Court Says KBR Construction Costs in Iraq were Unreasonable
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFMike Bosse of Bernstein Shur, analyzed a case involving Kellogg Brown and Root Services Inc. (KBR) and the U.S. Army for services that KBR provided during Operation Iraqi Freedom, according to JDSupra Business Advisor: “The court case involved KBR’s construction of dining facility services near Mosul, Iraq under a cost-plus fee arrangement. Under this contractual arrangement, all allowable costs were reimbursed by the government plus the contractor was paid an additional fee.”
KBR first started on a prefabricated metal dining hall that would serve 2,500 people, but part way into building they were told to stop construction and to instead start on a new reinforced concrete building that would serve almost three times as many people.
“After construction was finished, a defense contract auditing agency suspended some of the payments to KBR and instead of the $12.5 million it expected to receive, KBR was paid only $6.7 million,” reported JDSupra Business Advisor. “After trial, the court concluded KBR did not meet its burden to show the costs it incurred were reasonable under the circumstances.”
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Subcontract Requiring Arbitration Outside of Florida
August 07, 2018 —
David Adelstein - Florida Construction Legal UpdatesHave you entered into a subcontract that requires you to arbitrate disputes? If so, does the arbitration provision require you to arbitrate your dispute outside of Florida? If so, the case of Sachse Construction and Development Corp. v. Affirmed Drywall, Corp., 43 Fla. L. Weekly D1622e (Fla. 2d DCA 2018) applies and reinforces the notion: Read and consider what you sign!
In Sachse Construction, a drywall subcontractor entered into a subcontract for a construction project in Miami with an arbitration provision. The subcontract provided that it shall be construed in accordance with Michigan law and required that arbitration shall take pace in Michigan per the Construction Industry Rules of the American Arbitration Association.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
New Jersey Supreme Court Hears Insurers’ Bid to Overturn a $400M Decision
January 25, 2021 —
Lawrence J. Bracken II, Michael S. Levine & Daniel Hentschel - Hunton Andrews KurthNew Jersey’s highest court heard arguments Monday in the appeal of a ruling that the New Jersey Transit Corp.’s (“NJ Transit”) insurers are required to insure $400 million of water damage loss caused by Hurricane Sandy.
The matter stems from an insurance claim NJ Transit made after the super storm rocked the East Coast in 2012. NJ Transit claimed over $400 million in losses as a result of damage to its tracks, bridges, tunnels and power stations. In response, its tower of property insurers took the position that a $100 million flood sublimit applied to limit NJ Transit’s recovery under its insurance tower, not the policy’s $400 million overall limits.NJ Transit filed a coverage action in state court. The trial court granted summary judgment to NJ Transit, holding that NJ Transit was entitled to full coverage of $400 million under the tower’s named windstorm coverage. The insurers appealed, again arguing that the flood sublimit applied to the claim.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Mandatory Attorneys’ Fee Award for Actions Brought Under the Underground Utility Damage Prevention Act
September 22, 2016 —
Lindsay K. Taft – Ahlers & Cressman PLLCIn Washington, RCW 19.122 (the Underground Utility Damage Prevention Act or “Call Before You Dig” statute) provides for the protection of underground utilities. The statute was recently updated in 2013 and provides that homeowners and contractors must call “811” to schedule a “utility locate” prior to commencing any excavation. Failure to do so can result in steep penalties, as well as a mandatory fee award for the prevailing party.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
Eighth Circuit Remands to Determine Applicability of Collapse Exclusion
January 06, 2012 —
Tred R. Eyerly - Insurance Law HawaiiThe Eighth Circuit determined a jury instruction regarding the applicability of the "all-risk" policy’s exclusion for "collapse" was inadequate. See KAAPA Ethanol, LLC v. Affiliated FM Ins. Co., 2011 U.S. App. LEXIS 22158 (8th Cir. Nov. 3, 2011).
