Fourth Circuit Confirms Scope of “Witness Litigation Privilege”
November 21, 2018 —
Anthony B. Cavender - Gravel2GavelOn October 26, in the case of Day v. Johns Hopkins Health Sys. Corp., divided panel of the U.S. Court of Appeals for the Fourth Circuit affirmed the District Court’s ruling that the common law “Witness Litigation Privilege” protects an expert witness in a Black Lung Benefits Act benefits proceeding against civil claims that allege a federal RICO violation and Maryland state law claims for fraud, tortious interference, negligent misrepresentation and unjust enrichment attended the testimony of the expert witness.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Contract Terms Can Impact the Accrual Date For Florida’s Statute of Repose
October 19, 2017 —
William L. Doerler - White and Williams LLPWhen the validity of a construction defect claim depends on whether the claim is barred by the applicable state’s statute of repose, it is important to review the statute to identify when claims subject to the statute of repose accrue. In Busch v. Lennar Homes, LLC, 219 So.3d 93 (Fla. Ct. App. (5th Dist.) 2017), the Court of Appeals of Florida clarified the accrual date for the statute of repose in cases where the accrual date depends on a construction contract’s completion date. Pursuant to Busch, the date of full performance under the contract, not the building’s purchase closing date, is the date on which claims accrue.
In Busch, Timothy Busch (Busch), pursuant to a Purchase and Sale Agreement, contracted to have Lennar Homes build him a house. Nearly ten years after closing on the home, Busch served Lennar Homes with a notice of construction defects, as required by Florida’s right-to-repair act. Shortly thereafter, but more than 10 years after the home’s closing date, Busch filed suit against Lennar Homes, alleging that there were multiple construction defects associated with the home. Lennar Homes, relying on Florida’s statute of repose, Fla. Stat. § 95.11(3)(c), filed a motion to dismiss Busch’s complaint.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Anchoring Abuse: Evolution & Eradication
October 09, 2023 —
Tim Capowski & Chris Theobalt - Kahana FeldOver the past few years, the plaintiff bar has expanded its use of improper anchoring tactics. Historically, improper anchoring was seen as a risky tactic in which a plaintiff’s counsel would suggest an outrageous figure for pain and suffering during summation in the hope that the lay jury would either award it or split the difference (cut the suggested figure by half) and, either way, return an excessive or runaway verdict. Plaintiff counsel deployed the tactic infrequently through the turn of the century for fear of alienating the jury by appearing greedy.
Two interrelated factors happened to change this dynamic. First, the plaintiff bar worked extremely hard in the intervening years with great success to shed its “ambulance chaser” stereotype by marketing itself as the “protector of the vulnerable”. Second, with the rise in Reptile and punitive tactics spawned in part by the publication of the Reptile handbook, the plaintiff bar also discovered that juries were not alienated by outrageous anchors as long as they were preceded by Reptile commentary essentially to “prime” the jury to punish the defendant rather than compensate the plaintiff with its award.
This is not speculation. I recall sitting outside a courtroom with one of New York’s top plaintiff attorneys in 2006 during deliberations on a catastrophic personal injury trial, during which he conceded to me that he was worried he had asked the jury for too large a figure (it was not even eight figures). A decade later in 2016, that same attorney felt no trepidation in requesting nearly $100 million for a comparable injury. He fed the jurors a steady diet of Reptile tactics from start to finish and they dutifully awarded the requested figure. Our research confirms that this two-step strategy (Reptile + improper anchor) preceded every New York nuclear verdict returned from 2010-2022. The same is almost certainly true of most nuclear verdicts in other jurisdictions.
Reprinted courtesy of
Tim Capowski, Kahana Feld and
Chris Theobalt, Kahana Feld
Mr. Capowski may be contacted at tcapowski@kahanafeld.com
Mr. Theobalt may be contacted at ctheobalt@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Developer gets Reprieve in Leasehold Battle
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, a “Manhattan Supreme Court judge granted an injunction in favor of Tribeca Mews developer Thurcon Properties, which is fighting to keep the leasehold on several adjacent parcels in connection with a certificate of occupancy.”
In 2013, Thurcon Properties was sued by the condo board, who claimed “the certificate of occupancy was pushed back at the building due to a number of construction defects.” The Real Deal further reported that the condo board “claimed the developers sold about 10 units to an outside buyer, and took some of the proceeds for themselves.”
Recently, a judge “ordered Feldman Heritage, owner of the ground lease at 125 Church and several adjacent sites, to appear in court on April 30,” because he wants the lease owner “to show why Thurcon should not be given the chance to cure the alleged lease default.”
Read the court decisionRead the full story...Reprinted courtesy of
General Partner Is Not Additional Insured For Construction Defect Claim
August 26, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the project owner's general partner was not an additional insured entitled to a defense and indemnity against claims for construction defects. St. Paul Fire & Marine Ins. Co. v,. Cypress Fairway Condo. Ass'n, 2015 U.S. Dist. LEXIS 94012 (M.D. Fla. July 20, 2015).
