“Professional Best Efforts” part 2– Reservation of Rights for Engineers who agree to “best” efforts? (law note)
April 20, 2017 —
Melissa Dewey Brumback - Construction Law in North CarolinaRecently, a reader reached out to me to ask about case examples of an engineer losing his insurance coverage because he agreed to a “heightened” or “best” standard of care. The reader stated that he was an insurance adviser who handled various construction professional coverages, and that in his experience it was very unusual to deny or limit damages because of a heightened standard of care.
This comment led me to an informal survey of several insurance brokers that I deal with, and the general consensus is that instead of outright denying a claim, most E&O insurers will issue a “reservation of rights” letter. What that means is that the insurance company will defend the claim (i.e., pay for your lawyer to defend you and your Firm), but with the understanding that they are (potentially) denying any liability for any adverse money judgment against you.
Inevitably, most such cases settle, but if they do not, the question then is whether the heightened duty created part of the damages. The insurer may ask to intervene in the lawsuit to ask the jury that question, in an effort to limit its share of the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
NIST Florida Condo Collapse Probe Develops Dozens of Hypotheses
June 13, 2022 —
James Leggate - Engineering News-RecordFederal investigators looking into the causes of the partial collapse of the 40-year-old Champlain Towers South residential condominium in Surfside, Fla., last year have developed about two-dozen hypotheses, and are working to prove or disprove each, using a growing collection of evidence. They aim to issue recommendations for changes to building codes and standards, in an effort to avoid a similar tragedy, by the end of 2024.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “A Less Than Valiant Effort”
June 21, 2024 —
Daniel Lund III - LexologyA Miller Act claimant in federal court in New Jersey in relation to a VA medical center project found itself on the wrong end of the law and was sent packing by the court.
The claimant had supplied products for the project to general contractor Valiant Group, LLC, pursuant to a purchase order from the GC. The general contractor allegedly refused to pay the supplier, leading to the claim against the GC and its payment bond surety in the amount of $126,900. The supplier also sought recovery under the federal Prompt Payment Act, 31 U.S.C. §§ 3901-07. State law claims were asserted as well.
Chipping away at the federal law claims – the claims forming the asserted basis for federal court jurisdiction for the case – the court first dispensed with the Prompt Payment Act claim. According to the court, allegations that the general contractor had “wrongfully and improperly withheld remuneration… despite [having] ‘received payment from the U.S. Department of Veterans Affairs’" – whether or not accurate – did not trigger the Act. The court wrote:
“The Prompt Payment Act was enacted ‘to provide the federal government with an incentive to pay government contractors on time by requiring agencies to pay penalties . . . on certain overdue bills . . . [and] was later amended to include provisions applicable to subcontractors.’… Absent from the Act, however, are ‘any explicit provisions for subcontractor enforcement if the prime contractor fails to make timely payment.’… This is because the Act ‘merely requires that the prime contractor's contract with the subcontractor include the specified payment clause. [It] does not require the prime contractor to actually make payments to the subcontractor[.]’… The Act, therefore, does not ‘give subcontractors an additional cause of action for an alleged breach by a general contractor of a subcontract.’”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Use Your Instincts when Negotiating a Construction Contract
August 07, 2018 —
Christopher G. Hill - Construction Law MusingsI have often discussed the more “mechanical” aspects of contract negotiation and drafting here at Construction Law Musings. However, there is another, less objective (possibly) and more “feel” oriented aspect to construction contracting that can have as big an impact on your construction project. What am I talking about? Your instinct as a construction professional when looking the other party in the eye and getting a feel for the company or individual with whom you are contracting.
Why is this so important? Firstly, and this is a truism, no matter how well drafted your construction contract is (and it should be well drafted and reviewed by an experienced construction attorney), if the other party wishes to “play games” and not honor the terms of that contract, you could still very well end up in litigation with the attendant frustration and expense. Having a great looking, well thought out and at least reasonably “fair” construction contract may make the litigation process somewhat less painful but it does not completely avoid the risk of litigation. If the other party or parties to the contract decide not to pay you or perform as they promised, you are left to enforce whatever contract you have in place.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
General Indemnity Agreement Can Come Back to Bite You
October 21, 2019 —
Christopher G. Hill - Construction Law MusingsI talk about payment bonds often here at Construction Law Musings. I talk a bit less about performance bonds and even less about the General Indemnity Agreements (GIA) that are signed by companies and their principals as part of the agreement between a construction company and its bonding company for the provision of these bonds. However, this does not mean that these GIA’s are not important. In fact, these are the agreements that allow a bonding provider to recoup any money paid out pursuant to either a payment or performance bond.