KAAPA had nine large, cylindrical, stainless steel tanks fabricated at its location. Soon after operations began in 2003, some of the tanks experienced unusual movement and began to shift. A geotechnical engineer found "silty clay" had been used for infill instead of compacted granular fill called for in engineering drawings. A year long plan to repair all nine tanks was implemented.
Affiliated’s "all-risk" policy excluded damage caused by faulty workmanship. It also excluded damage caused by settling or cracking. The settling exclusion went on to provide, "This exclusion will not apply to loss or damage resulting from collapse of: a building or structure; or material part of a building or structure." Affiliated denied coverage because of the faulty workmanship and settling exclusions.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
The Colorado Supreme Court affirms Woodbridge II’s “Adverse Use” Distinction
December 20, 2021 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogLast year, I posted regarding the Colorado Court of Appeals’ decision in Woodbridge II, which concluded that the “adverse use” element for prescriptive easement claims only requires the claimant to “show a nonpermissive or otherwise unauthorized use of property that interfered with the owner’s property interests.” Viento Blanco, LLC, 2020 COA 34 (Woodbridge II), ¶ 2. Thus, Woodbridge II concluded, the claimants acknowledgement or recognition of an owner’s title alone is insufficient to defeat “adverse use” in the prescriptive easement context. Id. That decision was up for review by the Colorado Supreme Court at the time of my prior post. It has now been affirmed, thereby settling an arguable appellate decision split created by Woodbridge II. See Lo Viento Blanco, LLC v. Woodbridge Condo. Ass’n, Inc., 2021 CO 56 (“Woodbridge”).
“Like the division below, and for much the same reasons,” the Colorado Supreme Court affirmed in Woodbridge “that under Colorado law, a claimant’s acknowledgement or recognition of the owner’s title during the claimant’s asserted prescriptive period does not interrupt the prescriptive use or undermine the claimant’s adverse use.” Woodbridge, ¶ 2. Writing for a unanimous court, Justice Gabriel’s opinion agreed with the Court of Appeals’ reasoning “that although Woodbridge recognized that it did not hold title, no evidence indicated that it had acted in subordination to the owner’s title.” Id. ¶ at 13. The Court further agreed with Woodbridge II’srejection of Lo Viento’s “permissive use” argument because “the permission offered … was conditional and Woodbridge never agreed to any of the conditions set forth therein.” Id. On that basis, Woodbridge confirmed that “a claimant seeking to establish a prescriptive easement need not show that it asserted exclusive ownership of the property during the prescriptive period,” but only “that its use was without permission or otherwise unauthorized and that it interfered with the owner’s property interests.” Id. at ¶ 23.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Pacing in Construction Scheduling Disputes
September 14, 2017 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogOn a high level, construction delay litigation involves sorting out the impacts to the critical project path and determining which party is responsible for those impacts. One of the more difficult elements of this process is determining whether a delay would have occurred regardless of one party’s critical path impact due to a separate, independent impact to the critical path by the other party. For example, a contractor cannot collect delay damages for delays caused by the owner if the contractor itself was causing independent impacts that would have pushed off the completion date anyway.
However, the concept of “pacing” provides a potential defense for a party who is not on pace with the as-planned schedule for noncritical activities, even where those activities are still ongoing after the planned completion date. “Pacing delays” are a type of concurrent delay that occur when one party makes a conscious decision to decelerate or slow down the pace of noncritical activities to keep pace with the critical delays of another party. A more formal definition would be “deceleration of the work of the project, by one of the parties to a contract, due to a delay caused by the other party, so as to maintain steady progress with the revised overall project schedule.” Zack, Pacing Delays–The Practical Effect, Construction Specifier 47, 48 (Jan. 2000). A party to the construction process may decide to slow down its performance of noncritical activities to keep pace with the delayed progress. For example, contractors may adjust the pace of their work in light of delays in owner-furnished equipment, delays by other multiple prime contractors, delays in permits, limited access, or differing site conditions. Owners may slow down their response time to requests for information or submittals, or postpone the delivery of owner-furnished equipment or the processing of change orders. Id. at 48.
Read the court decisionRead the full story...Reprinted courtesy of