Construction of the Cypress Fairway Condominium project took place in 1999 and 2000. Cypress Fairway Ltd. ("Cypress") was the owner and Vineland Partners , LLC ("Vineland") was its general partner. The general contractor was Winter Park Construction Company ("WPC"). Water intrusion and property damage occurred, but it was unclear when or whether the damage was known. Cypress' expert indicated that the damage began shortly after the end of construction.
In 2004, the complex was sold to Cypress Madison Ownership Company. In 2010, the Cypress Fairway Condominium Association sued Cypress and Vineland. Count V of the underlying complaint asserted there were construction defects that Cypress and Vineland were responsible for when they owned and managed the project. Count VI alleged that Cypress and Vineland negligently supplied information which the Association relied on for the purchase of the condominiums.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Buffalo-Area Roof Collapses Threaten Lives, Businesses After Historic Snowfall
December 05, 2022 —
Thomas Leffler - AccuWeatherAfter a historical snowfall event in the Buffalo area this past week, residents weren’t just taking to the driveways and sidewalks to clear snow. In the Buffalo suburb of Orchard Park, New York (home to the NFL’s Buffalo Bills), the 80 inches of snow that accumulated was also cleared off local roofs in order to prevent a major danger to homes.
Snow as deep and heavy as the recent lake-effect snowstorm can cause roofs to collapse, threatening the lives of people who live inside. An unfortunate scenario befell Buffalo in November 2014, when a 6-foot snow event known as “Snowvember” led to emergency calls for numerous collapsed roofs around the region.
One Orchard Park business, Graffiti Grafix & Signs, had its roof collapse in 2014 and had about a third of the roof come down once again this past week, according to The Buffalo News. Orchard Park Police Chief Patrick Fitzgerald noted in an email that three commercial properties in Orchard Park, including Graffiti Grafix & Signs, suffered damage from roof collapse.
Read the court decisionRead the full story...Reprinted courtesy of
AccuWeather
Justin Clark Joins Newmeyer & Dillion’s Walnut Creek Branch as its Newest Associate
May 03, 2017 —
Newmeyer & Dillion LLPWALNUT CREEK, Calif. – APR. 28, 2017 – Up and coming associate and insurance attorney
Justin Clark is the newest associate to join the ever-growing litigation practice at Newmeyer & Dillion LLP’s Walnut Creek office. Clark brings experience in the areas of insurance litigation, construction defect litigation, and business transactions.
Walnut Creek’s managing partner Brian Morrow explained why he is so excited by the addition of Clark: “We are thrilled to have Clark on board, as his emphasis on insurance coverage will assist in a key area for our clients, and further expand our capabilities in our northern California office.”
Clark has a background in a variety of practice areas, including insurance coverage, products liability, and asbestos litigation. He advocates for manufacturers, suppliers, distributers, and contractors in all phases of litigation. Clark represents developers, builders, and general contractors in construction and insurance disputes. He also helps small business clients draft commercial contracts to better serve their growing business needs. Clark can be reached at justin.clark@ndlf.com or 925-988-3263.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Terms of Your Teaming Agreement Matter
July 30, 2019 —
Christopher G. Hill - Construction Law MusingsThese days in construction, and other pursuits, teaming agreements have become a great method for large and small contractors to work together to take advantage of various contract and job requirements from minority participation to veteran ownership. With the proliferation of these agreements, parties must be careful in how they draft the terms of these agreements. Without proper drafting, the parties risk unenforceability of the teaming agreement in the evewnt of a dispute.
One potential pitfall in drafting is an “agreement to agree” or an agreement to negotiate a separate contract in the future. This type of pitfall was illustrated in the case of InDyne Inc. v. Beacon Occupational Health & Safety Services Inc. out of the Eastern District of Virginia. In this case, InDyne and Beacon entered into a teaming agreement that provided that InDyne as Prime would seek to use Beacon, the Sub, in the event that InDyne was awarded a contract using Beacon’s numbers. The teaming agreement further provided:
The agreement shall remain in effect until the first of the following shall occur: … (g) inability of the Prime and the Sub, after negotiating in good faith, to reach agreement on the terms of a subcontract offered by the Prime, in accordance with this agreement.
InDyne was subsequently awarded a contract with the Air Force and shortly thereafter sent a subcontract to Beacon and requested Beacon’s “best and final” pricing. Beacon protested by letter stating that it was only required to act consistently with its original bid pricing. Beacon then returned the subcontract with the original bid pricing and accepting all but a termination for convenience provision. Shortly thereafter, InDyne informed Beacon that InDyne had awarded the subcontract to one of Beacon’s competitors. Beacon of course sued and argued that the teaming agreement required that InDyne award the subcontract to Beacon.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com