Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Zillow Topping Realogy Shows Web Surge for Housing Market
July 30, 2014 —
Prashant Gopal and John Gittelsohn – BloombergZillow Inc. (Z)’s purchase of Trulia Inc. makes the online company such a force in U.S. real estate that its market value now surpasses that of Realogy Corp., owner of renowned brokerage brands from Coldwell Banker to Century 21.
Zillow, the biggest U.S. real estate website, has seen its market value jump to about $5.83 billion from $4.99 billion on July 23, the day before Bloomberg News reported the deal talks with rival Trulia. Realogy, the largest residential brokerage operator, has a market value of about $5.47 billion, compared with $5.67 billion last week, data compiled by Bloomberg show.
The shift underscores the growing role of the Web in U.S. home sales as buyers start their hunt for homes and mortgages online and rely less on real estate agents, a migration that has taken longer than in industries such as music or travel. While Zillow is unlikely to compete directly with brokers, whose ad dollars are its top revenue source, buying Trulia (TRLA) gives it more command over marketing fees, sparking concerns among Realtors such as Stephen FitzMaurice that costs will rise.
Mr. Gopal may be contacted at pgopal2@bloomberg.net; Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal and John Gittelsohn, Bloomberg
Wilke Fleury Celebrates the Addition of Two New Partners
February 18, 2019 —
Wilke FleuryWilke Fleury celebrates the addition of two new partners – Shannon Smith-Crowley and Daniel J. Foster – who complement the firm’s shifting generations of leadership. Shannon and Danny bring unique perspective and excellent capability to Wilke Fleury’s partnership effective January 1, 2019.
Shannon has been a registered lobbyist in California for 20 years. After a career in managed care, she started lobbying with the California Medical Association before founding her own firm, Partners In Advocacy to specialize in medical and reproductive health advocacy. At Wilke Fleury, her areas of practice include health care, women’s equity, life sciences, the biomedical industry, new family formation and emerging technologies in green energy. After a four year tenure with the firm, she has been elevated to the partnership.
Click here to read more about Shannon Smith-Crowley.
Daniel Foster’s litigation practice is composed of matters involving complex construction defect litigation, mechanics liens claims, stop notice actions and Miller Act claims. He represents clients before the Contractors State License Board and handles matters involving breach of warranty, the Song-Beverly Consumer Warranty Act, indemnity agreements and liability insurance coverage.
Click here to read more about Daniel J. Foster Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury
Contract Terms Can Impact the Accrual Date For Florida’s Statute of Repose
October 19, 2017 —
William L. Doerler - White and Williams LLPWhen the validity of a construction defect claim depends on whether the claim is barred by the applicable state’s statute of repose, it is important to review the statute to identify when claims subject to the statute of repose accrue. In Busch v. Lennar Homes, LLC, 219 So.3d 93 (Fla. Ct. App. (5th Dist.) 2017), the Court of Appeals of Florida clarified the accrual date for the statute of repose in cases where the accrual date depends on a construction contract’s completion date. Pursuant to Busch, the date of full performance under the contract, not the building’s purchase closing date, is the date on which claims accrue.
In Busch, Timothy Busch (Busch), pursuant to a Purchase and Sale Agreement, contracted to have Lennar Homes build him a house. Nearly ten years after closing on the home, Busch served Lennar Homes with a notice of construction defects, as required by Florida’s right-to-repair act. Shortly thereafter, but more than 10 years after the home’s closing date, Busch filed suit against Lennar Homes, alleging that there were multiple construction defects associated with the home. Lennar Homes, relying on Florida’s statute of repose, Fla. Stat. § 95.11(3)(c), filed a motion to dismiss Busch’s complaint.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Homebuilders Opposed to Potential Change to Interest on Construction Defect Expenses
January 22, 2013 —
CDJ STAFFIn 2008, the Colorado Supreme Court concluded that in calculating interest on the expense of repairing construction defects would start at the time that the defect was repaired. In 2009, the Colorado State Legislature introduced a bill that would have made homeowners eligible for interest back to the purchase date of their homes. The Colorado Springs Business Journal notes that the Colorado Springs Housing and Building Association is concerned that the legislature might take up the issue again, in which case, the HBA would oppose it.
Read the court decisionRead the full story...Reprinted courtesy of
Seller Cannot Compel Arbitration for Its Role in Construction Defect Case<
March 01, 2012 —
CDJ STAFFThe buyer of a leaky home in Venice, California cannot be compelled to arbitration with the seller in a construction defect lawsuit, according to a decision in Lindemann v. Hume, which was heard in the California Court of Appeals. Lindemann was the trustee of the Schlei Trust which bought the home and then sued the seller and the builder for construction defects.
