Fourteen Years as a Solo!
July 08, 2024 —
Christopher G. Hill - Construction Law MusingsI have always found it appropriate that my jump to solo practice and Independence Day are so close in time. Today marks 14 years since
my first day as a solo practitioner of construction law at The Law Office of Christopher G. Hill, PC. Time sure has flown by thanks to the great clients and friends who followed me to solo practice and whom I have met since the firm’s founding on July 1, 2010. I also could not have made the transition and had the fun and success I have enjoyed over the past 14 years without the support of the best wife and family that any construction lawyer could want.
Since the firm’s last anniversary, my youngest child (who was 7 when this journey began!) started and completed her junior year at N. C. State University and is currently in Idaho working as an intern for Idaho Fish & Game, my second oldest is an assistant director of admissions at Appalachian State University in Boone, NC, and is newly married, and my oldest has bought a home, adopted an adorable golden retriever puppy, and celebrated her third marriage anniversary. Our home in Captiva, Florida has also continued its recovery from Hurricane Ian.
Professionally, I’ve had a great year. I am serving as the Vice Chair of the
Section Council of the Virginia Bar Association Construction and Public Contracts Law section. I was also honored to be nominated and elected to the
Virginia Legal Elite in Construction Law for the 17th straight year and to the
Virginia Super Lawyers in Construction Litigation for the 8th year running. I also continued to have the opportunity to teach in various construction-related venues on relevant topics and to help out some of the best clients around. I have also continued to grow my
ADR practice, including
arbitration and
mediation.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Unfinished Building Projects Litter Miami
November 18, 2011 —
CDJ STAFFBuildings born in ambitious development plans that were never brought to completion form a grim reminder of the building bust in Miami, according to an article in the Miami Herald. One project started in 2007 as a residential project, later there were hopes to develop it as a hotel. These plans are ten months old with no work done.
Another project was projected as a 30-story office and commercial tower. Four were built before the project was abandoned. The article describes the site as “squalid.” Another project completed the planned 17 stories, but no work has been done beyond constructing the shell. Once planned as luxury condos, the owner owes more than $30,000 in property taxes.
Each of the three sites profiled in the Miami Herald have become dumping grounds for trash. The building skeletons have also become damaged by the elements. Some abandoned projects have been taken over by homeless people. Businesses near the abandoned properties have been hurt. The buildings also represent failed obligations to subcontractors who have put liens on the properties for work they performed but were never paid for.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Proposed Florida Construction Defect Act
January 09, 2015 —
Beverley BevenFlorez-CDJ STAFFMichael J. Furbush and Thomas P. Wert of Roetzel & Andress discussed Florida’s House Bill 87, which proposes to “substantially overhaul Florida’s Construction Defect Act, Chapter 558, requiring property owners to provide more detailed notice of the alleged defect and imposing sanctions on property owners who make frivolous claims.”
Representative Kathleen Passidomo sponsored the bill, which “requires claimants to provide additional details about the alleged defect in the notice of claim, including the specific location of each alleged defect, and the specific provisions of the building code, plans, or specifications that serve as the basis of the defect claim. The failure to include this information in the notice of claim would be considered prima facie evidence of a defective notice.”
Read the court decisionRead the full story...Reprinted courtesy of
NEHRP Recommendations Likely To Improve Seismic Design
November 09, 2020 —
Nadine M. Post - Engineering News-RecordCode-based earthquake engineering is on the verge of getting simpler, thanks to the National Earthquake Hazards Reduction Program’s recommendation to replace the traditional seismic hazard maps with an improved seismic hazards database. The recommendation is one of the most significant changes put forth in the 2020 update of the NEHRP seismic design provisions, which are the foundation for the prescriptive seismic design code for buildings and other structures.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Statutes of Limitations May be the Colorado Contractors’ Friend
April 18, 2011 —
Beverley BevenFlorez CDJ STAFFAlbert Wolf, a principal in Wolf Slatkin & Madison P. C., has written an interesting article on statutes of limitations in construction defect claims in Colorado. While Wolf states that in most cases, “construction defect claims against construction industry participants (contractors, subcontractors, architects, engineers, etc.) requires that suits be started within two years after construction defects have been or should have been—in the exercise of reasonable diligence (care)—discovered,” if a project used the AIA General Conditions (AIA Document A2010) before the 2007 edition, the “statutes of limitations begin to run (accrue) at either substantial completion or breach by the contractor (installation of defective work), depending on the circumstances.”
