Approaches in the Absence of a Differing Site Conditions Clause
April 10, 2019 —
Parker A. Lewton - Smith CurrieA contractor who has encountered unforeseen conditions will typically rely on the contract’s differing site conditions clause as a means to recovery. Most construction contracts address those issues directly. In ConsensusDocs Standard Agreement and General Conditions between Owner and Constructor, the starting point is § 3.16.2. But what if the contract does not contain a differing site conditions clause? Or, what if the contract does contain such a clause, but the contractor failed to provide adequate notice or satisfy other conditions or requirements of the contract? When reliance on a differing site conditions clause is impractical, a contractor still may seek recovery in certain instances under one or more of the following legal theories: misrepresentation; fraud; duty to disclose; breach of implied warranty; and mutual mistake.
Misrepresentation
Misrepresentation occurs when an owner “misleads a contractor by a negligently untrue representation of fact[.]” John Massman Contracting Co. v. United States, 23 Cl. Ct. 24, 31 (1991) (citing Morrison–Knudsen Co. v. United States, 170 Ct. Cl. 712, 718–19, 345 F.2d 535, 539 (1965)). A contractor may be able to recover extra costs incurred, under a theory of misrepresentation, if it can show that (1) the owner made an erroneous representation, (2) the erroneous representation went to a material fact, (3) the contractor honestly and reasonably relied on that representation, and (4) the contractor’s reliance on the erroneous representation was to the contractor’s detriment. See T. Brown Constructors, Inc. v. Pena, 132 F.3d 724, 728–29 (Fed. Cir. 1997). These four requirements can be satisfied, for example, through the use of deposition testimony detailing the owner’s representations and the contractor’s reliance thereon. See, e.g., C & H Commercial Contractors, Inc. v. United States, 35 Fed. Cl. 246, 256–57 (1996).
Read the court decisionRead the full story...Reprinted courtesy of
Parker A. Lewton, Smith CurrieMr. Parker may be contacted at
palewton@smithcurrie.com
Another Defect Found on the Bay Bridge: Water Leakage
February 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the San Francisco Chronicle, the eastern span of the Bay Bridge has dealt with alleged “defective welds” and “cracked steel rods,” and now there are reports of leakage. The Chronicle stated that rainwater “is dripping into the steel structure beneath the road deck on the suspension stretch of the span, which,” according to Caltrans “is supposed to be watertight.”
Water corrosion on a bridge could cost $6.4 billion, the San Francisco Chronicle claimed. Caltrans said that they “are going to have teams of engineers and inspectors there this weekend to assess the problem.”
Read the court decisionRead the full story...Reprinted courtesy of
ASHRAE Approves Groundbreaking Standard to Reduce the Risk of Disease Transmission in Indoor Spaces
July 10, 2023 —
ASHRAEATLANTA, June 27, 2023 (GLOBE NEWSWIRE) -- ASHRAE announced the approval for publication of its highly anticipated standard to reduce the risk of airborne infectious aerosol transmission in buildings, bringing numerous benefits to occupants and promoting healthier environments.
ASHRAE Standard 241, Control of Infectious Aerosols establishes minimum requirements to reduce the risk of disease transmission by exposure to infectious aerosols in new buildings, existing buildings, and major renovations. Infectious aerosols are tiny, exhaled particles that can carry pathogens that cause infections or disease. These particles are so small that they can remain in the air for long periods of time. Use of this standard could reduce exposure to the SARS-COVID-2 virus, which causes COVID-19, the flu virus and other pathogens. Standard 241 provides requirements for many aspects of air system design, installation, operation, and maintenance.
Standard 241 available now for
presale in the ASHRAE Bookstore.
About ASHRAE
Founded in 1894, ASHRAE is a global professional society committed to serve humanity by advancing the arts and sciences of heating ventilation, air conditioning, refrigeration, and their allied fields.
For more information and to stay up-to-date on ASHRAE, visit ashrae.org and connect on
Instagram,
LinkedIn,
Facebook,
Twitter and
YouTube.
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Tornadoes, Hail Cost Insurers $1 Billion in June
July 09, 2014 —
Kelly Gilblom – BloombergTornadoes, hail and windstorms that pounded the U.S. from the Rocky Mountains to the Tennessee Valley last month will probably cost insurers more than $1 billion, Aon Plc said in a report.
Hailstorms and winds greater than 90 miles an hour (145 kilometers) in June caused billions of dollars of economic losses, led by a full week of storms early in the month, the London-based insurance broker said today.
More than 300 tornadoes hit the U.S. last month, compared with 125 a year earlier and 111 in June 2012, according to preliminary data from the National Weather Service’s Storm Prediction Center. May, June and July tend to be the worst months for twisters, it said.
Severe weather from June 3 to June 9 this year killed three people and led to more than 100,000 claims, Aon said. Later in the month, “hail and winds gusting to hurricane strength tracked eastward,” the broker said in its report. The storm “shattered windows, punctured roofs and downed trees onto homes, structures and vehicles.”
