A Quick Virginia Mechanic’s Lien Timing Refresher
February 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those who read Construction Law Musings on a regular basis know,
mechanic’s liens are a big part of my construction law practice. These
tricky and strictly enforced statutory collection tools are very powerful when correctly recorded and utterly useless if they aren’t recorded in a timely fashion and with the correct information contained within them. Couple that fact with recent
changes to the mechanic’s lien form in 2019, and I feel the need to give a quick refresher.
If you’ve kept up with Musings, you know about the two big numbers for Virginia mechanic’s lien timing, 90 and 150. These should be kept in mind for every general contractor, subcontractor, or supplier on any construction project in Virginia.
Virginia Code Section 43-4 sets out the reasons to keep these numbers in mind. The code section sets out why you need to know these numbers.
The 90 refers to the deadline for recording a lien. This number affects the right to a lien in Virginia. In order to preserve lien rights, a construction contractor must record the lien within ninety days of the last day of the last month in which the last work was performed or no later than ninety days from the date of completion of the project or other termination of work. The short version is that most general contractors on commercial projects have 90 days from the last work in which to record their lien and most subcontractors have 90 days from the last day of the last month of work. However, the best practice is to simply calculate the 90 days from the last work performed or material supplied to avoid issues and arguments between attorneys regarding timing.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Is the Sky Actually Falling (on Green Building)?
November 03, 2016 —
Christopher G. Hill – Construction Law MusingsI have spoken on many occasions here at Construction Law Musings and elsewhere about the risks and rewards for contractors found in sustainable construction. The rewards were fairly apparent. New markets, government incentives and the desires of owners to be “green” clearly point toward a need for contractors to get into the sustainable building game.
However, when I was first writing my Eeyore like thoughts most of the thoughts of all us construction attorneys were speculative. Whether because wholesale “green” construction was relatively new or because the court process was relatively slow, there were not many ways to test if our, shall we say “less optimistic,” predictions were going to come to pass.
For better or worse, several of the more dire predictions have come true. One major green construction debacle is the Destiny USA litigation. I cannot possibly set out all of the various issues as well as my friend and colleague Chris Cheatham does in his e-book about the project and its aftermath. I highly recommend this e-book and the posts found at Chris’ Green Building Law Update blog for those of you interested in how the IRS, the USGBC and the Green Bonds Program interact to cause many a pitfall for construction and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ahlers Distinguished As Top Super Lawyer In Washington And Nine Firm Members Recognized As Super Lawyers Or Rising Stars
August 10, 2020 —
Joshua Lane - Ahlers Cressman & Sleight BlogACS is very honored and pleased to announce nine members of our firm were awarded the distinction of top attorneys in Washington. Our blog articles usually cover Construction Legal News, but we feel this is a newsworthy accolade to be shared with friends and clients.
To become candidates to receiving the Super Lawyer nomination, lawyers are nominated by a peer or identified by research. After completing this first step in the process, Super Lawyer’s research department analyzes 12 indicators, such as experience, honors/awards, verdicts/settlements and others. As for the third step, there is a peer evaluation by practice area. Finally, for step four, candidates are grouped into four firm-size categories. In other words, solo and small firm lawyers are compared only with other solo and small firm lawyers, and large firm lawyers are compared with other large firm lawyers. The process is very selective and only 5 percent of the total lawyers in Washington are nominated as Super Lawyers.
John P. Ahlers, one of the firm’s founding partners, was recognized as the Top Lawyer out of all Washington lawyers in the State. Mr. Ahlers stated that “It was humbling to receive this distinction, particularly considering the many talented Super Lawyers in the State and I am a ‘construction lawyer’ to boot! I am grateful for the confidence my many colleagues in the bar have in me, by honoring me with their vote”.
Founding partner Paul R. Cressman Jr. and partner Brett M. Hill were both recognized as one of the 100-Best Lawyers in the State.
Four other firm members are also recognized as Super Lawyers: Scott R. Sleight, Bruce A. Cohen, Lawrence S. Glosser and Ryan W. Sternoff.
Two other firm members, partner Lindsay (Taft) Watkins and associate Scott D. MacDonald are also recognized as Super Lawyer Rising Stars, which recognizes attorneys either 40 years old or younger, or in practice 10 years or less.
