Insureds Survive Motion to Dismiss Civil Authority Claim
September 29, 2021 —
Tred R. Eyerly - Insurance Law HawaiiAfter suffering business losses due to a hurricane, the insured's Civil Authority claim survived the insurer's motion to dismiss. Pathology Lab. v. Mt. Hawley Ins. Co., 2021 U.S. Dist. LEXIS 145129 (W.D. La. Aug. 3, 2021).
Hurricane Laura devastated Lake Charles, Louisiana causing severe damage to the insured property as well as other properties within a mile of the insured property. All seven electrical transmission line corridors feeding Lake Charles were catastrophically damaged causing an extensive power outage. Government shutdown Orders prohibited the insureds' access to the Lab. The Orders were issued by the respective civil authorities both in anticipation of and as a result of damage and dangerous physical conditions expected from and actually resulting from Hurricane Laura and the continuation thereof. When the hurricane arrived, all businesses that were not essential to the recovery were ordered closed until electricity, water and sewer services were restored. As a result, the Lab was closed from August 27, 2020 toSeptember 8, 2020.
The Lab sued for business income under the policy's Civil Authority provisions. Mt. Hawley moved to dismiss. Mt. Hawley argued that the Orders did not by their explicit terms close the Lab's business because closure was entirely dependent on the conditions of the described premises itself and whether it was safe to occupy. Mt. Hawley further argued that the mandatory Evacuation Order was issued in anticipation of property damage and therefore did not trigger coverage under the Civil Authority provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Enforceability of Contract Provisions Extending Liquidated Damages Beyond Substantial Completion
April 15, 2024 —
Stu Richeson - The Dispute ResolverThis post takes a look at the enforceability of contract provisions providing for liquidated delay damages after substantial completion. Typically, the assessment of liquidated delay damages ends at substantial completion of a project. However, various standard form contracts, including some of the ConsensusDocs and EJCDC contracts, contain elections allowing for the parties to agree on the use of liquidated damages for failing to achieve substantial completion, final completion, or project milestones. The standard language in the AIA A201 leaves it up to the parties to define the circumstances under which liquidated damages will be awarded.
Courts are split on the enforceability of provisions that seek to assess liquidated damages beyond substantial completions. Courts in some jurisdictions will not impose liquidated damages after the date of substantial completion on the ground that liquidated damages would otherwise become a penalty if assessed after the owner has put the project to its intended use. Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). When the terms are clear, other jurisdictions will enforce contract terms providing for liquidated damages until final completion, even if the owner has taken beneficial use of the facility. Carrothers Const. Co. v. City of S. Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009).
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
LA Lakers Partially Survive Motion to Dismiss COVID-19 Claims
June 13, 2022 —
Tred R. Eyerly - Insurance Law HawaiiWhile the appellate court affirmed dismissal of a majority of the claims submitted by the Los Angeles Lakers for closure of the Staples Center and other properties due to COVID-19, a portion of their claims survived. L.A. Lakers v. Fed Ins. Co., 2022 U.S. Dist. LEXIS 31503 (C.D. Calif. March 17, 2022).
Government orders closed the Staples Center in March 2020. The Lakers alleged they lost tens of millions of dollars in revenue. They further alleged that the presence of coronavirus particles on fixtures and building systems caused physical alterations to the covered properties. The Lakers had to upgrade their properties to include new air filters, touchless light switches, toilets and sinks; sleeves or coatings for high-touch surfaces; and plexiglass dividers. The Lakers also alleged that five Metro stations within a mile of the Staples Center, that was used to get to games, were closed by civil authorities due to the presence of COVID-19.
The Lakers submitted a claim for property damage and business interruption to Federal. The claim was denied and the Lakers filed suit. In February 2021, the court granted Federal's motion to dismiss without prejudice, after concluding that the Lakers' allegations of direct physical loss or damage were mere legal conclusions and not sufficient to state a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Defects in Roof May Close School
October 21, 2013 —
CDJ STAFFA school in Wales may have to close due to roof leaks. The school was opened six years ago, but since then the leaks at Ysgol Ffynnonbedr are “leading to the deterioration of the structure and fabric of the school.” The Lampeter city council have budgeted £35,000 (about $56,000) for repairs to the roof.
The leaks have already rendered some of the electrical systems and teaching areas unusable. The city council had been in discussion with the builders, Cowlin Construction, when that firm was bought by Balfour Beatty. Balfour Beatty did not comment to the Cambrian Times about resolving the construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Virginia Decision Emphasizes Importance of Naming All Necessary Parties
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFNate Budde on the Construction Payment Blog, discussed the potential of mechanics liens, and the pitfalls that occur when not all necessary parties are named. Budde analyzed the case Johnson Controls Inc. v. Norair Eng’g Corp. that involved a “claimant’s failure to name all the necessary parties in his claim against a bond,” resulting “in the claimant losing his claim against the bond, and with it, an opportunity to get paid.”
