$48 Million Award and Successful Defense of $135 Million Claim
June 04, 2024 —
Peckar & AbramsonPeckar & Abramson is proud to have represented one of the nation’s largest general contractors in the achievement of a $48 million award in its favor and the denial of a $135 million claim against it in Federal Court in the Middle District of Florida on May 3, 2024 arising out of the FDOT’s $2.3 billion reconstruction of I-4, a P3 project and the Department’s largest project ever in the State of Florida.
After a 2-week bench trial, P&A secured the favorable decision which found that the general contractor client was entitled to recover $48 million on its affirmative claim against the party who initiated the lawsuit and that it did not breach its fiduciary duties and was not grossly negligent as was claimed which resulted in a denial of the initiating party’s $135 million claim in its entirety.
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson
How Many Bridges Does the Chesapeake Bay Need?
August 03, 2022 —
Ethan McLeod - BloombergSteve Kline, a 7th-generation Marylander, knows well the vacation tradition of driving across the twin spans of the Chesapeake Bay Bridge for trips to the beach resort of Ocean City. His grandfather, an ironworker, helped build the bridge’s first span, which opened in 1952.
He’s also very familiar with another seasonal rite: wading through the infamous miles-long traffic backups that last from Memorial Day through the end of summer.
But Kline, president of the nonprofit Eastern Shore Land Conservancy, is not on board with the state’s proposed multibillion-dollar fix — a new 4.3-mile-long crossing, to be built alongside the two current spans of the Bay Bridge. In April, the Maryland Transportation Authority (MDTA) announced it had received federal approval to use this route for a potential new, wider bridge that would be likely to eventually replace its older siblings, addressing the notorious summer bottlenecks for decades to come. And on June 10, at a press conference held near the bridge’s eastbound ramp, Maryland Governor Larry Hogan announced that he would commit $28 million in bridge toll revenue to fund the second phase of an environmental impact study on the idea.
Read the court decisionRead the full story...Reprinted courtesy of
Ethan McLeod, Bloomberg
Green Energy Can Complicate Real Estate Foreclosures
November 30, 2016 —
Bob L. Olson – Snell & Wilmer Real Estate Litigation BlogA quick drive through almost any newer residential community in the Southwest will show that a lot of residents are embracing “Green Energy” or renewable energy by placing solar panels on their properties. While most people would agree that increasing the use of alternative energy is socially responsible, there are a number of real estate investors that may view it as an opportunity to make additional profits by purchasing distressed properties with solar panels and then reselling those properties for more than they would be worth without solar panels. The theory is relatively straight forward as many believe that foreclosure of a deed of trust that was recorded before the solar panels were installed would extinguish any liens in favor of the vendor that sold or financed the sale of the solar panels. After all, it is generally held that “a valid foreclosure of a mortgage terminates all interest in the foreclosed real estate that are junior to the mortgage being foreclosed.” See SFR Investments Pool 1, LLC v. U.S. Bank, N.A., 130 Nev. Adv. Op. 75, 334 P.3d 408, 412 (2014) (quoting Restatement (Third) of Property, Mortgages §7.1 (1997)).
NOT SO FAST! While the general rule is that foreclosure of a senior lien terminates junior liens, most purveyors of solar panels do not encumber the property with mortgages or deeds of trust to secure payment of amounts they are owed. Rather, they typically either lease the solar panels to the property owner or secure repayment of the purchase price of the solar panels with a fixture filing under the Uniform Commercial Code (the “UCC”).
Read the court decisionRead the full story...Reprinted courtesy of
Bob L. Olson, Snell & WilmerMr. Olson may be contacted at
bolson@swlaw.com
Sometimes it Depends on “Whose” Hand is in the Cookie Jar
January 21, 2015 —
Roger Hughes – California Construction Law BlogIn a lengthy and somewhat detailed decision, the California Court of Appeal for First District, in Pittsburg Unified School District v. S.J. Amoroso Construction Company, Inc., Case No. A138825 (December 22, 2014), held that a public entity could unilaterally withdraw retention funds during a pending legal dispute without the court first finding that the contractor had defaulted on the public works project.
Background
In 2008, general contractor S.J. Amoroso Construction Company, Inc. (“S.J. Amoroso”) entered into a construction contract with the Pittsburg Unified School District (“District”) for the reconstruction and modernization of a high school in Pittsburg, California.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Traub Lieberman Partner Eric D. Suben Obtains Federal Second Circuit Affirmance of Summary Judgment in Insurer’s Favor
April 10, 2023 —
Eric D. Suben - Traub LiebermanIn the underlying action, a property owner hosting a motorcycle rally was sued after a motorcycle collided with an auto near the entrance to the premises, injuring the cyclists. The cyclists sued the property owner, among others, alleging failure to supervising traffic on the adjoining roadway. The property owner tendered the claim under its CGL policy, which was endorsed with an “absolute auto exclusion,” precluding coverage for claims “arising out of or resulting from the ownership, maintenance, use or entrustment to others of any…auto.” The CGL insurer disclaimed coverage based on the endorsement.