Read the court decisionRead the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & SleightMr. Lane may be contacted at
joshua.lane@acslawyers.com
Oregon Duty to Defend Triggered by Potential Timing of Damage
June 28, 2013 —
CDJ STAFFThe Oregon Supreme Court has concluded that if it is possible that damage could have occurred prior to the completion of the project, then the policies in effect at that time are triggered. John Green of Farella Braun + Martel LLP writes that “we have long argued that, since the duty to defend exists if there is any ‘potential’ of covered liability, there is a potential that damage happened before that project was completed, or at any time after completion, triggering all policies in that time frame.” The Oregon court concluded that if property damage could have happened during construction, the insuerer had a duty to defend and “the insured had no burden to establish any additional facts to support that potential.”
Read the court decisionRead the full story...Reprinted courtesy of
Contractors May be Entitled to Both Prompt Payment Act Relief and Prejudgment Interest for a Cumulative 24%!
August 22, 2022 —
Margarita Kutsin - Ahlers Cressman & SleightThe Washington Prompt Payment Act, in Ch. 39.76 RCW and in RCW 39.04.250, ensures that contractors and subcontractors are promptly paid for their performance on public works contracts. Where a government entity or a prime contractor wrongfully withholds undisputed amounts due, that government entity or prime contractor must pay interest at a rate of 12% per annum.
Separately, prejudgment interest is awarded “based on the principle that a defendant ‘who retains money which he ought to pay to another should be charged interest upon it.’” Hansen v. Rothaus, 107 Wn.2d 468, 472, 730 P.2d 662 (1986) (quoting Prier v. Refrigeration Eng’g Co., 74 Wn.2d 25, 34, 442 P.2d 621 (1968)). The purpose is to “compensate the plaintiff for the use value of the money representing liquidated or determinable damages.” Id.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
New Orleans Drainage System Recognized as Historic Civil Engineering Landmark
May 29, 2023 —
The American Society of Civil EngineersNEW ORLEANS, La. – The
American Society of Civil Engineers (ASCE) today recognized the New Orleans Drainage System in New Orleans, Louisiana as a
Historic Civil Engineering Landmark. The project was innovative and largely unprecedented for its time, and the first portions came online in the year 1900. The system now consists of 22 drainage pumping stations and 1,200 miles of network drains, as well as green infrastructure elements to manage stormwater runoff. The infrastructure is largely credited for making the existence of New Orleans possible, and the improved drainage and reduction in standing water contributed to better public health and reduced the number of malaria and typhoid deaths in the early 20th century.
New Orleans' position near the mouth of the Mississippi River made it a vital city for trade and commerce in the U.S. economy since the early 1800s, despite its problematic natural environment. The city was perched along the banks of the Mississippi River and next to Lake Pontchartrain, surrounded by swamps. Improvements to levee systems prevented the city from being inundated with flooding from the river, but rainfall became a pervasive issue as the city's population grew in the 1870s.
The drainage system was first proposed in 1876 to replace primitive "drainage machines," steam-powered paddle wheels that moved water runoff into canals that led to Lake Pontchartrain. The existing system was inefficient and could not handle the frequent, heavy tropical rain New Orleans experiences and could not lift water sufficiently to drain the city. After several proposals, construction on the current drainage system started in 1897, and the first portions of the system came online in 1900. The system drains stormwater through pipes and canals to reach drainage pump stations which expel the water into several bodies of water surrounding the city. Engineers have repeatedly expanded and enlarged the drainage system, including a massive investment in the drainage system authorized by the Southeast Louisiana Urban Flood Control Project and approved by Congress in 1996. The Sewerage and Water Board's green infrastructure plan is a critical partner and complement to the drainage system today.
The New Orleans Drainage System's design has inspired water management system design in communities around America and worldwide. In Southeastern Florida, water management systems using pumps and canals divert excess water away from heavily populated areas during heavy rain, including tropical storms and hurricanes. Engineers in Kolkata, India and Shanghai, China have also used drainage and pumping systems like the ones in New Orleans to assist with water management.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Rhode Island District Court Dismisses Plaintiff’s Case for Spoliation Due to Potential Unfair Prejudice to Defendant
September 04, 2018 —
Lian Skaf - The Subrogation StrategistIn Amica Mutual Ins. Co. v. BrassCraft Mfg., Co., 2018 U.S. Dist. LEXIS 88986 (D.R.I. May 29, 2018), the United States District Court for the District of Rhode Island addressed the question of whether the defendant was so unfairly prejudiced by the subrogating insurer’s spoliation of evidence that dismissal of the plaintiff’s case was the appropriate Rule 37(b)(2)(a)(i)-(vi) sanction. The court, focusing on the potential for undue prejudice to the defendant, granted the defendant’s motion to dismiss.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams, LLPMr. Skaf may be contacted at