Budde concluded, “Unfortunately, as was the case here, when the bond claim is not handled correctly procedurally, a party can be left with no recourse for payment. It’s important to understand which of the parties involved should be named in both mechanics lien claims and bond claims.”
Read the court decisionRead the full story...Reprinted courtesy of
Oregon Condo Owners Make Construction Defect Claim
January 13, 2014 —
CDJ STAFFResidents of two condominiums in Florence, Oregon have filed suits alleging that construction defects have led to water intrusion and damage. The two condominium projects were built by separate developers. Each association has brought its own lawsuit, according to an article in the Register-Guard.
The Bridgeport Landing condominium owners have sued CJ Cable LLC for $2.5 million. Cindy Cable said of lawsuit, “I’ve done everything I could do to get this resolved, and I still get sued.” She said that “the only way to get it corrected is with a lawsuit.”
Meanwhile, residents of the Stillwater Condominiums have sued Thomas Hornback Construction for $2.1 million. Hornback is reported to have denied the allegations made by the Stillwater owners, but says that any problems would be due to subcontractors or failure of the owners to maintain the buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Think Twice Before Hedging A Position Or Defense On A Speculative Event Or Occurrence
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesSometimes, hedging a position on a potential occurrence is not prudent. Stated differently, hedging a position on a contingent event is not the right course of action. The reason being is that a potential occurrence or contingent event is SPECULATIVE. The occurrence or event may not take place and, even if it does take place, the impact is unknown.
An example of hedging a defense on such a potential occurrence or contingent event can be found in a construction dispute involving a federal project out of the Eastern District of Virginia, U.S. f/u/b/o Champco, Inc. v. Arch Insurance Co., 2020 WL 1644565 (E.D.Va. 2020). In this case, the prime contractor hired a subcontractor to perform electrical work, under one subcontract, and install a security system, under a separate subcontract. The subcontractor claimed it was owed money under the two subcontracts and instituted a lawsuit against the prime contractor’s Miller Act payment bond. The prime contractor had issued the subcontractor an approximate $71,000 back-charge for delays. While the subcontractor did not accept the back-charge, it moved for summary judgment claiming that the liability for the back-charge can be resolved at trial as there is still over $300,000 in contract balance that should be paid to it. The prime contractor countered that the delays caused by the subcontractor could be greater than $71,000 based on a negative evaluation in the Contractor Performance Assessment Reporting System (“CPARS”). A negative CPARS rating by the federal government due to the delays caused by the subcontractor would result in a (potential) loss of business with the federal government (i.e., lost profit) to the prime contractor. The main problem for the prime contractor: a negative CPARs rating was entirely speculative as there had not been a negative CPARs rating and, even if there was, the impact a negative rating would have on the prime contractor’s future business with the federal government was unknown. To this point, the district court stated:
In this case, [prime contractor’s] claim for damages is wholly speculative. [Prime contractor] has not produced any evidence that its stated condition precedent—a negative CPARS rating—will actually occur and will have a negative impact on its future federal contracting endeavors. Specifically, [prime contractor] has not identified any facts that indicate that it will be subject to a negative CPARS rating or any indication of the Navy’s dissatisfaction with its work as the prime contractor on the Project… Further, a CPARS rating is only one aspect taken into consideration when federal contracts are awarded. In sum, there is no evidence of the following: (1) a negative CPARS rating issued to [prime contractor]; (2) [prime contractor’s] hypothetical negative rating will be the result of the delay [prime contractor] alleges was caused by [subcontractor]; or (3) [prime contractor’s] hypothetical negative CPARS rating will result in future lost profits.
U.S. f/u/b/o Champco, Inc., supra, at *2 (internal citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
ABC Chapter President Comments on Miami Condo Collapse
July 11, 2021 —
Rachel O'Connell - Construction ExecutivePeter Dyga, ABC Florida East Coast Chapter president, has been one of the go-to experts in the aftermath of the shocking collapse of the Champlain Towers South condo building in Surfside, Florida.
As of publication, the death toll stands at 46 people and another 94 remain unaccounted for. On July 7, rescue officials announced the search would transition to a recovery operation at midnight on July 8, following the demolition of the remaining building over the July 4 weekend.
Dyga sat down with Construction Executive to discuss the critical nature of this tragedy and to review potential next steps.
Construction Executive: This incident has become national news. Why do you think the building collapse has garnered so much attention?
Peter Dyga: Because of the enormity of the tragedy and because it’s so uncommon for a building to collapse on its own.
Reprinted courtesy of
Rachel O'Connell, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of