Tennessee Court: Window Openings Too Small, Judgment Too Large
November 18, 2011 —
CDJ STAFFThe Tennessee Court of Appeals has issued a ruling in the case of Dayton v. Ackerman, upholding the decision of the lower court, even as they found that the award was incorrectly computed. The Daytons purchased a house that had been designed and built by the Ackermans, who operated a construction business. The court noted that the warranty with the house promised that “for a period of 60 days, the following items will be free of defects in materials or workmanship: doors (including hardware); windows; electric switches; receptacles; and fixtures; caulking around exterior openings; pluming fixtures; and cabinet work.”
Soon, the Daytons began to experience problems with the house. Many were addressed by the Ackermans, but the Daytons continued to have problems with the windows. Neither side could specify a firm date when the Ackermans were contacted by the Daytons about the window problems. The Ackermans maintained that more than two years passed before the Daytons complained about the windows. The lower court found the Daytons more credible in this.
Initially, the Daytons included the window manufacturer in their suit, but after preliminary investigations, the Daytons dropped Martin Doors from their suit. Martin Doors concluded that the windows were improperly installed, many of them “jammed into openings that were too small for them.”
After the Daytons dismissed Martin Doors, the Ackermans sought to file a third party complaint against them. This was denied by the court, as too much time had elapsed. The Ackermans also noted that not all of the window installations were defective, however, the courts found that the Daytons ought not to have mismatched windows.
Unfortunately for the Daytons, the window repair was done incorrectly and the windows were now too small for the openings. The firm that did the repair discounted the windows and Daytons concealed the problem with plantation shutters, totalling $400 less than the original lowest estimate. However, the appeals court noted that it was here that the trial court made their computation error. Correcting this, the appeals court assessed the Ackermans $12,016.20 instead of $13,016.20.
Finally, the Ackerman’s expert was excluded as he had changed his testimony between deposition and trial. The trial reviewed the expert’s testimony and had it been admissible, it would not have changed the ruling.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
NCCER Celebrates Construction Education Programs and Products in 2024
January 07, 2025 —
The National Center for Construction Education and ResearchALACHUA, Fla., Dec. 30, 2024 (GLOBE NEWSWIRE) --
The National Center for Construction Education and Research (NCCER) released several new or updated educational products in 2024, serving its ongoing mission to provide workforce development solutions for the construction industry and impacting 330,000 people.
NCCER's newest craft training products include a new certification program, multiple curricula updates, new Spanish curriculum translations, and NCCERconnect digital courses and resources.
One of the highlights of the year was the launch of the brand-new
Construction Foreman Certification Program. Helping to fill a significant gap in formal training for frontline supervisors, the program covers critical areas of field leadership such as people management, communication, quality, safety and productivity. The Construction Foreman Certification Program is the latest offering in NCCER's Construction Leadership Series (CLS), which provides turnkey, self-paced online certification solutions for leadership development. The first title in the CLS, the
Construction Superintendent Certification Program, debuted in 2023.
About NCCER – The National Center for Construction Education and Research (NCCER) is an independent 501(c)(3) nonprofit education foundation and the leading provider of construction education for industry and career and technical education programs. With flexible workforce development and learning solutions, NCCER's programs provide consistency and quality to ensure craft professionals and learners receive industry-recognized credentials and certifications. To learn more, visit www.nccer.org.
Read the court decisionRead the full story...Reprinted courtesy of
Toll Brothers Shows how the Affluent Buyer is Driving Up Prices
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFJohn McManus of Big Builder explained how prices per square foot are rising due to an increase in more affluent buyers: “Discretionary buyers—ones with access to cash treasure troves, robust and growing stock portfolios, sovereign wealth in search of anti-inflationary investment, and, for good measure, throw in a smattering of seven-figure income households flush with this year’s bonus payouts—are who, unit by unit, have electrified the housing market’s recovery on the heels of institutional bulk buyers of 2012 and early 2013.”
Toll Brothers, according to McManus, “was, is, and will be the organization most committed to home buying’s discretionary buyer.”
