Harsh New Time Limits on Construction Defect Claims
April 26, 2011 —
Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq.A recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.
The Statute of Limitations for Construction Defect Claims
Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.
The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.
The Smith Opinion and its Effect on the Statute of Limitations
In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.
The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.
Read the full story…
Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.
Read the court decisionRead the full story...Reprinted courtesy of
Antidiscrimination Clause Required in Public Works and Goods and Services Contracts –Effective January 1, 2024
January 22, 2024 —
Travis Colburn - Ahlers Cressman & SleightIn July 2023, the Washington legislature passed Senate Bill 5186, which mandates inclusion of select antidiscrimination clauses in every state contract and subcontract for public works, goods, or services executed after January 1, 2024.
[i] RCW 49.60.530(3) codifies the now-required antidiscrimination clauses, which prohibit four categories of discrimination against any person because of age, sex, marital status, sexual orientation, gender identity, race, creed, color, national origin, citizenship or immigration status, honorably discharged veteran or military status, the presence of any sensory, mental, or physical disability, or the use of a trained dog guide or service animal by a person with a disability (the “Protected Class”).
Under the new law, public contractors and subcontractors (“Public Contractor”) may not refuse to hire a person because that person is a member of the Protected Class, unless that refusal is based upon a bona fide occupational qualification or if a person with a particular disability would be prevented from properly performing the particular work involved.
[ii] Similarly, Public Contractors may not discharge or bar a person from employment or discriminate against any person – either in terms of compensation or other terms and conditions of employment – because that person is a member of the Protected Class.
[iii] Last, Public Contractors may not print or circulate (or cause to be printed or circulated) any statement, advertisement, publication, form of application for employment, or make inquiry in connection with prospective employment, which expresses any limitation, specification, or discrimination as to the Protected Class.
[iv] Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
United States Supreme Court Upholds Class Action Waivers in Arbitration Agreements
May 24, 2018 —
Amy R. Patton, Jason I. Bluver, & Jeffrey K. Brown - Payne & Fears LLPOn May 21, 2018, the United States Supreme Court held, in a 5-4 decision, that arbitration agreements which mandate individualized resolution of claims (as opposed to class or collective resolution) are enforceable under the Federal Arbitration Act ("FAA"). In doing so, the Court rejected the argument that such "class action waivers" violate Section 7 of the National Labor Relations Act ("NLRA"), which generally protects employees' rights to act "in concert" with one another.
The Court addressed a split created by decisions from three Federal Circuit Courts of Appeal: Epic Systems Corp v. Lewis (7th Circuit), Ernst & Young v. Morris (9th Circuit) and National Labor Relations Board v. Murphy Oil USA (5th Circuit). All three cases involved employees who sought to bring collective or class actions under the Fair Labor Standards Act (the "FLSA"), and their respective employers who sought to enforce pre-dispute arbitration agreements which waived such collective actions and mandated "one-on-one" arbitration of wage disputes. In support of their position, the employees argued that the class and collective action waivers were illegal because they violated the NLRA's prohibition on barring employees from engaging in "concerted activities."
Reprinted courtesy of Payne & Fears LLP attorneys
Amy R. Patton,
Jason I. Bluver and
Jeffrey K. Brown
Ms. Patton may be contacted at arp@paynefears.com
Mr. Bluver may be contacted at jib@paynefears.com
Mr. Brown may be contacted at jkb@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
The Texas Storm – Guidance for Contractors
March 08, 2021 —
Curtis W. Martin & Paulo Flores - Peckar & Abramson, P.C.The Texas snow and ice storm of February 2021 will long be remembered. It has affected everyone across the State, and its impacts continue to be felt a week later. This Alert provides the construction industry with guidance and recommendations for navigating commercial risk resulting from the storm.
The potential impacts to your projects may be wide reaching. Consequences on a project site can include damage to the site, delays to work from the storm or from government orders, or simply the lack of help from trades who are dealing with serious personal catastrophes. Offsite impacts can cover a much broader scope of issues, including supply production issues or transportation interruptions. So, what can contractors facing such impacts do to avoid losses, mitigate the impacts, and prepare for what’s to come?
Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C. and
Paulo Flores, Peckar & Abramson, P.C.
Mr. Martin may be contacted at cmartin@pecklaw.com
Mr. Flores may be contacted at PFlores@Pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Buy America/Buy American, a Primer For Contractors
March 23, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCPresident Trump has promoted his campaign agenda—bringing manufacturing jobs back to the United States (especially jobs relating or pertaining to the steel industry.) To do this, he has strengthened domestic preferences through the Buy America and Buy American Acts.[1]
1. Buy America Act:
The Buy America Act refers to a collection of domestic contract restrictions pertaining to the U.S. Department of Transportation/Federal Highway Administration projects (highway, mass transit and other transportation projects). The USDOT grants provided to state and local governments prohibit the federal government from obligating funds unless the steel, iron and manufactured products used in the projects are produced in the U.S. Generally, Buy America applies to projects where USDOT provides part of the funding, applies to steel, iron and manufactured products, and requires that “all manufacturing processes, including application of a coating, for these materials…occur in the United States.”
- Buy American:
Buy American is critical for construction contractors because FAR 52.225-9 requires that all federal construction contracts under approximately $7 million[2] contain a clause which mandates that contractors use “only domestic construction material in performing [the] contract.” [Note: This requirement is not limited to steel and steel products, as the Buy America Act is.]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Nebraska’s Prompt Pay Act for 2015
January 21, 2015 —
Craig Martin – Construction Contractor AdvisorContinuing with our theme of Ready for 2015, this blog serves as a reminder of your rights and obligations under Nebraska’s Prompt Pay Act, Neb. Rev. Stat. §§ 45-1201-1211.
As you may recall, Nebraska’s legislature amended the Prompt Pay Act in 2014. The most significant changes are highlighted below.
Attorney’s Fees May be Recovered. The most significant change in the Prompt Pay Act allows contractors to recover damages if they pursue a claim under the Act. And, this is not reciprocal in that the defendant may not recover fees.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 —
Beverley BevenFlorez CDJ STAFFIn the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision… Read the court decisionRead the full story...Reprinted courtesy of
“Unwinnable”: Newark Trial Team Obtains Unanimous “No Cause” Verdict in Challenging Matter on Behalf of NYC Mutual Housing Association
May 15, 2023 —
Lewis BrisboisNewark, N.J. (May 8, 2023) – Newark Partner Afsha Noran and New Jersey Managing Partner Colin P. Hackett recently obtained a “no cause” verdict on behalf of multi-unit apartment owners and managers, notwithstanding that the trial judge initially deemed the matter an “unwinnable case” for the defense.
In this matter, Lewis Brisbois represented a large New York City mutual housing association that owned and managed a single multi-unit apartment building in Paterson, New Jersey. The plaintiffs – a mother and her two children – alleged that the housing association failed to maintain the property, which led to defective conditions and mold throughout their apartment. They further contended that the mold caused multiple pulmonary, nasal, and skin injuries. Despite
the shortage of trial judges in New Jersey, this case proceeded to trial, with the plaintiffs’ significant six-figure demand in place.
Over the course of the four-day trial, the plaintiffs presented five witnesses: the plaintiff mother, the plaintiff 18-year-old child, the liability expert, and two medical experts. The client chose not to retain either liability or damages experts to counter those of the plaintiffs. As such, Lewis Brisbois’ trial team was left to defend the matter with an opening statement, a cross-examination of the plaintiffs and their experts, the testimony of the client’s property manager, and a closing argument.
Read the court decisionRead the full story...Reprinted courtesy of