Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
The Indemnification Limitation in Section 725.06 does not apply to Utility Horizontal-Type Projects
February 07, 2018 —
David Adelstein - Florida Construction Legal UpdatesOne of the most important provisions in construction contracts is the indemnification provision. Appreciating contractual indemnification obligations are critical and certainly should not be overlooked. Ever!
Florida Statute s. 725.06 (written about here and here) contains a limitation on contractual indemnification provisions for personal injury or property damage in construction contracts. There should always be an indemnification provision in a construction contract that addresses property damage or personal injury. Always!
Section 725.06 pertains to agreements in connection with “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance, including moving and excavating associated therewith…” If the contract requires the indemnitor (party giving the indemnification) to indemnify the indemnitee (party receiving the indemnification) for the indemnitee’s own negligence, the indemnification provision is unenforceable unless it contains a “monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.” It is important to read the statute when preparing and dealing with a contractual indemnification provision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Aurora Joins other Colorado Cities by Adding a Construction Defect Ordinance
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Aurora Sentinel, the city council of Aurora, Colorado, approved an ordinance targeted at making it more difficult for homeowners to sue builders over construction defect claims.
Similar to other recent Colorado city construction defect measures, “the new rule gives builders the right to repair defects before the litigation is pursued, requires that the majority of home owners in a home owners association – as opposed to just a majority of HOA board members – approve of any lawsuits, and allows builders to offer monetary settlements to homeowners in lieu of repairs.”
Read the court decisionRead the full story...Reprinted courtesy of
Properly Trigger the Performance Bond
January 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesOriginally Published by CDJ on January 5, 2017
A performance bond is a valuable tool designed to guarantee the performance of the principal of the contract made part of the bond. But, it is only a valuable tool if the obligee (entity the bond is designed to benefit) understands that it needs to properly trigger the performance bond if it is looking to the bond (surety) to remedy and pay for a contractual default. If the performance bond is not properly triggered and a suit is brought upon the bond then the obligee could be the one materially breaching the terms of the bond. This means the obligee has no recourse under the performance bond. This is a huge downside when the obligee wanted the security of the performance bond, and reimbursed the bond principal for the premium of the bond, in order to address and remediate a default under the underlying contract.
A recent example of this downside can be found in the Southern District of Florida’s decision in Arch Ins. Co. v. John Moriarty & Associates of Florida, Inc., 2016 WL 7324144 (S.D.Fla. 2016). Here, a general contractor sued a subcontractor’s performance bond surety for an approximate $1M cost overrun associated with the performance of the subcontractor’s subcontract (the contract made part of the subcontractor’s performance bond). The surety moved for summary judgment arguing that the general contractor failed to property trigger the performance bond and, therefore, materially breached the bond. The trial court granted the summary judgment in favor of the performance bond surety. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Supreme Court Grants Petition for Review Regarding Necessary Parties in Lien Foreclosure Actions
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCFor several years, the requirements for which parties must be named in a lien foreclosure action when a release of lien bond is in place have been cloudy. RCW 60.04 et seq., the “mechanics’ lien” or “construction lien” statute, provides protection for a party or person who provides labor, materials, or equipment to a construction project. That person or party, if not paid, can file a lien against the construction project property to secure recovery. As the lien impacts the property by “clouding title” and could potentially result in foreclosure of the property, the statute sets forth strict requirements with respect to timing, notice, and parties. For example, the lien must be recorded within 90 days of the person or party’s last day of work or materials or equipment supplied, and the lien claimant must then give a copy of the claim of lien to the owner or reputed owner within 14 days of the lien recording. RCW 60.04.081.
The statute also allows a property owner or other party to “free” the property from the lien prior to the claim being resolved by issuing a release of lien bond. While the claim is still in dispute, the lien then attaches to the bond and not the property. The same rules about foreclosure, however, still apply but not without some confusion.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
Triggering Duty to Advance Costs Same Standard as Duty to Defend
April 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiInterpreting Hawaii law, the federal district court held that the standard for triggering the duty to defend is the same as the standard for the duty to advance costs under a D&O policy.
Maui Land & Pineapple Co. v. Liberty Ins. Underwriters, 2018 U.S. Dist. LEXIS 56949 (D. Haw. April 3, 2018).
The underlying plaintiffs sued 22 defendants, including Maui Land Pineapple (MLP) and Ryan L. Churchill, concerning a residential development project known as The Ritz-Carlton Club & Residences. The underlying complaint alleged that MLP "directly or indirectly through wholly owned subsidiaries exerts control" over Kapalua Bay, LLC, the defendant in the underlying lawsuit. Kapalua Bay, LLC was created as a joint venture of which MLP held 51%. Churchill was a senior executive officer of MLP, President of Kapalua Bay, and an executive officer of Kapalua Realty, which participated in all aspects of the Project, such as financing, development, and construction.
In their second amended complaint, the underlying plaintiffs alleged nine Counts against the defendants, including breach of fiduciary duty. It was alleged that defendants were not transparent and kept owners in the dark regarding the status of the project. Several allegations named Churchill individually and described his alleged material misrepresentations to the underlying plaintiffs regarding the project's financing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Exploring the Future of Robotic Construction with Dr. Thomas Bock
November 06, 2023 —
Aarni Heiskanen - AEC BusinessIn
this episode of the AEC Business podcast, host Aarni Heiskanen interviews Dr. Thomas Bock, a renowned expert in construction robotics. With 45 years of experience in the field and multiple books on the topic, Thomas shares his insights and expertise.
Tune in to learn more about his professional journey and the advancements in construction robotics.
An unconventional professional journey
Thomas’s journey in construction robotics began when he built his own house as a student. The labor-intensive process led him to explore the potential of robotics in construction. He studied civil engineering and architecture simultaneously, gaining a multidisciplinary understanding of the field. His interest in robotics grew when he saw the first welding robot at a Daimler-Benz factory in Stuttgart. This encounter sparked his curiosity and led him to question why robots couldn’t be used for assembling walls and buildings.
The Illinois Institute of Technology (IIT) in Chicago was one of Thomas’s destinations during his journey. There he studied under professors who had worked on iconic architectural projects. He also learned about Japanese companies like Toyota and Sekisui, which were producing houses using innovative methods. Intrigued by these advancements, Thomas secured a scholarship to study in Japan, where he discovered that the country was ahead of what he had known in the United States.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Coverage for Faulty Workmanship Denied
June 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no coverage for the insureds' alleged negligent failure to construct a building. Evanston Ins. Co. v. DCM Contracting, 2020 U.S. Dist. LEXIS 63977 (N.D. Ga. Feb. 28, 2020).
Turning Point Church sued DCM Contracting for faulty workmanship on a construction project. Turning Point sent a demand letter to DCM on August 18, 2017 and filed suit in December. Evanston did not receive notice of Turning Point's claims and the lawsuit until May 15, 2018.
Evanston filed suit for a declaratory judgment and moved for summary judgment. The court first considered the late notice. The policy required notice "as soon as practicable" DCM was also required to provide copies of demands, notices, or legal papers to Evanston. Here, DCM did not give notice to Evanston until nine months after receipt of Turning Point's demand. A phone communication with DCM's agent between August 2017 and May 2018 was insufficient. DCM provided no documents, including the summons and complaint, to the agent. DCM waited five months to forward the underlying lawsuit. This was a breach of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com