“Thanks to the demand for luxury, and for three- and four-bedroom places, we’re seeing pricing-per-square-foot get better and better the greater number of square feet we offer,” David Von Spreckelsen, Toll Brothers City Living division president, told Big Builder.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized as 2024 New York – Metro Super Lawyers®
November 11, 2024 —
Traub LiebermanTraub Lieberman is pleased to announce that seven Partners from the Hawthorne, NY office have been selected to the 2024 New York - Metro Super Lawyers list.
2024 New York – Metro Super Lawyers
- Copernicus Gaza – Insurance Coverage
- Jonathan Harwood – Professional Liability
- Lisa Rolle – Construction Litigation
- Hillary Raimondi – Employment Litigation
- Christopher Russo – Professional Liability
- Lisa Shrewsberry – Professional Liability
- Stephen Straus – Insurance Coverage
Lisa Shrewsberry was also selected to the Top 25: 2024 Westchester County Super Lawyers® list.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Fourth Circuit Rejects Application of Wrap-Up Exclusion to Additional Insured
December 11, 2018 —
K. Alexandra Byrd & Samantha M. Oliveira - Saxe Doernberger & Vita, P.C.Utilizing an owner-controlled or contractor-controlled insurance program (collectively known as “wrap-ups”) can reduce claims, save costs, and give owners and general contractors comfort in knowing their project is adequately insured. However, problems often arise when a subcontractor doesn’t enroll in the wrap-up and, instead, agrees to provide additional insured coverage to the owner and general contractor on the subcontractor’s own general liability policy. One of those problems is the prevalence of wrap-up exclusions on subcontractors’ general liability policies. If the wrap-up exclusion is too broadly drafted, the exclusion can eliminate coverage for the general contractor and owner even when the subcontractor is not enrolled in the wrap-up.
Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C. and
Samantha M. Oliveira, Saxe Doernberger & Vita, P.C.
Ms. Byrd may be contacted at kab@sdvlaw.com
Mr. Oliveira may be contacted at smm@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Utility Contractor Held Responsible for Damaged Underground Electrical Line
October 11, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLCThe Washington State Court of Appeals recently addressed an excavation contractor’s responsibilities under the Underground Utilities Damage Prevention Act (UUDPA), RCW 19.122. That statute was enacted in 2011 and imposed certain statutory duties on parties involved with projects requiring excavation.
In this case, Titan Earthworks, LLC contracted with the City of Federal Way to perform certain street improvements including installation of a new traffic signal. During the process of excavating for the traffic signal, Titan drilled into an energized underground Puget Sound Energy power line. PSE sought damages from Titan and Titan sued the City of Federal Way.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Park Avenue Is About to Get Something It Hasn’t Seen in 40 Years
February 05, 2015 —
David M. Levitt – BloombergSometime next week, a metal frame will go up around the blocky brick tower at Manhattan’s 425 Park Ave., designed to protect pedestrians from falling objects. It’s a prelude to the building’s demise.
In about three years, if all goes according to plan, the site will have a new Norman Foster-designed skyscraper more than twice the height of the existing one. The replacement would be the first new office building in almost four decades on what the developer, David Levinson, called New York’s “grand boulevard of commerce.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, Bloomberg
Property Insurance Exclusion for Constant or Repeated Leakage of Water
March 14, 2018 —
David Adelstein – Florida Construction Legal UpdatesA
property insurance policy, no different than any insurance policy, contains
exclusions for events that are NOT covered under the terms of the policy. One such common exclusion in a property insurance policy is an exclusion for damages caused by "
constant or repeated seepage or leakage of water…over a period of 14 or more days."
The application of this exclusion was discussed in the recent opinion of
Hicks v. American Integrity Ins. Co. of Florida, 43 Fla. L. Weekly D446a (Fla. 5th DCA 2018). In this case, while the insured was out of town, the water line to his refrigerator started to leak. When the insured return home over a month later, the supply line was discharging almost a thousand gallons of water per day. The insured submitted a property insurance claim. The property insurer engaged a consultant that opined (likely, correctly) that the water line had been leaking for at least five weeks. Based on the above-mentioned exclusion,
i.e., that water had been constantly leaking for over a period of 14 days, the insurer
denied coverage. This denial led to the inevitable coverage dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com