Read the court decisionRead the full story...Reprinted courtesy of
Kelly Gilblom, BloombergMs. Gilblom may be contacted at
kgilblom@bloomberg.net
Blurred Lines: New York Supreme Court Clarifies Scope of Privileged Documents in Connection with Pre-Denial Communications Prepared by Insurer's Coverage Counsel
September 17, 2015 —
Greg Steinberg – White and Williams LLPIn a recent decision, the New York Supreme Court clarified the scope of privileged documents with respect to communications prepared by an insurer’s counsel prior to issuing a denial of coverage letter. The coverage litigation at issue arose out of MF Global Inc.’s claims under fidelity bonds for losses incurred as a result of large trades made by former MF Global employee, Evan Dooley. The trades cost MF Global, Dooley’s former clearing firm, $141 million after it had to reimburse the CME Group, Inc. futures clearinghouse that handled the trade. The insurers that issued the fidelity bonds contested coverage and sued MF Global in 2009.
The opinion underscores the fact that there is no “bright line” rule in New York with respect to disclosure of communications in the insurance context prior to the issuance of a coverage determination – the disclosure requirement will instead turn on what’s actually privileged. In addition, while retention of counsel may not serve as an automatic shield for all documents prepared prior to the coverage decision, insurers will not be required to disclose, among other things, communications which include an “indicia of the provision of legal services.”
Read the court decisionRead the full story...Reprinted courtesy of
Greg Steinberg, White and Williams LLPMr. Steinberg may be contacted at
steinbergg@whiteandwilliams.com
LEEDigation: A Different Take
June 22, 2020 —
Christopher G. Hill - Construction Law MusingsThis weeks Guest Post Friday at Musings is a real treat. Sara Sweeney is a registered architect, LEED AP and GreenFaith Fellow in religious environmental leadership. Her 18-year architectural career reflects her passion and commitment to sustainable building design and stewardship of our natural environment. She is the founder of EcoVision LLC, a solutions-based research and consulting firm, grounded in sustainable design practices, environmental stewardship, and building science.
Dude
Every so often I come across a word that drives me nuts. A few years ago it was ‘Dude.’ Lately, it is ‘LEEDigation.’ It’s a new term to “describe green building litigation” coined by Chris Cheatham, a fine person and very knowledgeable attorney in construction law and a LEED AP as well. Per his definition, LEEDigation “could involve disputes arising from green building certification, could arise if a project fails to obtain government incentives or satisfy mandates for green building construction, or could simply result from improperly designed or constructed green building strategies. It all makes sense. So why does it drive me nuts?
Round Peg. Square Hole.
Although I fully understand why the term was coined, such a term keeps us in flat world, that is, the world of conventional design and construction. Designing and building to LEED standards, or rather, just designing and building sustainably in general, whether to meet a third party standard or not, is a different way than what we have been used to. Period. Whereas our conventional way is focused on first costs, and sees the building more as a commodity than the human imprint and legacy on Earth, sustainable design and building is a process which, at its best, considers the economic impacts of NOT building responsibly. It is a more holistic way of building and balances long-term costs and implications with short term costs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Late Filing Contractor Barred from Involving Subcontractors in Construction Defect Claim
March 01, 2012 —
CDJ STAFFThe Colorado Court of Appeals looked at that state’s Construction Defect Action Reform Act in determining if a general contractor could add subcontractors as third-party defendants to a construction defect lawsuit. Shaw Construction, LLC was the general contraction of the Roslyn Court condominium complex, and was sued by the homeowners’ association in a construction defect case. United Builder Services was the drywall subcontractor on the project. MB Roofing had installed roofs, gutters, and downspouts. The certificate of occupancy for the last building was issued on March 10, 2004. The project architect certified completion of all known remaining architectural items in June, 2004.
The HOA filed a claim against the developers of the property on January, 21, 2009. A week later, the HOA amended its complaint to add Shaw, the general contractor. Shaw did not file its answer and third-party complaint until March 29, 2010, sending its notice of claim under the CDARA on March 30.
The subcontractors claimed that the six-year statute of limitations had ended twenty days prior. Shaw claimed that the statute of limitations ran until six years after the architect’s certification, or that the HOA’s suit had tolled all claims.
The trial court granted summary judgment to the subcontractors, determining that “substantial completion occurs ‘when an improvement to real property achieves a degree of completion at which the owner can conveniently utilize the improvement of the purpose it was intended.’”
The appeals court noted that “Shaw correctly points out that the CDARA does not define ‘substantial completion.’” The court argued that Shaw’s interpretation went against the history and intent of the measure. “Historically, a construction professional who received a complaint responded by ‘cross-nam[ing] or add[ing] everybody and anybody who had a part to play in the construction chain.’” The court concluded that the intent of the act was to prevent unnamed subcontractors from being tolled.
The court further rejected Shaw’s reliance on the date of the architect’s certification as the time of “substantial completion,” instead agreeing with the trial court that “the architect’s letter on which Shaw relies certified total completion.”
The appeals court upheld the trial court’s determination that the statute of limitation began to run no later than March 10, 2004 and that Shaw’s complaint of March 29, 2010 was therefore barred. The summary judgment was upheld.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Not In Contract With The Owner? Serve A Notice To Owner.
August 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesA subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights. Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment. Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com