Construction Litigation Roundup: “A Less Than Valiant Effort”
June 21, 2024 —
Daniel Lund III - LexologyA Miller Act claimant in federal court in New Jersey in relation to a VA medical center project found itself on the wrong end of the law and was sent packing by the court.
The claimant had supplied products for the project to general contractor Valiant Group, LLC, pursuant to a purchase order from the GC. The general contractor allegedly refused to pay the supplier, leading to the claim against the GC and its payment bond surety in the amount of $126,900. The supplier also sought recovery under the federal Prompt Payment Act, 31 U.S.C. §§ 3901-07. State law claims were asserted as well.
Chipping away at the federal law claims – the claims forming the asserted basis for federal court jurisdiction for the case – the court first dispensed with the Prompt Payment Act claim. According to the court, allegations that the general contractor had “wrongfully and improperly withheld remuneration… despite [having] ‘received payment from the U.S. Department of Veterans Affairs’" – whether or not accurate – did not trigger the Act. The court wrote:
“The Prompt Payment Act was enacted ‘to provide the federal government with an incentive to pay government contractors on time by requiring agencies to pay penalties . . . on certain overdue bills . . . [and] was later amended to include provisions applicable to subcontractors.’… Absent from the Act, however, are ‘any explicit provisions for subcontractor enforcement if the prime contractor fails to make timely payment.’… This is because the Act ‘merely requires that the prime contractor's contract with the subcontractor include the specified payment clause. [It] does not require the prime contractor to actually make payments to the subcontractor[.]’… The Act, therefore, does not ‘give subcontractors an additional cause of action for an alleged breach by a general contractor of a subcontract.’”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Franchisors Should Consider Signing a Conditional Lease Assignment Rather Than a Franchisee’s Lease
November 17, 2016 —
Richard H. Herold – Real Estate Litigation BlogIn Franchise & High Properties, LLC v. Happy’s Franchise, LLC, a 2015 decision issued by the Court of Appeals in Michigan, the franchisor, Happy’s Pizza Franchise, LLC, signed a five-year lease for the commercial space to be occupied by its franchisee, Happy’s Pizza #19, Inc. The franchisor did so to secure a right of first refusal to purchase the property and to enforce the franchise agreement to have the lease assigned to the franchisor if the franchisee defaulted.
The issue in the case was whether the term “tenant” referred solely to Happy’s Pizza #19 or whether it also included Happy’s Franchise as a co-tenant. “Tenant” was defined as follows: “Happy’s Pizza #19, Inc., 29102 Telegraph Road, Suite 607, Southfield, MI 48034, the lessee, and Happy’s Pizza Franchise, LLC, a Michigan limited liability company (hereinafter referred to as `Franchisor’), hereinafter designated as the Tenant.”
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Real Estate Litigation BlogMr. Herold may be contacted at
rherold@swlaw.com
Recovering Unabsorbed Home Office Overhead Due to Delay
May 30, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the
preceding article, I discussed the use of a retrospective as-built delay analysis in a case before the Civilian Board of Contract Appeals (CBCA). This case also discussed a damages component in certain delay claims known as unabsorbed home office overhead—a challenging damages component to recover because this deals with indirect costs as opposed to direct costs.
Unabsorbed home office overhead is a damages component when the contractor is on standby, but this is NOT as easy as just claiming standby thereby you are automatically entitled to unabsorbed home office overhead. There are requirements that MUST be met.
To obtain an equitable adjustment for unabsorbed home office overhead as compensation for being on standby, [the contractor] must initially show “[1] a government-caused delay of uncertain duration,” that “[2] the delay extended the original time for performance” or precluded the contractor from finishing earlier than scheduled, and that “[3] the contractor [was] on standby and unable to take on other work during the delay period.
CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022) quoting Nicon, Inc. v. U.S., 331 F.3d 878, 883 (Fed. Cir. 2003).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Efficient Proximate Cause Applies to Policy's Collapse Provisions
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court applied the efficient proximate cause doctrine to find coverage under a property policy for a building's collapse. Vardanyan v. Amco Ins. Co., 2015 Cal. App. LEXIS 1181 (Cal. Ct. App. Dec. 11, 2015).
