be more efficient and save money when managing billion dollar construction megaprojects. According to Construction Digital, “Booz & Company, (recently rebranded as Strategy&), is celebrating its 100th anniversary this year, and over a century of working with huge clients in several sectors, has gathered the knowledge to identify what it terms a $40 trillion opportunity for savings in construction megaprojects over the next 20 years as clients combat a 30 percent average figure of overrun in schedule and cost.”
Dann cited several reasons for inefficiencies in megaprojects, including “inefficient advance planning and analysis” and “lack of completion of detail design engineering prior to the start of construction,” reported Construction Digital. The inefficiencies can be countered, according to Dann, “when following a clear strategy.”
Read the court decisionRead the full story...Reprinted courtesy of
Actual Cost Value Includes Depreciation of Repair Labor Costs
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss after determining that benefits paid for actual cost value (ACV) did not include repair or replacement labor costs. Shahan v. Allstate Vehicle & Prop. Ins. Co., 2022 U.S. Dist. LEXIS 135488 (W.D. La. July 29, 2022).
Hurricane Laura damaged the insured's home. She filed a claim with Allstate under her homeowners policy. Allstate issued payment. The insured filed suit alleging Allstate wrongfully withheld amounts by depreciating labor when calculating the ACV of the damaged property. Allstate moved to dismiss.
The policy was a replacement cost policy where the insured would receive the actual cash value of her insured property when it was damaged or destroyed by a covered peril. ACV was calculated by taking the repair/replacment which included both material and labor, and then deducting for depreciation. If no repairs or replacements were made, the insured was paid the ACV. If repairs or replacement was done, Allstate reimbursed the insured for the depreciation deduction. The insured challenged Allstate's refusal to pay 100% of the future labor costs, without any depreciation, even if the insured did not replace or repair the damaged property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses
October 24, 2022 —
Amanda L. Marutzky - ConsensusDocsSince October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.
The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.
Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda L. Marutzky, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Ms. Marutzky may be contacted at