The initial owner was the Hancock Park Trust, a real estate trust for Nicholas Cage. Richard Hume was the trustee. In 2002, Cage agreed to buy the home which was being built by the Lee Group. Cage transferred the agreement to the Hancock Park Trust. Hancock had Richard Nazarin, a general contractor, conduct a pre-closing walk through. They also engaged an inspector. Before escrow closed, the Lee Group agreed to provide a ten-year warranty “to remedy and repair any and all damage resulting from water infiltration, intrusion, or flooding due to the fact that the door on the second and third floors of the residence at the Property were not originally installed at least one-half inch (1/2”) to one inch (1”) above the adjacent outside patio tile/floor on each of the second and third floors.”
Cage moved in and experienced water intrusion and flooding. The Lee Group was unable to fix the problems. Hume listed the home for sale. The Kamienowiczs went as far as escrow before backing out of the purchase over concerns about water, after the seller’s agent disclosed “a problem with the drainage system that is currently being addressed by the Lee Group.”
The house was subsequently bought by the Schlei Trust. The purchase agreement included an arbitration clause which included an agreement that “any dispute or claim in Law or equity arising between them out of this Agreement or any resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.” The warranty the Lee Group had given to Hancock was transferred to the Schlei trust and Mr. Schlei moved into the home in May 2003.
Lindemann enquired as to whether the work done would prevent future flooding. Nazarin sent Schlei a letter that said that measures had been taken “to prevent that situation from recurring.” In February, 2004, there was flooding and water intrusion. Lindemann filed a lawsuit against the Lee Group and then added the Hancock Park defendants.
The Hancock Park defendants invoked the arbitration clause, arguing that Lindemann’s claims “were only tangentially related to her construction defect causes of action against the Lee Group.” On June 9, 2010, the trial court rejected this claim, ruling that there was a possibility of conflicting rulings on common issues of law. “With respect to both the developer defendants and the seller defendants, the threshold issue is whether there was a problem with the construction of the property in the first instance. If there was no problem with the construction of the property, then there was nothing to fail to disclose.” Later in the ruling, the trial court noted that “the jury could find there was no construction defect on the property, while the arbitration finds there was a construction defect, the sellers knew about it, and the sellers failed to disclose it.” The appeals court noted that while Hancock Park had disclosed the drainage problems to the Kamienowiczs, no such disclosure was made to Sclei.
The appeals court described Hancock Park’s argument that there is no risk of inconsistent rulings as “without merit.” The appeals court said that the issue “is not whether inconsistent rulings are inevitable but whether they are possible if arbitration is ordered.” Further, the court noted that “the Hancock Park defendants and the Lee Group have filed cross-complaints for indemnification against each other, further increasing the risk of inconsistent rulings.”
The court found for Lindemann, awarding her costs.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Additional Insured Coverage Confirmed
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Texas Court of Appeals found that Exxon Mobil Corporation was an additional insured under the CGL policy for Exxon's service provider. Liberty Surplus Ins. Corp. v. Exxon Mobil Corporation, 2015 Tex. App. LEXIS 12757 (Tex. Ct. App. Dec. 17, 2015).
Exxon contracted with Wyatt Field Service Company to perform "services" as set forth in various work orders from Exxon's affiliates. The contract also required Wyatt to maintain $5 million of commercial general liability insurance. The contract provided that the policies must cover Exxon and its affiliates "as additional insureds in connection with the performance of Services."
In 2008, Wyatt was assigned to work on a flexicoker unit at Exxon's refinery. Wyatt was to reinstall dummy nozzles and chains. It completed this service in October 2008. Three years later, one of the dummy nozzles pulled free, and the escaping steam and coke burned three individuals who were working on the unit. After the accident, it was discovered that the safety chain had been installed in the wrong location so that it did not properly secure the dummy nozzle.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
AIA Releases Decennial 2017 Updates to its Contracts Suites
June 29, 2017 —
Garret Murai - California Construction Law BlogThe American Institute of Architect’s (AIA) suite of design and construction documents are among the most popular industry form contracts. Every ten years the AIA reviews and updates its core documents, and early this Spring, announced the release of its updated contract documents.
Among the new changes include:
- Communications Between Owners and Contractors: Expands the ability of owners and contractors to communicate directly while maintaining an architect’s ability to remain informed about communications that affect the architect’s services.
- Owners’ Financial Ability to Pay for Project: Clarifies provisions requiring owner to provide proof it has made financial arrangements to pay for project.
- Contractor Pay Application Requirements: Simplifies provisions for contractors to apply for, and receive, payments.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com