“That’s a huge difference,” Wolf writes in his article. “For example, if the structural defect caused by faulty foundation work is not discovered or discoverable until walls begin to exhibit cracking more than two years after the building is completed, the owner’s claim against the contractor may be barred if the AIA provision is applied.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Court Finds that Subcontractor Lacks Standing to Appeal Summary Judgment Order Simply Because Subcontractor “Might” Lose at Trial Due to Order
May 03, 2021 —
Garret Murai - California Construction Law BlogCases sometimes take unanticipated twists and turns. Atlas Construction Supply, Inc. v. Swinerton Builders, Case No. D076426 (January 26,2021), involving a tragic construction accident, a motion for summary judgment, a motion for good faith settlement, and a stipulated dismissal, is one of those cases.
The Accident
Swinerton Builders was the general contractor on a residential construction project in San Diego, California. Swinerton contracted with J.R. Construction, Inc. to perform concrete work and with Brewer Crane & Rigging, Inc. to perform crane work on the project. J.R. Construction in turn rented a concrete column formwork approximately 10 feet tall and weighing 300 to 400 pounds from Atlas Construction Supply, Inc.
One day on the construction project, Marcus Develasco, Sr. and another co-worker, employees of J.R. Construction, climbed to the top of the formwork to adjust its size. The formwork, which had been positioned on the site by Brewer, was upright but unsupported by braces. When the co-worker stepped off the formwork, Develasco’s weight caused the unsecured formwork to topple over, killing Develasco in the process.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Insurer’s Duty to Indemnify Not Ripe Until Underlying Lawsuit Against Insured Resolved
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesA liability insurer has two duties: 1) the duty to defend its insured; and 2) the duty to indemnify its insured.
With respect to the second duty – the duty to indemnify – this duty is typically “not ripe for adjudication unless and until the insured or putative insured has been held liable in the underlying action.” Hartford Fire Ins Co. v. Beazer Homes, LLC, 2019 WL 5596237, *2 (M.D.Fla. 2019) (internal quotation omitted).
For instance, Beazer Homes involved an insurance coverage dispute stemming from construction defects. An owner sued its general contractor for construction defects relating to stucco problems. The general contractor paid for the repairs. The general contractor then sued its stucco subcontractor to recover the costs it incurred. The subcontractor tendered the defense of the lawsuit to its commercial general liability insurer which is defending its insured-subcontractor under the commonly issued reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Policy Lanuage Expressly Prohibits Replacement of Undamaged Material to Match Damaged Material
March 09, 2020 —
Tred R. Eyerly - Insurance Law HawaiiConstruing an all-risk Businessowners Policy, the court found that the policy language did not required replacement of undamaged material match materials that were damaged. Pleasure Creek Townhomes Homeowners' Ass'n v. Am. Family Ins. Co., 2019 Minn. App. Unpub. LEXIS 1095 (Minn. Ct. App. Nov. 25, 2019).
The policy covered the Association's 14 townhome buildings. In June 2017, a hail storm damaged siding on all 14 buildings. An appraisal panel included the cost to replace the undamaged, faded siding in its appraisal award so that it would match the new siding. American Family refused to pay this component - which was appraised at about $211,382 - of the award.
An exclusion in the policy provided,
We will not pay to repair or replace undamaged material due to mismatch between undamaged material and new material used to repair or replace damaged material.
We do not cover the loss in value to an property due to mismatch between undamaged material and new material used to repair or replace damaged material.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com