Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL
May 10, 2012 —
CDJ STAFFThe case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”
The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”
In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”
The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”
Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”
The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”
In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Why Federal and State Agencies are Considering Converting from a “Gallons Consumed” to a “Road Usage” Tax – And What are the Risks to the Consumer?
August 26, 2015 —
Roger Hughes – California Construction Law Blog“‘We’re going to have to find another way to finance the upkeep of the roads,’ Gov. Jerry Brown said earlier this year in rolling out his 2015 budget. Governor Brown gave no specifics, but last fall he signed a law that set up a commission to study a ‘road usage charge’ with a call to ‘establish a pilot program by Jan. 1, 2017…'” – San Jose Mercury News, January 27, 2015
This Change, It’s a Coming (Maybe)
Many states and the federal government are seriously considering converting from a “gallons consumed” tax levy to a “miles driven” program for determining gasoline tax. There are several compelling reasons for such a change. First, our roads are falling apart while revenue from current highway taxes fall woefully short of our current and projected needs. In the meantime, the number of miles driven by all-electric cars that pay no gas tax, is increasing rapidly; and by hybrids that pay substantially reduced tax; and worse for the taxing authorities, by increasingly efficient gas-powered cars. All of this means rapidly dropping gas tax revenues. Seeing this trend, local, state and the federal governments are making a major push to convert from a consumption based tax to a “miles driven” tax. This a good thing for those of us that believe increased investment in our transportation infrastructure is of high national concern.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
How Fort Lauderdale Recovered a Phished $1.2M Police HQ Project Payment
May 13, 2024 —
Richard Korman - Engineering News-RecordJan. 25th was a happy day for the city of Fort Lauderdale, Fla., as Mayor Dean Trentalis and Police Chief William Schultz announced in a press conference the recovery of a $1.162-million electronic payment meant for Moss Construction that had been stolen in September via an email phishing fraud.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Stormy Seas Ahead: 5th Circuit to Review Whether Maritime Law Applies to Offshore Service Contract
July 26, 2017 —
Richard W. Brown & Afua S. Akoto - Saxe Doernberger & Vita, P.C.Earlier this year, the 5th Circuit applied the Davis factors to determine the validity of an indemnity clause in a Master Services Contract. In Larry Doiron Inc. et al., v. Specialty Rental Tool & Supply LLP et al., the court affirmed the notion that if a contract provides services on navigable waters aboard a vessel, a maritime contract exists, even if the contract calls for incidental or insubstantial work unrelated to the use of a vessel. With this decision, plaintiffs were granted indemnification for a crane injury and all was well on the open seas.
The 5th Circuit made waves, however, on July 7, 2017, when it agreed to rehear the case en banc. In its petition for rehearing, defendant STS argued that: (1) the original opinion conflicted with Supreme Court precedent by applying tort law principles to a contract case; (2) the court misapplied the Davis factors and the decision was contrary to Davis because the historical treatment of specialty well service work has been established as non-maritime; (3) the court needed to address whether a contract is subject to maritime or land-based law in the context of offshore mineral exploration.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Afua S. Akoto, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Ms. Akoto may be contacted at asa@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (7/2/24) – Increase in Commercial Property Vacancy Rates, Trouble for the Real Estate Market and Real Estate as a Long-Term Investment
July 31, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the evolution of stadium construction, an increase in legal and legislative action affecting the multifamily sector, and growing concerns for owners of office space.
- The work-from-home trend will likely push up the commercial property vacancy rate in 2026 to a peak average of 24%, or 4 percentage points higher than the first quarter of this year. (Jim Tyson, CFO Dive)
- In recent years, stadium construction has evolved to focus more on cultivating the game day experience with some multibillion-dollar projects breaking ground, as existing venues get renovations. (Zachary Phillips, Construction Dive)
- A number of prominent issues affecting the multifamily industry, including rent control, fees and antitrust concerns, have been subject to increasing levels of legal and legislative action over the past year. (Mary Salmonsen, Multifamily Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Don’t Sign a Contract that Doesn’t Address Covid-19 (Or Pandemics and Epidemics)
December 14, 2020 —
David Adelstein - Florida Construction Legal UpdatesDo yourself a favor: Don’t sign a construction contract that doesn’t address COVID-19 or any pandemic or epidemic from this point forward!
As the number of COVID-19 numbers rise, it would be reasonable to think this could have an impact on ongoing or future construction projects. For this reason, I want to revisit the subject of addressing COVID-19 (and any pandemic or epidemic) in your construction contract.
The potential impact caused by COVID-19 could result from governmental regulations that impact construction of the project, shutdowns due to affected workers, owners’ decisions to suspend performance or adjust the way the project is being constructed, increased deep cleaning requirements, and increased measures associated with social distancing and re-sequencing of shifts. This all plays into the timeliness of performance and the productivity of manpower and equipment usage. When submitting a price, a lot of these considerations may not be factored in because doing so could lead to a price that will never get accepted.
Read the court decisionRead the full story...Reprinted courtesy of