The insured submitted a claim to Amco for damage to the flooring of the house and for mold. Amco's adjustor reported that the house seemed to be settling, possibly due to a water leak. A structural engineer then inspected and found multiple potential leaks in the roof, gutters in disrepair, downspouts that deposited water at the base of the walls of the house, and evidence that a faucet had been spraying the wall in one area. Water damage was noticed in these areas. Further, the kitchen was water damaged and had past termite infestation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indicted Union Representatives Try Again to Revive Enmons
June 22, 2016 —
Wally Zimolong – Supplemental ConditionsThe
Boston Globe reports that the Massachusetts AFL-CIO has filed a friend of the court brief seeking to have the indictment of five members of the Teamsters Union in Boston dismissed. The Teamsters members are facing federal charges that they extorted non-union contractors and owners that employed non-union contractors. The Massachusetts AFL-CIO is arguing that under the Supreme Court’s 1972 decision in
U.S. v. Enmons the Teamsters alleged conduct was in furtherance of a legitimate union objective and, therefore, no illegal.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Supplemental ConditionsMr. Zimolong may be contacted at
wally@zimolonglaw.com
Third Circuit Court of Appeals Concludes “Soup to Nuts” Policy Does Not Include Faulty Workmanship Coverage
December 11, 2018 —
Timothy Carroll - White and Williams LLPEarlier this month, in Frederick Mutual Insurance Company v. Hall, the U.S. Court of Appeals for the Third Circuit concluded that coverage for faulty workmanship claims is “simply not the kind of coverage insurance agents and insurance companies expect to provide” to construction industry professionals “unless the insured explicitly requests such coverage.” 2018 U.S. App. LEXIS 31666, at *9 (3d Cir. Nov. 8, 2018). In Hall, a stone masonry contractor was sued by its customer for causing over $350,000 in property damage resulting from “substandard and defective work” performed on the customer’s residence. The insurer sought a declaration that it owed neither a defense nor indemnity for those damages because, under Pennsylvania law, the policy did not cover property damage caused by faulty workmanship.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy Carroll, White and Williams LLPMr. Carroll may be contacted at
carrollt@whiteandwilliams.com
Multiple Construction Errors Contributed to Mexico Subway Collapse
June 21, 2021 —
Jim Parsons - Engineering News-RecordThe May 3 collapse of an elevated section of the Line 12 subway in Mexico City that killed 26 passengers appears to have resulted from multiple construction faults, according to a risk management firm's preliminary report.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
White House’s New Draft Guidance Limiting NEPA Review of Greenhouse Gas Impacts Is Not So New or Limiting
September 09, 2019 —
Norman F. Carlin & Eric Moorman - Gravel2Gavel Construction & Real Estate Law BlogOn June 21, 2019, the White House Council on Environmental Quality (CEQ) issued draft guidance clarifying the treatment of greenhouse gas (GHG) emissions in environmental impact reviews of federal projects under the National Environmental Policy Act (NEPA). Those wishing to comment on the draft must submit comments within 30 days after it is published in the Federal Register.
The draft guidance is part of the Trump Administration’s continuing efforts to streamline the permitting and environmental review process for infrastructure and energy projects. It replaces NEPA guidance on climate impacts issued in 2016 by the Obama administration, which was rescinded by President Trump’s Executive Order 13783 early in 2017. Although some initial reports suggest that the new draft guidance significantly pulls back from the Obama administration’s approach, on closer comparison it does not depart that much from the major recommendations of the rescinded guidance.
In general, NEPA requires federal agencies proposing to undertake, approve or fund a major federal action to evaluate its environmental impacts, including both direct and reasonably foreseeable indirect effects; to consider alternatives and mitigation; and to discuss cumulative impacts resulting from the incremental effects of the project when added to those of other past, present, and reasonably foreseeable future projects. The new draft and the rescinded 2016 guidance contain similar recommendations regarding an agency’s obligations to consider indirect and cumulative GHG impacts, as well as on the use of cost-benefit analysis and the contentious Social Cost of Carbon (SCC) metric.
Reprinted courtesy of
Norman F. Carlin, Pillsbury and
Eric Moorman, Pillsbury
Mr. Carlin may be contacted at norman.carlin@pillsburylaw.com
Mr. Moorman may be contacted at eric.moorman@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of