A 2018 case illustrates their importance. In Allegheny Cas. Co. v. River City Roofing, LLC, the Court considered a claim by Allegheny seeking both specific performance of the collateral agreement and reimbursement of certain expenses and investigative costs expended by Allegheny pursuant to its performance bond. Allegheny sought to be reimbursed for certain payments for siding work, investigative costs, and costs spent enforcing the GIA. Allegheny further sought to force the defendants to post sufficient collateral. To do so, Allegheny sued in the Eastern District of Virginia and then moved for summary judgment stating that the GAI uneuivocally required such a result due to the good faith payment for the siding work and the plain language of the GIA.
In response, the Defendants, River City Roofing and its principals that had personally guaranteed the indemnity, argued that the GIA did not apply to the siding work because only the roofing contract was subject to the performance bond and that any bond claims for which collateral was demanded were inchoate and therefore not proper for specific performance.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Owners Should Serve Request for Sworn Statement of Account on Lienor
August 10, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhen an owner receives a construction lien, an owner should serve the lienor with a Request for Sworn Statement of Account. The Request for Sworn Statement is authorized by Florida Statute s. 713.16(2) and should be in the following form:
REQUEST FOR SWORN STATEMENT OF ACCOUNT
WARNING: YOUR FAILURE TO FURNISH THE REQUESTED STATEMENT, SIGNED UNDER OATH, WITHIN 30 DAYS OR THE FURNISHING OF A FALSE STATEMENT WILL RESULT IN THE LOSS OF YOUR LIEN.
To: (Lienor’s name and address)
The undersigned hereby demands a written statement under oath of his or her account showing the nature of the labor or services performed and to be performed, if any, the materials furnished, the materials to be furnished, if known, the amount paid on account to date, the amount due, and the amount to become due, if known, as of the date of the statement for the improvement of real property identified as (property description) .
(name of contractor)
(name of the lienor’s customer, as set forth in the lienor’s Notice to Owner, if such notice has been served)
(signature and address of owner)
(date of request for sworn statement of account)
From both an owner and lienor’s perspective, the bolded, capitalized language is key. It states that if the lienor fails to respond under oath within 30 days, it will LOSE its lien. That is a very punitive measure for a lienor’s failure to respond, meaning a lienor should absolutely respond, no questions asked. Plus, a lienor’s response to a Request for Sworn Statement of Account is not a burdensome ordeal.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
New OSHA Fall Rules to Start Early in Minnesota
June 14, 2011 —
CDJ STAFFMinnesota has elected to implement the new OSHA rules concerning fall prevention in residential construction on June 20, well before OSHA’s September 15 deadline. Brian Johnson, reporting in Finance and Commerce, quotes Pam Perri, the executive vice president of the Builders Association of Minnesota, “this is the worst time to implement a new rule.” Ms. Perri notes “In Minnesota, education time for the residential construction industry is between November and March 1, not in the middle of the construction season.”
Mike Swanson of Rottlund Homes estimated that the new regulations would add between $200 to $500 to the cost of a house and that he felt the current safety regulations were adequate. OSHA officials are quoted that there continues “to be a high number of fall-related deaths in construction.”
Read the fully story…
Read the court decisionRead the full story...Reprinted courtesy of
Reduce Suicide Risk Among Employees in Remote Work Areas
November 24, 2019 —
Sandra Moran - Construction ExecutiveIn the construction industry, a disturbing and unnerving trend has been developing over the past few decades. Construction and resource extraction have the highest rate of deaths by suicide compared to any other industry. This phenomenon is not limited to a single country. The statistics from three developed countries with strong construction and resource extraction industries (United States, United Kingdom and Australia), reflect the same pattern.
A major risk factor that has not been given much attention and scrutiny is the requirement for many workers to be away from their homes for long periods of time, based in remote locations and basecamps. This isolation contributes to loneliness and disconnectedness that increases the vulnerability to employees at risk due to underlying mental health disorders, such as depression and anxiety, or those with suicidal ideations or prior attempts. Basecamps or remote work locations remove workers from the support networks of family, friends, and even medical and psychological caregivers.
Employers placing employees in remote work locations should be mindful that simply wanting to work in a remote location does not necessarily equate to being able to cope well in such an environment—unless appropriate supports are provided. Companies need to become proactive to lead employees to become true teams to help reduce the risk of suicide among their workers.