In the ensuing coverage litigation, Traub Lieberman represented the insurer, and moved for summary judgment arguing that the “absolute auto exclusion” was dispositive of coverage on the facts alleged, citing case law from New York state courts enforcing similar exclusions to preclude coverage for multi-vehicle accidents. The insured argued in opposition that the outcome should be controlled by Essex Insurance Company v. Grande Stone Quarry, LLC, 82 A.D.3d 1326, 918 N.Y.S.2d 238 (3rd Dep’t 2011), in which the court declined to apply such exclusion in the case of a single-vehicle accident caused by a dangerous condition of the insured’s premises. The federal district judge disagreed with the insured’s argument in this regard, granting Traub Lieberman’s motion for summary judgment in favor of the insurer.
Read the court decisionRead the full story...Reprinted courtesy of
Eric D. Suben, Traub LiebermanMr. Suben may be contacted at
esuben@tlsslaw.com
Product Liability Alert: “Sophisticated User” Defense Not Available by Showing Existence of a “Sophisticated Intermediary”
November 26, 2014 —
R. Bryan Martin & Kristian B. Moriarty - Haight Brown & Bonesteel LLPIn Gottschall v. Crane Co., (No. A136516, Filed 10/8/2014, published 10/22/2014), the Court of Appeal, First Appellate District, held a company that manufactured and sold asbestos-containing products could not prevail under the “sophisticated user” doctrine based on the contention that a “sophisticated intermediary” existed, in an action brought by the end user of the products.
Decedent Robert Gottschall worked in a variety of shipyards for the U.S. Navy between 1957 and 1989. Defendant Crane Co. (“Crane”) manufactured and sold products containing asbestos to the Navy during that time. During his work at the various shipyards, decedent was exposed to asbestos and contracted mesothelioma.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Court of Appeals Diverges from Damico Opinion, Sending Recent Construction Defects Cases to Arbitration
October 24, 2023 —
Laura Paris Paton - Gordon Rees Construction Law BlogCould the latest opinion from the South Carolina Court of Appeals be the distant ringing of a death knell for runaway construction defects verdicts? On the heels of the Damico ruling earlier this year, the courts have issued several opinions distinguishing various arbitration agreements from the one analyzed in Damico and have sent subsequent cases to arbitration.
This summer, the Supreme Court and Court of Appeals compelled arbitration in Cleo Sanders v. Savannah Highway Automotive Company, et al. Appellate Case No. 2021-000137 / Opinion No. 28168 (petition for rehearing pending) and Joseph Abruzzo v. Bravo Media Productions, et al. Appellate Case No. 2020-001095 / Opinion 6004. Now, in the matter of Jonathan Mart, on behalf of himself and others similarly situated, Respondent, v. Great Southern Homes, Inc., Appellant, Appellate Case No. 2018-001598, the Court of Appeals reversed the circuit court’s order denying a homebuilder’s motion to dismiss and compelled arbitration in this action, which was brought by the homeowner, individually and on behalf of other similarly situated homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
Laura Paris Paton, Gordon Rees Scully MansukhaniMs. Paton may be contacted at
lpaton@grsm.com
Ahlers Distinguished As Top Super Lawyer In Washington And Nine Firm Members Recognized As Super Lawyers Or Rising Stars
August 10, 2020 —
Joshua Lane - Ahlers Cressman & Sleight BlogACS is very honored and pleased to announce nine members of our firm were awarded the distinction of top attorneys in Washington. Our blog articles usually cover Construction Legal News, but we feel this is a newsworthy accolade to be shared with friends and clients.
To become candidates to receiving the Super Lawyer nomination, lawyers are nominated by a peer or identified by research. After completing this first step in the process, Super Lawyer’s research department analyzes 12 indicators, such as experience, honors/awards, verdicts/settlements and others. As for the third step, there is a peer evaluation by practice area. Finally, for step four, candidates are grouped into four firm-size categories. In other words, solo and small firm lawyers are compared only with other solo and small firm lawyers, and large firm lawyers are compared with other large firm lawyers. The process is very selective and only 5 percent of the total lawyers in Washington are nominated as Super Lawyers.
John P. Ahlers, one of the firm’s founding partners, was recognized as the Top Lawyer out of all Washington lawyers in the State. Mr. Ahlers stated that “It was humbling to receive this distinction, particularly considering the many talented Super Lawyers in the State and I am a ‘construction lawyer’ to boot! I am grateful for the confidence my many colleagues in the bar have in me, by honoring me with their vote”.
Founding partner Paul R. Cressman Jr. and partner Brett M. Hill were both recognized as one of the 100-Best Lawyers in the State.
Four other firm members are also recognized as Super Lawyers: Scott R. Sleight, Bruce A. Cohen, Lawrence S. Glosser and Ryan W. Sternoff.
Two other firm members, partner Lindsay (Taft) Watkins and associate Scott D. MacDonald are also recognized as Super Lawyer Rising Stars, which recognizes attorneys either 40 years old or younger, or in practice 10 years or less.
Read the court decisionRead the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & SleightMr. Lane may be contacted at
joshua.lane@acslawyers.com