Where Breach of Contract and Tortious Interference Collide
July 18, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hunton Andrews Kurth Promotes Insurance Recovery Lawyer Andrea (Andi) DeField to Partner
April 05, 2021 —
Lorelie S. Masters - Hunton Insurance Recovery BlogEffective April 1, 2021, Hunton Andrews Kurth LLP has promoted insurance recovery lawyer,
Andi DeField, and six other attorneys, to
partner. “Andi has been a superstar in our practice since the day she arrived,” said insurance recovery practice head,
Walter Andrews, adding that “Andi’s promotion reflects the incredible hard work she has contributed to the practice and outstanding results she has achieved for our clients over the years.” A native of Miami, Andi ascended through the ranks at Hunton in its Miami office, joining the firm as a contract lawyer before earning promotions to associate, counsel and, now, partner. But Andi’s rapid ascension did not come without much hard work. Since joining the firm, “Andi has, year after year, consistently knocked the cover off the ball in terms of her tireless work ethic, the superior results she has achieved and her extraordinary aptitude for marketing herself, our practice and the firms many other practices,” said insurance recovery partner,
Mike Levine. Levine added, “Andi is an amazing lawyer and a true champion for her clients. I’m proud to now call her my partner.”
Read the court decisionRead the full story...Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews KurthMs. Masters may be contacted at
lmasters@HuntonAK.com
Another Case Highlighting the Difference Between CGL Policies and Performance Bonds
January 07, 2015 —
David M. McClain – Colorado Construction Litigation During the summer of 2011, Ellis Construction hired Cool Sunshine Heating & Air Conditioning to install the HVAC systems in a single-family home it was building for Gary Doberman and Ellen Robertson in Boulder, Colorado. The homeowners took issue with much of the work performed on their home and tried to negotiate directly with Ellis Construction. When those negotiations broke down, the homeowners sent a notice of claim pursuant to the Construction Defect Action Reform Act, C.R.S. § 13-20-801, et seq. One of the defects alleged in the notice of claim was that the SEERS 13 compressor installed by Cool Sunshine was inappropriate for the system and that because it was installed to run on only one stage, it did not meet the City of Boulder’s code requirements for noise levels. The homeowners therefore requested that the compressor be replaced with a SEERS 20 compressor, which would comply with the Boulder City Code.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Floating Crane on Job in NYC's East River Has a Storied Past of Cold War Intrigue
January 04, 2018 —
Nadine M. Post - Engineering News-RecordOriginally Published by CDJ on March 22, 2017
The complex maneuver of lifting heavy prefabricated modules out of New York City's East River to build a university laboratory took careful planning and the work of one particular floating crane with a complicated past.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Policyholders' Coverage Checklist in Times of Coronavirus
March 16, 2020 —
Richard W. Brown & Andres Avila - Saxe Doernberger & Vita, P.C.Every state but West Virginia have reported hundreds of Coronavirus (COVID-19) cases in the U.S. More than half are in California, Washington, New York, and Massachusetts. The unprecedented social and economic impact of the Coronavirus makes it necessary for policyholders to keep open all lines of communications with their insurance brokers, insurance carriers, financial advisors, safety & compliance experts, and insurance coverage counsel even if it is not certain whether they will need to file insurance claims.
As always, the specific terms of the insurance policies and the way losses are documented and presented to insurance carriers will be pivotal in securing coverage for Coronavirus-related exposures, such as jobsite closures, stop-work orders, remote work mandated measures, business interruption, event cancelation, employees’ claims, among others.
Policyholders should consider the following checklist of key insurance coverage tasks to be better positioned to face the risks posed by the Coronavirus:
- Pre-Loss Risk Management: A careful review of the policyholder’s insurance program may show coverage for the Coronavirus outbreak. Now is the time to assess, with the guidance of your brokers and insurance coverage counsel, the specific coverages in place. Policyholders may want to particularly review the terms and conditions of their Property, General Liability, Pollution, Directors & Officers, Professional Liability, Fiduciary Liability, as well as Event Cancelation Insurance coverages, among others depending on their specific business trade. For instance, Policyholders would want to assess, ahead of time, whether there are bacterial/virus/communicable diseases/pandemics exclusions in their policies. It is also relevant to review, with a keen eye, the insuring agreements and pose hypotheticals to stress test them and see how far coverage would go with respect to a Coronavirus exposure;
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Andres Avila, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Mr. Avila may be contacted at ara@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Massive Redesign Turns Newark Airport Terminal Into a Foodie Theme Park
March 05, 2015 —
Belinda Lanks – BloombergYou wait on what looks like a Soviet bread line. You show your I.D. to a guard. You take off your shoes, empty your pockets, and surrender to a digital scanner.
Fortunately, there’s always a bevy of gleaming cocktail bars and foodie outposts welcoming you to the other side.
No? Get ready. That’s the plan for United Airlines’ Terminal C at Newark Liberty International Airport—a $120 million redesign that includes 55 dining venues with enough celebrity-chef cameos to rival the glitziest of Las Vegas casinos. Instead of the usual McDonald’s, TCBY, and Sbarro, there will be restaurants serving up far-ranging cuisine, from authentic ramen and tacos to gourmet, Neapolitan-style pizza and Swedish meatballs. Since the terminal must remain in operation, all the structures will be assembled off-site and dropped in next year to keep construction time to a minimum.
Read the court decisionRead the full story...Reprinted courtesy of
Belinda Lanks, Bloomberg
Godfather Charged with Insurance Fraud
July 01, 2011 —
CDJ STAFFTexas-based Godfather Construction is a recipient of a fraud suit from the Cook County state attorney’s office. The firm incorporated in Illinois in April 2010, moving there to do business after storms damaged homes in the Chicago suburbs, according to a report in the Chicago Tribune. The state attorney alleges that Godfather brought unlicensed out-of-state workers and the work they performed was “incomplete or shoddy.” Godfather is claimed to have received about $60,000 from Illinois homeowners. The prosecutors are seeking restitution for Godfather’s clients and seek to forbid the firm from doing business in Illinois.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Chutes and Ladders...and Contracts.
November 25, 2024 —
Daniel Lund III - LexologyA contractor which designed and constructed a hydroelectric plant in Guatemala sued under the Federal Arbitration Act in federal court in Florida to overturn a project-related arbitration decision, “on the basis that the Tribunal had exceeded its powers.” That petition was denied based upon Eleventh Circuit precedent which foreclosed that challenge under the FAA for an arbitration conducted “under the Convention on the Recognition and Enforcement of Foreign Arbitral Awards,” a.k.a., the “New York Convention.”
The U. S. 11th Circuit initially affirmed the lower court decision, but then upon an en banc rehearing reversed: holding that in a New York Convention case where the arbitration seat is in the U. S., or where United States law governs the arbitration conduct, “Chapter 1 of the FAA provides the grounds for vacatur of the arbitral award. … § 208 of the FAA provides that ‘Chapter 1 applies to actions and proceedings brought under [Chapter 2] to the extent that chapter is not in conflict with [Chapter 2] or the [New York] Convention as ratified by the United States.’ …Chapter 1 of the FAA… thus acts as a gapfiller and provides the vacatur grounds for an international arbitration award otherwise governed by Chapter 2.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com